Menengai 2 geothermal power plant is a geothermal power plant in pre-construction in Nakuru North, Nakuru, Kenya.
Project Details
Table 1: Unit-level project details for Menengai 2 geothermal power plant
Status | Commissioning year | Nameplate capacity | Technology | Owner | Operator |
---|---|---|---|---|---|
Pre-construction[1] | 2025 (planned)[1] | 60 MW[2] | Flash steam - unknown[2] | Geothermal Development Company (GDC) [100%][2] | Geothermal Development Company (GDC)[2] |
Location
Table 2: Unit-level location details for Menengai 2 geothermal power plant
Location | Coordinates (WGS 84) |
---|---|
Nakuru North, Nakuru, Kenya | -0.196, 36.063 (exact) |
The map below shows the exact location of the geothermal power plant:
Articles and Resources
Additional data
To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit the Global Geothermal Power Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 https://web.archive.org/web/20240319062129/https://www.powermag.com/green-light-for-second-geothermal-power-project-in-kenyas-menengai-field/. Archived from the original on 19 March 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 2.3 https://web.archive.org/web/20230209223645/https://www.gdc.co.ke/menengai.html. Archived from the original on 09 February 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help)