Parit Baru power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Parit Baru power station is a power station in Jungkat, Siantan, Pontianak, West Kalimantan, Indonesia with multiple units of varying statuses, none of which are currently operating. It is also known as 巴比巴卢电站.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Parit Baru power station | Jungkat, Siantan, Pontianak, West Kalimantan, Indonesia | 0.05798, 109.20362 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 3, Unit 4: 0.05798, 109.20362
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | construction[1] | coal: unknown | 50 | subcritical | 2025[1] |
Unit 2 | construction | coal: unknown | 50 | subcritical | 2025 |
Unit 3 | shelved | coal: unknown | 50 | subcritical | – |
Unit 4 | shelved | coal: unknown | 50 | subcritical | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | China Gezhouba Group Co Ltd; PT Praba Indopersada | China Energy Engineering Corp Ltd; HKSCC Nominees Ltd; PT Praba Indopersada |
Unit 2 | China Gezhouba Group Co Ltd; PT Praba Indopersada | China Energy Engineering Corp Ltd; HKSCC Nominees Ltd; PT Praba Indopersada |
Unit 3 | China Gezhouba Group Co Ltd; PT Praba Indopersada | China Energy Engineering Corp Ltd; HKSCC Nominees Ltd; PT Praba Indopersada |
Unit 4 | China Gezhouba Group Co Ltd; PT Praba Indopersada | China Energy Engineering Corp Ltd; HKSCC Nominees Ltd; PT Praba Indopersada |
Project-level coal details
- Permit(s):
Location of Parit Baru Units 1 & 2
The map below shows the plant, in Jungkat Village, Siantan District, Pontianak Regency, West Kalimantan Province.[2] Planet satellite photos show construction progress from April 2016 to April 2018.
Background
Units 1 & 2
Work on the Parit Baru project began in 2010 and completion was initially targeted for 2012.[3] It was the first coal plant EPC (engineering, procurement, and construction) contract undertaken by a joint venture comprising Gazhouba Group in Indonesia (a subsidiary of China Energy Engineering Corporation) and PT Praba Indopersada (a subsidiary of general contractor firm Praba Group of Indonesia).[4] In May 2011 it was estimated that the project would cost US$172 million. The project was set to be 85% financed by the Export-Import Bank of China which was to provide a US$133 million loan for the plant's construction in 2011.[5] The joint venture between the two companies was formalized in a memorandum of understanding at the conclusion of a three day visit to Indonesia by Chinese Premier Wen Jiabao. On the trip Jiabao pledged $19 billion in investment and loans to a range of projects in Indonesia.[4][6]
In March 2013, 78 Chinese-national workers at the Parit Baru construction site were threatened with deportation for lacking proper work authorization.[7] Hundreds of Chinese workers were repatriated in 2013.[3] According to the 2015-2024 PT PLN supply plant, Parit Baru 1 and 2 would be completed in 2016.[8]
In September 2013, construction resumed on the project.[9] The project faces the South China sea in the west and is adjacent to the Pontianak-Singkawang provincial highway. It occupies 40 hectares. According to the contract, construction would be completed in 33 months.[9]
In November 2016, the Operations and Construction Manager of PT PLN West Kalimantan Development Master Unit, I Wayan Semudiarsa, said that the Parit Baru project was experiencing financial difficulties and progress was slow.[10] At the time, it was also reported that construction on the units had been delayed.[11]
In March 2017, President Joko Widodo stated that after seven years, the legal problems that had delayed the plant were resolved and the plant was moving toward completion.[12]
In June 2018, it was believed that one unit was commissioned. However, the article may have been referring to Bengkayang Power Station.[13]
The long-range plan for 2019-2028 projected 100 MW from Parit Baru power station being commissioned in 2019.[14]
In August 2019, it was believed that the second unit was commissioned. However, the article may have been referring to Bengkayang Power Station.[15]
In the long-range plan for 2021-2030, FTP1 (Unit 1) was listed as under construction, with COD targeted for 2025.[16]
In June 2022, PLN documents listed the project as part of a "fast track program".[17]
According to a PLN 2022 annual report, as of December 2022, construction progress on the 2 x 50 MW power station was 86% complete.[18]
In May 2024, the construction of the power station was described as "stalled".[19] In November 2024, the power station was described as "incomplete and nonfunctional".[20]
Financing for Units 1 and 2
In 2011, China's Exim Bank announced it would provide a $133 million loan for Units 1 and 2.[5]
Units 3 & 4
According to some sources, the project was proposed to be expanded by two additional 50-MW coal-fired units.[6] According to the 2015-2024 PT PLN supply plan, Parit Baru Units 3 and 4 would be completed in 2017 and 2018 respectively. However, as of April 2016, these units had not yet begun construction, as shown by Google Earth archival imagery.[8] In October 2018, a 2 x 55 MW plant with the name of "Kalbar 3" was listed as being under construction in Bengakayang Regency, which is adjacent to Pontianak Regency where Units 1 and 2 are operating.[21] Units 3 and 4 did not appear in the RUPTL 2017-2026, RUPTL 2018-2027, or RUPTL 2019-2028. Satellite photography from Planet did not show further construction occurring at Parit Baru between August 2019 and December 2019.
In May 2021, Indonesia's National Land Agency issued land certificates for 18 PLN projects in Kalimantan, including land for the construction site of the Parit Baru expansion project. The Parit Baru expansion would be located in Bengkayang, about 60 miles north of Parit Baru Units 1-2, and near the Kalbar-1 power station[22]
June 2021 news reports listed the 2 x 50 MW Parit Baru expansion as one of 34 projects being developed by PLN whose construction had either been "hampered" or "stalled". 12 of those projects were declared to have been cancelled, but government officials stated that they planned to continue development of the Parit Baru expansion.[23]
In 2023, with no apparent news on additional units beyond Units 1 and 2, Units 3 and 4 were presumed to be shelved. Bengkayang Power Station may have been the expansion, as the timeline matched initial projections and the power station was built approximately 60 miles north of the Parit Baru power station Units 1 and 2 site.
Alleged Corruption
In November 2024, an investigation was launched into alleged corruption tied to the construction of Parit Baru power station. Preliminary examinations had reportedly begun in February 2024. An investigative audit estimated potential losses of IDR 323.2 billion (US$62.41 million).[20]
Articles and Resources
References
- ↑ 1.0 1.1 (PDF) https://web.archive.org/web/20211021081234/https://web.pln.co.id/statics/uploads/2021/10/ruptl-2021-2030.pdf. Archived from the original (PDF) on 21 October 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ PLTU Parit Baru, Jungkat, Pnk., Wikimapia, accessed Mar. 2015.
- ↑ 3.0 3.1 "Menyoal Pembangunan PLTU di Kalbar," Pontianakpost.co.id, 2 June 2016
- ↑ 4.0 4.1 Linda Yulisman, "Chinese firm to build coal-fired power plant in W. Kalimantan", Jakarta Post, May 03 2011.
- ↑ 5.0 5.1 China Exim Bank provides $133 million loan to Indonesia for construction of Parit Baru power plant, China.AidData.Org, accessed Jun.19, 2020.
- ↑ 6.0 6.1 Rencana Strategis (Strategic Plan) KESDM 2015-19, Indonesia Ministry of Energy & Natural Resources, 24 Feb. 2015.
- ↑ 78 Pekerja PLTU Asal Cina Terancam Deportasi, Republika, 20 Mar. 2013.
- ↑ 8.0 8.1 "Executive Summary: Electricity Supply Business Plan, PT PLN (Persero) 2015-2014,"
- ↑ 9.0 9.1 "Parit Baru Coal Fired Power Plant Construction Commenced," China Gezhouba (Group) Corporation press release, September 7, 2013
- ↑ "PLN: Dua Proyek Pembangkit Di Kalbar Masih Terkendala," AntaraKalbar.com, 14 November 2016
- ↑ "PLN unveils details of 34 troubled power plants under SBY govt being probed by KPK," Rambu Energy, November 24, 2016
- ↑ "Jokowi Singgung PLTU Parit Baru Mangkrak," IndonesiaOversight, 19 March 2017
- ↑ PLN Operasikan PLTU Baru 50 MW di Kalimantan Barat, Industri, Jun. 6, 2018
- ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2019-2028, PT PLN Persero, V-51
- ↑ PLTU Parit Baru Site Bengkayang kapasitas 100 MW sudah beropersi penuh, Kalbar, Aug. 22, 2019
- ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2021-2030, PT PLN Persero
- ↑ Laporan Keuangan Konsolidasian, Perusahaan Perseroan (Persero) PT Perusahaan Listrik Negara Dan Entitas Anak, July 2022
- ↑ Laporan Tahunan 2022, PT PLN (Persero), 2022
- ↑ BPKP Minta PLN Evaluasi Pembangunan PLTU 1 Kalbar yang Mangkrak, teras.id, May 31, 2024
- ↑ 20.0 20.1 Indonesia Suffers $62 Million Loss in Massive Corruption in PLTU Kalbar-1 Project, Indonesia Sentinel, November 7, 2024
- ↑ LAPORAN KUNJUNGAN KERJA SPESIFIK KOMISI VI DPR RI KE PROVINSI KALIMANTAN BARAT, DEWAN PERWAKILAN RAKYAT REPUBLIK INDONESIA ], Oct. 10, 2018
- ↑ Amankan Aset Negara, BPN Terbitkan 18 Sertifikat Tanah di Bengkayang, iNewsKalbar, May 28, 2021
- ↑ Suci Sedya Utami, 12 Proyek Pembangkit Batu Bara Batal Dibangun, MedCom.id, 04 June 4, 2021
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.