Oil and Gas Pipeline Construction Costs
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Summary
The following are ranges for pipeline cost estimates. For further discussion, see below:
- Oil & Gas Journal 2015-2016: $4.75 million/km (US onshore gas)
- Oil & Gas Journal 2014-2015: $3.23 million/km (US onshore gas)
- American Petroleum Institute 2017: $3.32 million/km (US onshore gas, national average)
- Global Fossil Infrastructure Tracker median for 64 onshore and offshore projects: $2.34 million/km (date unspecified, worldwide)
Background
There are four categories of pipeline construction costs; material, labor, miscellaneous, and right-of-way (ROW). The cost per category, expressed as a percentage of total construction costs, tends to vary by both location and year. Materials may include line pipe, pipe coating, and cathodic protection. Miscellaneous costs generally cover surveying, engineering, supervision, contingencies, telecommunications equipment, freight, taxes, allowances for funds used during construction (AFUDC), administration and overheads, and regulatory filing fees. ROW costs include obtaining rights-of-way and allowing for damages.[1]
Current Trends
Pipelines built in 2015 and 2016 were historically expensive, as determined by the costs for new projects as filed by operators with FERC, according to an Oil & Gas Journal analysis. For proposed onshore US gas pipeline projects in 2015-16, the average cost was $7.65 million/mile ($4.75 million/km), up from both the 2014-15 average cost of $5.2 million/mile ($3.23 million/km) and the 2013-14 average cost of $6.6 million/mile ($4.10 million/km). In 2012-13 the average cost was $4.1 million/mile ($2.55 million/km) as compared with $3.1 million/mile ($1.93 million/km) in 2011-12; $4.4 million/mile ($2.73 million/km) in 2010-11; $5.1 million/mile ($3.17 million/km) in 2009-10; and $3.7 million/mile ($2.30 million/km) in 2008-09.[1]
For the 33 land spreads filed for in 2015-16, cost-per-mile projections rose in all categories except material. In 2011 miscellaneous charges passed material to become the second most expensive cost category and they retained this position through 2016. Material-$992,991/mile, down from $1,012,698/mile 2014-15. Labor-$3,603,334/mile, up from $1,977,938/mile for 2014-15. Miscellaneous-$2,615,028/mile, up from $1,867,393/mile for 2014-15. ROW and damages-$441,548/mile, up from $378,255/mile for 2014-15. The continued rise in miscellaneous costs is driven by companies increasing the amount set aside for contingencies in their estimates.[1]
Labor spiked as a portion of land construction costs, reinforcing its place as the single most expensive category. Labor's portion of estimated costs for land pipelines jumped to 47.08% in 2016 from 37.77% in 2015, 42.36% in 2014, 38.84% in 2013, 44.61% in 2012, 44.27% in 2011, and 44.61% in 2010. Material costs for land pipelines, meanwhile, eased to 12.98% from 19.34% in 2015, 13.6% in 2014, 23.2% in 2013, 15.99% in 2012, and 14.54% in 2011.[1]
Average Pipeline Size
Pipeline cost is often estimated per inch-mile. According to NaturalGas.org, the average diameter of an interstate pipeline is between 24 inches and 36 inches, or an average of 30 inches.[2]
Offshore versus Onshore
According to USAID, offshore costs per mile for pipelines were about 1.96 times as high as costs per mile for onshore pipelines in 2000-2001, in 1995-1996 the cost ratio was 1.79.[3]
Gazprom Costs
An analysis of Gazprom offshore construction costs found the following:[4]
- Nord Stream - €3.4 million/km
- South Stream - €2.7 million/km
- Dzhubga-Sochi - >€5.0 million/km
BTU Analytics Survey or U.S. Northeast and Central U.S. Pipelines
A survey by BTU analytics of 9 gas pipelines in the U.S. Northeast found a range of $5.5 million - $13.14 million per mile, with a median of $8.45 million/mile, or $5.25 million/km. The pipelines were onshore and ranged from 118 to 600 miles length. The pipelines were built from 2017 to 2020. The analysis also cited two pipelines in the Great Plaints and West Texas/Gulf Coast regions. Those pipelines included a pipeline built in 2009 that cost $2.98 million/mile in 2009 dollars, and two pipelines that cost $3.51 million and $5.15 million per mile respectively in 2019.[5]
American Petroleum Institute 2017 Estimate
In its study of infrastructure through 2035, the API estimated average U.S. pipeline costs of $178,000 per inch-mile for 2016 (in nominal dollars) for large gas transmission pipelines. Combined with the estimate of 30 inches for average pipeline size, that amounts to $5.34 million per mile for gas pipelines, or $3.32 million per km. The API also estimate regional costs multipliers:[6]
- Central - 0.65
- Midwest - 1.20
- Northeast - 1.68
- Offshore - 1.00
- Southeast - 0.80
- Southwest - 0.74
- Western - 0.94
Estimating Construction Costs
The average cost-per-mile for the projects rarely shows consistent trends related to either length or geographic area. In general, however, the cost-per-mile within a given diameter decreases as the number of miles rises, suggesting that fewer and longer pipelines are more cost efficient. Lines built nearer populated areas tend to have higher unit costs. Additionally, road, highway, river, or channel crossings and marshy or rocky terrain each strongly affect pipeline construction costs.[1]
A 2011 study published in the Journal of Oil, Gas, and Coal Technology identified the variability within the four main cost categories. The percentage share of material cost of pipeline construction increased when pipeline diameter increased. In term of pipeline lengths, the share of material cost rose from 28% for short pipelines to 35% for long pipelines, with share of the other cost components decreasing except ROW, which was constant at 7% regardless of the total pipeline length. Therefore, the share of material cost increased when pipeline diameter and length increased, but the labour cost maintained as the primary cost component for all diameters and lengths, averaging 40% of total cost. The shares of cost components were also different for different regions in the United States. The material cost in the Central region made up around 41% of the total cost, while it was only 24% of the total cost in the Northeast and Southeast regions. The share of labour cost is between 34% and 48% in different regions. This may be influenced by differing costs of living by region. Miscellaneous cost was often a small part of the total cost, but the share of miscellaneous cost in the Southeast region reached to 30% of the total cost, even higher than share of material cost. The share of ROW cost of US pipelines ranged from 4% to 12% of total cost, while the share of ROW cost in Canada share was only 1% of total cost. The share of material cost and labour cost were approximately the same for Canadian pipelines, about 40%. The results agree with the conclusion that the shares of costs vary by countries and categories.[7]
Stranded Assets
Stranded assets refers to the amount of fossil fuel reservers that would have to remain in the ground, or fossil fuel infrastructure that wold have to remain unused at some point prior to providing a return on the investment, if the world were to transition to non-fossil fuel energy sources. For example, according to a 2015 study in Nature, an estimated 33% of oil reserves, 50% of gas reserves and more than 80% of known coal reserves should remain unused in order to meet global temperature targets under the Paris Agreement. Assets become stranded when new government regulations that limit the use of fossil fuels (like carbon pricing) are instituted, from a change in demand (for example, a shift towards renewable energy because of lower energy costs), or by legal action. Those who have invested in the fossil fuel industry are at most risk, including people who have bought stocks or bonds. This can include a wide variety of people and institutions such as individual investors, banks, pension funds, insurance companies, and universities, among others. Although the ‘stranded assets’ discussion often focuses on fossil fuels, it’s not just companies extracting oil, gas, and coal that could be affected by transition risk. Other companies that use fossil fuels as inputs for production, or are otherwise energy or carbon-intensive, could also be affected by new climate legislation, technological advances, or a shift in demand.[8]
A 2018 study published in Nature Climate Change suggests that part of the stranded assets would occur as a result of an already ongoing technological trajectory, irrespective of whether or not new climate policies are adopted. This loss would be amplified if new climate policies were adopted to reach the 2 °C target of the Paris Agreement, or if low-cost producers (such as some OPEC countries) maintain their level of production, or sell out, despite declining demand. The magnitude of the loss from stranded assets may amount to a discounted global wealth loss of US$1–4 trillion. Net importers, such as China or Europe, would fair better as fossil fuel prices drop. But net exporters, for example, Russia, the United States, or Canada, could see their fossil fuel industries nearly shut down. The two effects would largely offset each other at the level of aggregate global GDP.[9]
Meanwhile, a 2018 report indicated that major banks have increased fossil fuel financing. A report by Rainforest Action Network, Oil Change International, BankTrack, Indigenous Environmental Network, Sierra Club, and Honor The Earth, found that the major banks funneled $115 billion into extreme fossil fuels (defined as: tar sands, Arctic, and ultra-deepwater oil; coal mining and coal-fired power; and liquefied natural gas export in North America) in 2017, an increase of 11% from 2016. The single biggest driver of the increase in financing came from the tar sands sector, where financing grew by 111% from 2016 to 2017. The massive hike in bank support for tar sands to nearly $47 billion, led tar sands to overtake coal power as the most heavily funded extreme energy sector.[10] Further investments increase the carbon bubble and therefore the potential negative future consequences caused by the bursting of it.
Survey
The following table shows the results of a survey of projects documented by the Global Fossil Infrastructure Tracker. The survey is based on a diverse collection of projects worldwide. It shows the wide range in costs per km, which can likely be attributed primarily to differences between offshore and onshore projects, the inclusion or exclusion of additional infrastructure such as drilling platforms or pressurization stations, regional cost differences, and variations by year. For that reason, these results should be viewed as non-conclusive. A more reliable global finding would require careful project definition (including exclusion of secondary infrastructure), thereby allowing apples-to-apples comparisons. The median cost in the survey is $2,338,492 per km, lower than the $4.75 million/km estimated by Oil and Gas Journal in November 2018 for U.S. onshore gas pipeline projects in 2015-2016, but within the range of reported costs in the preceding 8 years, which ranged from $2.30 million/km in 2008-09 to $4.1 million/km in 2013-14 (see above).
Wiki | Name | Owner | Status | Estimated Investment (US$) | Lengthkm | Inv per km (US$) |
---|---|---|---|---|---|---|
http://bit.ly/2PmmZHc | Saddle West Pipeline | TransCanada | Proposed | 655,000,000 | 29 | 22,586,207 |
http://bit.ly/2gqy1bb | Alaska LNG Pipeline (AKLNG) | Alaska Gasline Development Corp (AGDC) | Proposed | 55,000,000,000 | 2760 | 19,927,536 |
http://bit.ly/2z9PJeY | Driftwood LNG Pipeline | Tellurian Inc. | Proposed | 2,900,000,000 | 154 | 18,831,169 |
http://bit.ly/2RB09JD | Kukrahati-Itinda Gas Pipeline | H-Energy | Proposed | 1,828,846,000 | 125 | 14,630,768 |
http://bit.ly/2BPP9Ba | Rio Bravo Gas Pipeline | NextDecade | Proposed | 2,200,000,000 | 220 | 10,000,000 |
http://bit.ly/2Pk8x2B | Eagle Spirit Pipeline | Eagle Spirit Energy Holdings Ltd. | Proposed | 16,000,000,000 | 1601.3 | 9,991,882 |
http://bit.ly/2RnomCZ | TEMAX Project | Spectra Energy (50%), ConocoPhillips (50%) | Proposed | 500,000,000 | 53.1 | 9,416,196 |
http://bit.ly/2PzmJVt | 2019 NGTL System | TransCanada | Proposed | 2,400,000,000 | 275.2 | 8,720,930 |
http://bit.ly/2JfrAFN | Sooner Trails Pipeline | Proposed | 3,500,000,000 | 402.3 | 8,699,975 | |
http://bit.ly/2Je5SC1 | Granite Bridge Pipeline | Algonquin Power & Utilities Corp. | Proposed | 340,000,000 | 43.5 | 7,816,092 |
http://bit.ly/2Rk8wcc | Buckeye Xpress Pipeline | TransCanada | Proposed | 709,000,000 | 103 | 6,883,495 |
http://bit.ly/2PyoSk6 | North Montney Mainline Pipeline | TransCanada | Proposed | 1,400,000,000 | 206 | 6,796,117 |
http://bit.ly/2PzmJVt | 2018 NGTL System | TransCanada | Proposed | 570,000,000 | 88.5 | 6,440,678 |
http://bit.ly/2Rnu1ZS | Wyndwood Pipeline Expansion Project | Spectra Energy | Proposed | 170,300,000 | 27.4 | 6,215,328 |
http://bit.ly/2JfajfN | South Saskatchewan Access Pipeline | Proposed | 47,000,000 | 8 | 5,875,000 | |
http://bit.ly/2z8EW4K | Eagle Mountain-Woodfibre gas pipeline | FortisEnergy B.C. | Proposed | 250,000,000 | 47 | 5,319,149 |
http://bit.ly/2Jkk5gZ | Haynesville Global Access Pipeline | Tellurian | Proposed | 1,400,000,000 | 321.9 | 4,349,177 |
http://bit.ly/2JfpJAP | Delmarva Pipeline | H4 Capital Partners LLC | Proposed | 1,300,000,000 | 305.8 | 4,251,145 |
http://bit.ly/2Je683X | Buncombe County Pipeline | SCANA | Proposed | 72,500,000 | 19.3 | 3,756,477 |
http://bit.ly/2gAgk8W | Keystone XL Oil Pipeline | TransCanada | Proposed | 7,000,000,000 | 1900 | 3,684,211 |
http://bit.ly/2PmwBBY | Permian Global Access Pipeline | Tellurian Inc. | Proposed | 3,700,000,000 | 1005.8 | 3,678,664 |
https://bit.ly/2CTIisZ | Cirebon-KHT Gas Pipeline | Rekind | Proposed | 300,000,000 | 84 | 3,571,429 |
http://bit.ly/2ptQvws | West-East Gas Pipeline | Proposed | 5,000,000,000 | 1500 | 3,333,333 | |
http://bit.ly/2BSPbbq | Northern Access Gas Pipeline | National Fuel Gas Company | Proposed | 500,000,000 | 155 | 3,225,806 |
http://bit.ly/2RtenMu | East Med Gas Pipeline | Proposed | 7,000,000,000 | 2200 | 3,181,818 | |
http://bit.ly/2RwOzPk | Bay of Bengal-Chittagong Oil Pipeline | Bangladesh Petroleum Corporation | Proposed | 694,000,000 | 220 | 3,154,545 |
http://bit.ly/2Rsr8GU | Bay of Bengal-Chittagong Oil Pipeline 2 | Bangladesh Petroleum Corporation | Proposed | 694,000,000 | 220 | 3,154,545 |
http://bit.ly/2gA9TD5 | Pilgrim Oil Pipeline | Ares Management | Proposed | 900,000,000 | 286 | 3,146,853 |
http://bit.ly/2JgiMzw | Big Foot Oil Pipeline | Enbridge | Proposed | 200,000,000 | 64.4 | 3,105,590 |
http://bit.ly/2PIMXoM | Israel Jordan Gas Pipeline | Proposed | 200,000,000 | 65 | 3,076,923 | |
http://bit.ly/2JdyiMl | Southern Reliability Link Pipeline | New Jersey Resources | Proposed | 130,000,000 | 48.3 | 2,691,511 |
http://bit.ly/2JdyYBn | Whistler Pipeline | Targa Resources | Proposed | 2,600,000,000 | 997.8 | 2,605,733 |
http://bit.ly/2PiDpQR | Permian to Gulf Coast Pipeline | Proposed | 2,000,000,000 | 965.6 | 2,071,251 | |
http://bit.ly/2JfqlX9 | Marquette Connector Pipeline | AltaGas | Proposed | 137,500,000 | 67.6 | 2,034,024 |
http://bit.ly/2BRlXdl | Spire STL Pipeline | Spire | Proposed | 210,000,000 | 106 | 1,981,132 |
http://bit.ly/2Jg62cf | Risberg Line Pipeline | RH Energytrans | Proposed | 86,000,000 | 45.1 | 1,906,874 |
http://bit.ly/2Jfeecs | Palmetto Pipeline | Kinder Morgan | Proposed | 1,100,000,000 | 579.4 | 1,898,516 |
http://bit.ly/2PoRZGL | Energia Mayakan Pipeline Expansion | Proposed | 300,000,000 | 159.3 | 1,883,239 | |
http://bit.ly/2RxJ6YJ | Ennore-Nellore Gas Pipeline | Gas Transmission India Private Ltd. | Proposed | 779,672,880 | 430 | 1,813,193 |
http://bit.ly/2PCaLu9 | Israel Cyprus Gas Pipeline | Energean | Proposed | 350,000,000 | 200 | 1,750,000 |
https://bit.ly/2OndckB | Cirebon-Semarang Gas Pipeline | PT Pertamina Gas | Proposed | 400,000,000 | 235 | 1,702,128 |
http://bit.ly/2toFVeU | Reedy Creek Walumbilla Pipeline | APA Group | Proposed | 80,000,000 | 49 | 1,632,653 |
http://bit.ly/2JiImUA | Arkoma Residue Capacity Pipeline | Tall Oak Midstream | Proposed | 200,000,000 | 128.7 | 1,554,002 |
http://bit.ly/2z9Q80Y | Eastern Shore Gas Pipeline Expansion | Chesapeake Utilities | Proposed | 99,000,000 | 67 | 1,477,612 |
http://bit.ly/2Jf2PJD | Roadrunner Pipeline | Fermaca (50%), ONEOK (50%) | Proposed | 475,000,000 | 321.9 | 1,475,614 |
https://bit.ly/2Q6HN32 | Cactus 2 Oil Pipeline | Plains All American Pipeline | Proposed | 1,100,000,000 | 829 | 1,326,900 |
http://bit.ly/2PAwBhO | Neka Jask Pipeline | National Iranian Oil Company | Proposed | 2,000,000,000 | 1515 | 1,320,132 |
http://bit.ly/2RwyZTT | Hon La-Thakhek Oil Pipeline | Petro Lao | Proposed | 380,000,000 | 306 | 1,241,830 |
http://bit.ly/2JdfKfr | Arctic Fox Pipeline | Fairbanks Pipeline Company | Proposed | 1,000,000,000 | 827.2 | 1,208,897 |
http://bit.ly/2Prs29D | Iron Horse Pipeline | Tallgrass Energy (50%), Silver Creek Midstream (50%) | Proposed | 150,000,000 | 128.7 | 1,165,501 |
http://bit.ly/2PeJ36P | Knight Warrior Pipeline | Blueknight Energy Partners | Proposed | 300,000,000 | 257.5 | 1,165,049 |
https://bit.ly/2Ps2Yz6 | Salina Cruz-Tapachula Gas Pipeline | Afinan | Proposed | 442,000,000 | 440 | 1,004,545 |
http://bit.ly/2DHBYSf | Western Slopes Pipeline | APA Group | Proposed | 450,000,000 | 450 | 1,000,000 |
https://bit.ly/2pU3kjO | Natuna-West Kalimantan Gas Pipeline | TBD | Proposed | 550,000,000 | 687 | 800,582 |
http://bit.ly/2z11vIV | Yamoussoukro-Ferkessédougou Petroleum Products Pipeline | Petroci | Proposed | 250,000,000 | 357 | 700,280 |
http://bit.ly/2oZrgBj | Queensland Hunter Gas Pipeline | Hunter Gas Pipeline Pty Ltd | Proposed | 500,000,000 | 825 | 606,061 |
https://bit.ly/2CgE7ak | Central Kalimantan-South Kalimantan Gas Pipeline | TBD | Proposed | 97,000,000 | 162 | 598,765 |
http://bit.ly/2RwKV8k | Barauni-Guwahati Gas Pipeline | Proposed | 414,900,000 | 750 | 553,200 | |
http://bit.ly/2JeJZTg | Mountaineer Gas Pipeline | IGS Utilities | Proposed | 45,000,000 | 90.8 | 495,595 |
http://bit.ly/2RDXjUf | Contai-Paradip-Dattapulia Gas Pipeline | H-Energy | Proposed | 333,858,720 | 705 | 473,558 |
http://bit.ly/2RtwnWW | Mehsana-Bhatinda Gas Pipeline | Gujarat State Petronet; Indian Oil; Bharat Petroleum; Hindustan Petroleum | Proposed | 955,674,720 | 2052 | 465,728 |
http://bit.ly/2JgXd1u | Doosan Bobcat Pipeline | MDU Resources Group | Proposed | 13,800,000 | 33.8 | 408,284 |
http://bit.ly/2PzmJVt | 2021 NGTL System | TransCanada | Proposed | 140,000,000 | 350.8 | 399,088 |
https://bit.ly/2IYxniG | West Kalimantan-Central Kalimantan Gas Pipeline | TBD | Proposed | 516,400,000 | 1800 | 286,889 |
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 Natural gas pipeline profits, construction both up Oil & Gas Journal, September 5, 2016
- ↑ "Natural Gas Pipeline Construction Cost Per Mile," Hanging H, accessed October 2020
- ↑ "Natural Gas Value Chain: Pipeline Transportation," USAID, accessed October 2020
- ↑ Michail Korchemkin, "Pipeline construction costs go up when Gazprom works alone," Archipelago Gazprom, April 2, 2014
- ↑ Andrew Bradford, "Gas Pipeline Costs Run Higher," BTU Analytics, September 7, 2018
- ↑ "U.S. Oil and Gas Infrastructure Investment Through 2035," American Petroleum Institute, April 2017
- ↑ Historical Pipelines Construction Cost Analysis Research Gate, accessed November 2018
- ↑ What are stranded assets? The London School of Economics and Political Science, accessed November 2018
- ↑ Macroeconomic impact of stranded fossil fuel assets Nature, accessed November 2018
- ↑ Report Finds Major Banks Ramped Up Fossil Fuel Financing to $115 Billion in 2017 Oil Change International, accessed November 2018