Ningcheng Lihe cogen power station (宁城县立和热电有限公司背压式热电联产集中供热项目) is a power station in the pre-permit stage in Tianyi Town, Ningcheng County, Cifeng, Inner Mongolia, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Ningcheng Lihe cogen power station Tianyi Town, Ningcheng County, Cifeng, Inner Mongolia, China 41.560504, 119.341125 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 pre-permit coal: unknown 30 CFB 2024 (planned)
Unit 2 pre-permit coal: unknown 30 CFB 2024 (planned)
Unit 3 pre-permit coal: unknown 30 CFB 2024 (planned)

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Ningcheng Lihe Thermal Power Co Ltd [100%] Hainan Yuanlong Energy Technology Co Ltd [65.6%]; Dalian Lihe Yinghai Technology Co Ltd [28.5%]; Arhorqin Dingsheng New Energy Co Ltd [5.0%]; other [1.0%]
Unit 2 Ningcheng Lihe Thermal Power Co Ltd [100%] Hainan Yuanlong Energy Technology Co Ltd [65.6%]; Dalian Lihe Yinghai Technology Co Ltd [28.5%]; Arhorqin Dingsheng New Energy Co Ltd [5.0%]; other [1.0%]
Unit 3 Ningcheng Lihe Thermal Power Co Ltd [100%] Hainan Yuanlong Energy Technology Co Ltd [65.6%]; Dalian Lihe Yinghai Technology Co Ltd [28.5%]; Arhorqin Dingsheng New Energy Co Ltd [5.0%]; other [1.0%]

Background

In October 2022, a bidding process for the construction of a 3 x 30 MW power project, the Ningcheng Lihe power station, was announced by Ningcheng County He Thermal Power Co., Ltd. [1] The project was to be built in Tianyi Town Machinery Industrial Park, Ningcheng County, Inner Mongolia and construction was expected to begin in March 2023.[1]

A further bidding process for the construction of the power plant's chimneys was announced in April 2023, at which time construction was expected to take place from May 2023 to September 2024.[2] [3]