Ningxia Xinghua Iron and Steel Co Ltd (宁夏兴华钢铁有限公司) is a blast furnace (BF) announced steel plant in Shizuishan, Ningxia, China.

Location

The map below shows the exact location of the plant in Shizuishan, Ningxia, China:

Loading map...
  • Location: Shizuishan Industrial Park, Huinong District, Shizuishan City, Ningxia Hui Autonomous Region
  • Coordinates (WGS 84): 39.309571, 106.790930 (exact)

Background

The company's equipment upgrade and renovation project has been suspended for environmental impact assessment due to its location being less than 1 kilometer from the Yellow River, posing potential environmental risks.[1]

Plant Details

Table 1: General Plant Details

Plant status Announced date Workforce size
Announced[2] 2019-09[2] 719[3]

Table 2: Ownership and Parent Company Information

Parent company Parent company GEM ID Owner Owner company GEM ID
Fujian Longgang New Materials Co Ltd [100.0%] E100000123261 [100%] Ningxia Xinghua Iron and Steel Co., Ltd.[3] E100000126524

Table 3: Process and Products

Main production equipment Detailed production equipment
BF[2] 1 BOF (1x138-tonne)[2]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status* Basic oxygen furnace steelmaking capacity Nominal crude steel capacity (total)
announced 1500 TTPA[2] 1500 TTPA[2]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status* Blast furnace capacity Nominal iron capacity (total)
announced 1370 TTPA[2] 1370 TTPA[2]

Blast Furnace Details

Table 6: Blast Furnace Details

Unit name Status Announced date Construction date Start date Current size Current capacity (ttpa) Decarbonization technology Most recent relining
unknown announced[2] 2019-09[2] unknown unknown 1580 m³[2] 1370[2] unknown unknown

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. "关于暂停办理宁夏兴华钢铁有限公司 装备升级改造循环经济产业链项目 环境影响评价事宜的函". 宁夏回族自治区生态环境厅. 2022-08-17. {{cite news}}: line feed character in |title= at position 17 (help)
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 https://factory.mysteel.com/19/0911/17/4570C877E28EA6E1.html. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://web.archive.org/web/20220318140230/https://www.qcc.com/weblogin?back. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)

Resources