Nizhnekamsk Petrochemical power station
Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
Related categories: |
Nizhnekamsk Petrochemical power station (ПГУ-ТЭС ПАО "Нижнекамскнефтехим", НКНХ, Лемаевская ПГУ) is an operating power station of at least 495-megawatts (MW) in Nizhnekamsk, Republic of Tatarstan, Russia. It is also known as NKNH, Lemayevskaya power plant.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Nizhnekamsk Petrochemical power station | Nizhnekamsk, Republic of Tatarstan, Russia | 55.576002, 51.924953 (exact)[1] |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- 1-1: 55.576002, 51.924953
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year |
---|---|---|---|---|---|---|
1-1 | Operating[2][3][4][5][6][7][8] | fossil gas: natural gas, fossil gas: unknown[3][9][10] | 495[11] | combined cycle[12] | no[13] | 2022[2][10][14][15][8] |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
1-1 | Nizhnekamskneftekhim PJSC [100%][3] | SIBUR Holding PJSC [100.0%] |
Project-level captive use details
- Captive industry use (heat or power): power[13][16][4]
- Captive industry: Oil & Refining[13][16][4]
- Non-industry use: none[13][16][4]
Background
The petrochemical plant Nizhnekamskneftekhim (Нижнекамскнефтехим) relies on heat and electricity generated by Nizhnekamsk 1 power station that is located at the same site as the plant, as well as on its own source of electricity, provided by a gas turbine block with generating capacity of 75 MW, consisting of three turbine units 25 MW each.[17] This turbine block was commissioned in 2007.[18]
In 2017, the company has signed a contract with Siemens AG for the construction of a new combined cycle unit with capacity of 495 MW.[19] In December 2021, construction was complete; in August 2021, the two gas turbines were tested out and synchronized with the electrical grid.[20] In March 2022, work was carried out to further test and set up the equipment.[21] It was reported that as of October 2022, the unit was still in test mode and not officially commissioned.[22] In October 2022, Rostekhnadzor (Russian federal Service for Environmental, Technological and Nuclear Supervision), following an inspection, issued a conclusion on the compliance of the constructed facility with the requirements of the design documentation. This is usually one of the final stages before the official launch of the generation facility into commercial operation.[23] In 2022, Siemens stopped its operations in Russia due to the sanctions, and SIBUR had to independently carry out the commissioning of the power station.[24]
According to the Russian Ministry of Energy 2023-2028 energy plan, released in February 2023, the unit was commissioned in July 2022.[25] The launch of the combined-cycle power plant marked the largest addition of new generation capacity not only in Tatarstan but also in the entire Russia.[26]
Articles and Resources
References
- ↑ https://www.google.com/maps/place/55%C2%B034'33.6%22N+51%C2%B055'29.8%22E/@55.576005,51.9227643,632m/data=!3m2!1e3!4b1!4m6!3m5!1s0x0:0x0!7e2!8m2!3d55.5760024!4d51.9249532.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 (PDF) https://web.archive.org/web/20230313035117/https://www.so-ups.ru/fileadmin/files/company/future_plan/public_discussion/2023/final/55_Respublika_Tatarstan_fin.pdf. Archived from the original (PDF) on 13 March 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 3.2 https://web.archive.org/web/20221208003733/https://www.power-technology.com/projects/nizhnekamsk-combined-cycle-power-plant/. Archived from the original on 08 December 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 4.0 4.1 4.2 4.3 https://web.archive.org/web/20211222141514/https://www.tatar-inform.ru/news/zaryazennye-na-uspex-energetiki-niznekamskneftexima-planiruyut-vvod-novyx-moshhnostei-5847890. Archived from the original on 22 December 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220602062225/https://www.nknh.ru/pressroom/news/na-lemaevskoy-pgu-vpervye-dostignuta-moshchnost-500-mvt/. Archived from the original on 02 June 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20221014052714/https://www.tatar-inform.ru/news/rost-potrebleniya-elektroenergii-v-tatarstane-v-sentyabre-sostavil-17-5882453. Archived from the original on 14 October 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230111183335/https://www.tatar-inform.ru/news/tgk-16-novye-pgu-tes-na-nknx-i-kos-budut-obespecivat-potreblenie-kombinatov-5888103. Archived from the original on 11 January 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 https://web.archive.org/web/20221220050645/https://www.business-gazeta.ru/amp/576865. Archived from the original on 20 December 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://energybase.ru/news/companies/simens-i-gruppa-kompanij-taif-podpisali-kontrakt-na-stroitelstvo-elektrostancii--2017-12-18.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 https://web.archive.org/web/20230106060809/https://www.enka.com/ru/portfolio-item/nizhnekamsk-495-mw-combined-cycle-power-plant/. Archived from the original on 06 January 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20210922213703/https://www.hamon.com/press-releases/nizhnekamsk-natural-draft-cooling-tower.html. Archived from the original on 22 September 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20210922223312/https://www.enka.com/portfolio-item/nizhnekamsk-495-mw-combined-cycle-power-plant/. Archived from the original on 22 September 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 13.2 13.3 https://web.archive.org/web/20221205212800/https://www.so-ups.ru/odu-volga/odu-volga-zone/znachimye-ehnergoobekty/lemaevskaja-pgu/. Archived from the original on 05 December 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20221130155326/https://www.garant.ru/products/ipo/prime/doc/404487690/. Archived from the original on 30 November 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220303203139/http://tass.com/economy/981714. Archived from the original on 03 March 2022.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 16.0 16.1 16.2 https://web.archive.org/web/20230509151314/https://www.tatar-inform.ru/news/opadcii-lemaevskaya-pgu-na-nknx-budet-rabotat-na-roznicnom-rynke-5896717. Archived from the original on 09 May 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ "Нижнекамскнефтехим". Wikipedia (Russian). Retrieved Apr 20, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "«Нижнекамскнефтехим» ввел собственную генерирующую установку". Kommersant.ru. Aug 2, 2007. Retrieved Apr 20, 2022.
- ↑ "ПАО «Нижнекамскнефтехим» подписало контракт с компанией «Siemens AG» на строительство парогазовой установки (ПГУ-ТЭС) мощностью 495 МВт". NKNH.ru. Dec 18, 2017. Retrieved Apr 20, 2022.
- ↑ "Заряженные на успех: энергетики «Нижнекамскнефтехима» планируют ввод новых мощностей". Tatar-inform.ru. Dec 22, 2021. Retrieved Apr 20, 2022.
- ↑ "На Лемаевской ПГУ впервые достигнута мощность 500 МВт". NKNH.ru. Mar 9, 2022. Retrieved Apr 20, 2022.
- ↑ "Потребление электроэнергии в Татарстане в сентябре выросло на 1,7%". Tatar-inform.ru. Oct 7, 2022. Retrieved Oct 28, 2022.
- ↑ "Ростехнадзор разрешил ввести электростанцию на «Нижнекамскнефтехиме»". Tatar-inform.ru. Oct 25, 2022. Retrieved Oct 28, 2022.
- ↑ "«Катастрофы не будет»: почему уход Gеneral Electric не остановит ТЭЦ в Казани?". https://www.tatar-inform.ru/. June 26, 2023. Retrieved November 21, 2023.
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|website=
- ↑ "СХЕМА И ПРОГРАММА РАЗВИТИЯ ЭЛЕКТРОЭНЕРГЕТИЧЕСКИХ СИСТЕМ РОССИИ НА 2023–2028 ГОДЫ РЕСПУБЛИКА ТАТАРСТАН" (PDF). SO UPS of Russia. February 28, 2022. Retrieved November 21, 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Опадчий: Лемаевская ПГУ «Нижнекамскнефтехима» будет работать на розничном рынке Подробнее: https://www.tatar-inform.ru/news/opadcii-lemaevskaya-pgu-na-nknx-budet-rabotat-na-roznicnom-rynke-5896717". www.tatar-inform.ru. February 16, 2023. Retrieved November 21, 2023.
{{cite web}}
: External link in
(help); line feed character in|title=
|title=
at position 80 (help)CS1 maint: url-status (link)
Additional data