Panxian-2 power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Panxian-2 power station (粤电粤黔盘南电厂) is an operating power station of at least 2400-megawatts (MW) in Liupanshui City, Pan, Liupanshui, Guizhou, China with multiple units, some of which are not currently operating. It is also known as 贵州粤黔电力有限责任公司 (Phase III Unit 5), 响水电厂 (Phase III Unit 5, Phase III Unit 6).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Panxian-2 power station | Liupanshui City, Pan, Liupanshui, Guizhou, China | 25.4686039, 104.5924059 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6: 25.4686039, 104.5924059
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase I Unit 1 | operating | coal: bituminous | 600 | subcritical | 2006 |
Phase I Unit 2 | operating | coal: bituminous | 600 | subcritical | 2006 |
Phase II Unit 3 | operating | coal: bituminous | 600 | subcritical | 2007 |
Phase II Unit 4 | operating | coal: bituminous | 600 | subcritical | 2007 |
Phase III Unit 5 | announced | coal: bituminous | 660 | supercritical | – |
Phase III Unit 6 | announced | coal: bituminous | 660 | supercritical | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Guizhou Yueqian Electric Power Co Ltd [100%] | Guangdong Hengjian Investment Holding Co Ltd [48.8%]; China Huaneng Group Co Ltd [15.4%]; Guangzhou Development Group Inc [15.0%]; Guangdong Electric Power Development Co Ltd [13.0%]; other [7.8%] |
Phase I Unit 2 | Guizhou Yueqian Electric Power Co Ltd [100%] | Guangdong Hengjian Investment Holding Co Ltd [48.8%]; China Huaneng Group Co Ltd [15.4%]; Guangzhou Development Group Inc [15.0%]; Guangdong Electric Power Development Co Ltd [13.0%]; other [7.8%] |
Phase II Unit 3 | Guizhou Yueqian Electric Power Co Ltd [100%] | Guangdong Hengjian Investment Holding Co Ltd [48.8%]; China Huaneng Group Co Ltd [15.4%]; Guangzhou Development Group Inc [15.0%]; Guangdong Electric Power Development Co Ltd [13.0%]; other [7.8%] |
Phase II Unit 4 | Guizhou Yueqian Electric Power Co Ltd [100%] | Guangdong Hengjian Investment Holding Co Ltd [48.8%]; China Huaneng Group Co Ltd [15.4%]; Guangzhou Development Group Inc [15.0%]; Guangdong Electric Power Development Co Ltd [13.0%]; other [7.8%] |
Phase III Unit 5 | Guizhou Yueqian Electric Power Co Ltd [100%] | Guangdong Hengjian Investment Holding Co Ltd [48.8%]; China Huaneng Group Co Ltd [15.4%]; Guangzhou Development Group Inc [15.0%]; Guangdong Electric Power Development Co Ltd [13.0%]; other [7.8%] |
Phase III Unit 6 | Guizhou Yueqian Electric Power Co Ltd [100%] | Guangdong Hengjian Investment Holding Co Ltd [48.8%]; China Huaneng Group Co Ltd [15.4%]; Guangzhou Development Group Inc [15.0%]; Guangdong Electric Power Development Co Ltd [13.0%]; other [7.8%] |
Background
The first four coal-fired units of Panxian-2 power station, totaling 2,400 MW, were brought online between 2006 and 2007. The plant is sponsored by Yueqian Power Co., a subsidiary of Guangdong Yudean Group.[1] The electricity it generates supplies Guangdong Province.[2]
Description of Expansion
Plant owner Guizhou Yueqian Power Co is planning to build two additional coal-fired units at this plant, with a planned capacity of 660 MW each.[3][4][5][6]
There were no further developments on the proposed units after 2013, and they were likely suspended due to the country's traffic light policy, a national measure implemented in 2016 that prohibited new coal plant development throughout most of China's provinces, including Guizhou. However in March 2019 Guizhou was given a green light for new coal plants. In February 2020 it was announced that plans for development of the two units was revived.[7]
In 2023, with no further news, Phase III was presumed to be cancelled.
Plant Details for Existing Units 1-4
- Sponsor: Guizhou Yueqian Power Co
- Parent company: Guangdong Yudean Group (98%), China Southern Power Grid (2%)
- Location: Xiangshui, Pan County, Liupanshui Prefecture, Guizhou Province, China
- Coordinates: 25.4686039, 104.5924059 (exact)
- Status: Operating
- Gross capacity: 2,400 MW (Units 1-4: 600 MW)
- Start year: 2006 (Units 1 & 2); 2007 (Units 3 & 4)
- Type: Subcritical
- Coal type:
- Coal source:
- Source of financing:
Articles and Resources
References
- ↑ "贵州粤黔电力有限责任公司" 贵州粤黔电力有限责任公司, 6/6/2013
- ↑ "贵州粤黔电力有限责任公司"贵州省国控企业减排监测信息网
- ↑ "盘南电厂5、6号机组扩建工程可行性研究报告通过审查" accessed June 2013
- ↑ "粤黔电力召开盘南电厂5、6号机组扩建工程初可审查会议", 贵州粤黔电力有限责任公司, 12/20/2010
- ↑ "贵州粤黔电力有限责任公司盘南电厂5#、6#机组扩建工程水资源论证报告书公示," PRWRC, 2013-04-27
- ↑ "盘南电厂5、6号机组扩建工程可行性研究报告通过审查," Liupanshui City Government, 2011-11-30
- ↑ "六盘水市:推进盘南、大湾低热值煤发电厂项目和盘南电厂5号、6号机组建设," 北极星电力网新闻中心, 2020/2/14
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.