Oświęcim-Tworzen Gas Pipeline
From Global Energy Monitor
Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Related categories: |
Oświęcim-Tworzen Gas Pipeline is a proposed gas pipeline in Poland.[1]
Location
The pipeline will be routed through the Silesian and Lesser Poland Voivodeships. The gas pipeline will be routed through the territories of the following municipalities: Sławków, Bukowno, Jaworzno, Chrzanów, Libiąż, Chełmek and Oświęcim.[2]
Pipeline Details
- Operator: Gaz-System
- Owner: Gaz-System
- Parent: Gaz-System
- Proposed Capacity:
- Length: 44 km / 28 miles[2]
- Diameter: 700 mm[2]
- Cost: €44 million (US$50.16 million)[3]
- Status: Proposed
- Start Year: 2024[4]
Background
The pipeline was proposed in January 2019 and Gaz-System expects to begin construction in early 2021.[1]
As of August 2021, Gaz-System states that obtaining permission for the construction of the gas pipeline is planned for the third quarter of 2021.[2] However, an updated project description in 2022 pushes the commissioning of the pipeline to 2024, with construction yet to begin.[4]
Articles and resources
References
- ↑ 1.0 1.1 Oświęcim-Tworzen Pipeline, Gaz-System, accessed August 2020
- ↑ 2.0 2.1 2.2 2.3 "GAZ-SYSTEM S.A.: Oświęcim-Tworzeń". en.gaz-system.pl. Retrieved 2021-08-24.
- ↑ "BEMIP Gas Regional Investment Plan - Annex : Infrastructure Projects" (PDF). ENTSOG. 2012. Retrieved November 30, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 4.0 4.1 www.gaz-system.pl https://www.gaz-system.pl/en/transmission-system/investment-projects/other-major-investment-projects/oswiecim-tworzen.html. Retrieved 2022-07-14.
{{cite web}}
: Missing or empty|title=
(help)