Muarah Laboh geothermal plant is an operating geothermal power plant in Pauh Duo, West Sumatra, Indonesia.

Project Details

Table 1: Unit-level project details for Muarah Laboh geothermal plant

Unit name Status Commissioning year Nameplate capacity Technology Owner Operator
1 Operating[1] 2019[2] 85 MW[3] Flash steam - double[1] Sumitomo CORP [18%]; ENGIE [18%]; PT Supreme Energy [30%]; INPEX Corp [33%] (株式会社INPEX)[3][3][3][1] PT Supreme Energy[3]
2 Construction[2] 75 MW[2] Unknown type Sumitomo CORP [18%]; ENGIE [18%]; PT Supreme Energy [30%]; INPEX Corp [33%] (株式会社INPEX)[3][3][3][3] PT Supreme Energy[3]

Location

Table 2: Unit-level location details for Muarah Laboh geothermal plant

Unit name Location Coordinates (WGS 84)
1 Pauh Duo, West Sumatra, Indonesia -1.6268, 101.1296 (exact)
2 Pauh Duo, West Sumatra, Indonesia -1.6268, 101.1296 (exact)

The map below shows the exact locations of the geothermal power plant units:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit the Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 1.2 https://web.archive.org/web/20221108130549/http://thinkgeoenergy.com/map. Archived from the original on 08 November 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  2. 2.0 2.1 2.2 https://web.archive.org/web/20221203190825/https://www.supreme-energy.com/pt-supreme-energy-muara-laboh. Archived from the original on 03 December 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 https://web.archive.org/web/20221012131114/https://www.thinkgeoenergy.com/japanese-inpex-corp-joins-muara-laboh-geothermal-project-indonesia/. Archived from the original on 12 October 2022. {{cite web}}: Missing or empty |title= (help)