Mecsek Hills power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Mecsek Hills power station is a cancelled power station in Mecsek, Baranya, Southern Transdanubia, Hungary. It is also known as Mecsek Hills UCG Project.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Mecsek Hills power station | Mecsek, Baranya, Southern Transdanubia, Hungary | 46.1, 18.083333 (approximate) |
The map below shows the approximate location of the power station.
Project Details
Table 2: Unit-level details
Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|
cancelled | coal: bituminous | 400 | unknown | 2014 |
Table 3: Unit-level ownership and operator details
Owner | Parent |
---|---|
Wildhorse Energy [100%] | Wildhorse Energy [100.0%] |
Background
The project aims to produce synthetic gas (syngas) through the partial in-situ combustion of coal, which will be fed into a power plant to produce electricity.[1]
Wildhorse Energy has coal and coalbed methane exploration license areas covering an area of approximately 420 km² in the Mecsek coal formation of the Pécs region in Southern Hungary. Its website states that, after exploration, "Wildhorse has determined that the Váralja target area [in the Pécs region] is ideally suited for [underground coal gasification] and has been selected as the location for the Company’s first UCG project."[1]
The Project Pre-Feasibility Study was completed in the first quarter of 2012. The study was for a ≥400 MW Project consisting of two phases:[1]
- Phase I – Commercial Demonstration Plant ‐ designed to have a capacity of approximately 130MW of syngas which will be used to supply a 61MW Combined Cycle Gas Turbine (CCGT) power plant, with both the UCG and CCGT facilities expected to be in operation in Q4 2014;
- Phase II – Large Scale Commercial Plant ‐ designed to have a capacity of approximately 280 MW of syngas, with the UCG facility to supply syngas to a potential 130 MW (gross) power plant. The development of this phase will commence after the commissioning of Phase I.
Project cancelled
In October 2014 it was reported that Wildhorse Energy was to exit the Hungarian underground coal gasification sector, as the company’s shares had fallen 85% from the start of the year. The company said it had decided to shut down its Mecsek Hills UCG project in Hungary after failing to sell a part or all of the project to a strategic investor. The shutdown means the company will lose its mineral rights to the project. According to the company: "The value of the Hungarian projects had been progressively written down to nil value by 30 June 2014."[2]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 "Mecsek Hills UCG Project," Wildhorse Energy website, accessed Jan 2013.
- ↑ "Wildhorse Energy exits Hungarian underground coal gasification sector," World Coal, Oct 28, 2014
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.