Muara Tawar power station is an operating power station of at least 2279-megawatts (MW) in Bekasi, West Java, Indonesia with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Muara Tawar power station Bekasi, West Java, Indonesia -6.0867, 106.9987 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • 1, 2, 3-0, 3-1, 3-2, 3-3, 4-0, 4-1, 4-2, 4-3, 5-1: -6.0867, 106.9987

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Operating[2][3] fossil gas: natural gas[3] 615[4][5] combined cycle[6][4][7] not found 1997[6]
2 Operating[2][8][9][3] fossil gas: natural gas[10] 440[6][5][11][12] combined cycle[6][4][3][13] not found 2022[6][8]
3-0 Construction[2][8][14][3][9] fossil gas: waste heat from natural gas[10] 250[11][12] steam turbine[3][13] not found 2023[8][15]
3-1 Operating[2][5][3] fossil gas: natural gas[3] 140[4] gas turbine[4] not found 2005[4]
3-2 Operating[2][5][3] fossil gas: natural gas[3] 140[4] gas turbine[4] not found 2005[4]
3-3 Operating[2][5][3] fossil gas: natural gas[3] 140[4] gas turbine[4] not found 2005[4]
4-0 Construction[2][8][14][3][9] fossil gas: waste heat from natural gas[10] 250[11][12] steam turbine[3][13] not found 2023[8][15]
4-1 Operating[2][5][3] fossil gas: natural gas[3] 140[4] gas turbine[4] not found 2005[4]
4-2 Operating[2][5][3] fossil gas: natural gas[3] 140[4] gas turbine[4] not found 2005[4]
4-3 Operating[2][5][3] fossil gas: natural gas[3] 140[4] gas turbine[4] not found 2005[4]
5-1 Operating[2][3] fossil gas: natural gas[3] 384[4] combined cycle[4][7] not found 2010[4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
2 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
3-0 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
3-1 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
3-2 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
3-3 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
4-0 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
4-1 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
4-2 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
4-3 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]
5-1 PT PLN Nusantara Power [100%][3] PT PLN (Persero) [100.0%]

Articles and Resources

References

  1. https://web.archive.org/web/20230103182122/https://datasets.wri.org/dataset/globalpowerplantdatabase. Archived from the original on 03 January 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 (PDF) https://web.archive.org/web/20220721024338/https://www.ptpjb.com/wp-content/uploads/2021/08/AR-PJB-2020-1.pdf. Archived from the original (PDF) on 21 July 2022. {{cite web}}: Missing or empty |title= (help)
  3. 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.18 3.19 3.20 3.21 3.22 3.23 3.24 3.25 3.26 3.27 3.28 3.29 3.30 3.31 3.32 https://web.archive.org/web/20220929142449/https://www.ptpjb.com/unit-pembangkitan/. Archived from the original on 29 September 2022. {{cite web}}: Missing or empty |title= (help)
  4. 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 4.18 4.19 4.20 4.21 4.22 4.23 (PDF) https://web.archive.org/web/20221224155135/https://repit.files.wordpress.com/2013/04/gbu-pjb-pltgu-muara-tawar.pdf. Archived from the original (PDF) on 24 December 2022. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.7 (PDF) https://www.plnindonesiapower.co.id/id/komunikasi-berkelanjutan/Reports/STATISTIC%20REPORT%20PT%20INDONESIA%20POWER%20TAHUN%202021.pdf. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 6.2 6.3 6.4 (PDF) https://web.archive.org/web/20221224153843/https://openjicareport.jica.go.jp/pdf/11838976_02.pdf. Archived from the original (PDF) on 24 December 2022. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 https://web.archive.org/web/20230131074729/https://www.reconsult.co.id/ourexperience/detail/pltgu-muara-tawar-add-on-650-mw-block-2-3-4/. Archived from the original on 31 January 2023. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 8.2 8.3 8.4 8.5 https://www.plnnusantarapower.co.id/penyelesaian-proyek-add-on-pltgu-muara-tawar-blok-234-650-mw-memperkuat-kelistrikan-jawa-bali/. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 (PDF) https://web.archive.org/web/20240125050331/https://www.plnnusantarapower.co.id/wp-content/uploads/2023/07/AR-NP-2022_Final.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 10.2 https://web.archive.org/web/20210926024805/http://www.reconsult.co.id/ourexperience/detail/pltgu-muara-tawar-add-on-650-mw-block-2-3-4. Archived from the original on 26 September 2021. {{cite web}}: Missing or empty |title= (help)
  11. 11.0 11.1 11.2 (PDF) https://web.archive.org/web/20220119142241/https://gatrik.esdm.go.id/assets/uploads/download_index/files/3fa53-ruptl-pln-2018-2027.pdf. Archived from the original (PDF) on 19 January 2022. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 12.2 (PDF) https://web.archive.org/web/20211021081234/https://web.pln.co.id/statics/uploads/2021/10/ruptl-2021-2030.pdf. Archived from the original (PDF) on 21 October 2021. {{cite web}}: Missing or empty |title= (help)
  13. 13.0 13.1 13.2 https://web.archive.org/web/20210926024805/http://www.reconsult.co.id/ourexperience/detail/pltgu-muara-tawar-add-on-650-mw-block-2-3-4. Archived from the original on 26 September 2021. {{cite web}}: Missing or empty |title= (help)
  14. 14.0 14.1 https://web.archive.org/web/20210310055229/https://bekasipedia.com/ratusan-buruh-geruduk-kontraktor-pt-pjb-muara-tawar-tuntut-sisa-upah/7771/. Archived from the original on 10 March 2021. {{cite web}}: Missing or empty |title= (help)
  15. 15.0 15.1 https://www.hutamakarya.com/karakteristik-pola-operasi-khusus-pltgu-muara-tawar-sebagai-penanggung-beban-puncak. {{cite web}}: Missing or empty |title= (help)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.