Nishat Rahim Yar Khan power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Nishat Rahim Yar Khan power station is a cancelled power station in Liaqatpur, Rahim Yar Khan, Punjab province, Pakistan.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Nishat Rahim Yar Khan power station Liaqatpur, Rahim Yar Khan, Punjab province, Pakistan 28.935, 70.941 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Status Fuel(s) Capacity (MW) Technology
cancelled coal: unknown 660 supercritical

Table 3: Unit-level ownership and operator details

Owner Parent
Nishat Energy Ltd [100%] TBEA Co Ltd [70.0%]; Nishat Group [30.0%]

Project-level coal details

  • Coal source(s): imported

Background

In December 2016, the Nishat Group announced that it would be working together with Chinese company TBEA Xinjiang Sun Oasis Company (a subsidiary of Chinese firm TBEA) to build a single-unit, 660-MW coal-fired power plant in the Liaqatpur tehsil of Rahim Yar Khan district in Punjab. The plant would run on imported coal, and was slated for completion by the fourth quarter of 2020. It would cost $956 million, and would be included under the China-Pakistan Economic Corridor (CPEC). The Punjab Power Development Board had approved the consortium, a letter of intent had been obtained from the Chinese Development Bank, and a feasibility study was underway. Nishat had also hired ENERGEN Infra (Mauritius) Limited to act as an advisor in choosing a Chinese firm for the plant's engineering, procurement, and construction (EPC) contract.[1][2]

In July 2016, the ministry asked the Private Power and Infrastructure Board (PPIB) to stop issuing Letter of Intent to new imported fuel-based power plants except for the projects mutually agreed upon by Pakistan and China or those listed in the CPEC programme. It was predicted the move would harm or halt three 660-megawatt projects, including the proposed Nishat Rahim Yar Khan power station. In 2017, the government signaled it wanted to restart work on an imported coal-fired power project in Rahim Yar Khan and place it on the CPEC list, but this appeared focused on the separate Rahim Yar Khan power station.[3]

In November 2017, the Pakistan National Electric Power and Regulatory Authority (NEPRA) rejected the application of Nishat Energy Limited for a generation license for its proposed 660 MW imported coal power plant in Rahim Yar Khan.[4]

It is unclear if Nishat Energy continued to pursue the project or not. Given the lack of known progress since late 2016, the project appears to be shelved or abandoned.

Pakistan’s Indicative Generation Capacity Expansion Plan 2021-30 approved by the National Electric Power Regulatory Authority in September 2021 listed "Rahim Yar khan Imported Coal Based Power Plant (660 MW)" under its "New Generation Options" as a candidate generation technology "selected to be fed into the model." The project was not listed as a "committed" project.[5]

Articles and Resources

References

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.