Putian LNG Terminal
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Putian LNG Terminal (哈纳斯福建莆田LNG接收站) is a proposed LNG terminal in Fujian, China.
Location
Project details
Phase 1
- Owner: Putian Hanas LNG Co., Ltd. 莆田哈纳斯液化天然气有限公司[1][2]
- Parent company: Shanghai Hanas Energy Development Co., Ltd. 上海哈纳斯能源发展有限公司 100% --→ Shanghai Hanas Investment (Group) Ltd., Co. 上海哈纳斯投资(集团)有限公司 100%
- Location: Port of Meizhou, Meizhou Bai, Putian, Fujian, China
- Coordinates: 25.103809168959067, 119.07193777157194(exact)
- Capacity: 5.65 mtpa
- Status: Proposed
- Type: Import
- Start year: 2026
- Originally 2021
Phase 2
- Owner: Putian Hanas LNG Co., Ltd. 莆田哈纳斯液化天然气有限公司[3]
- Parent company: Shanghai Hanas Energy Development Co., Ltd. 上海哈纳斯能源发展有限公司 100% --→ Shanghai Hanas Investment (Group) Ltd., Co. 上海哈纳斯投资(集团)有限公司 100%
- Location: Port of Meizhou, Meizhou Bai, Putian, Fujian, China
- Coordinates: 25.103809168959067, 119.07193777157194(exact)
- Capacity: 5.26 mtpa[4]
- Status: Proposed
- Type: Import
- Start year:
Background
Putian LNG Terminal is a proposed LNG terminal in Fujian, China.[5]
The Putian LNG terminal is still in the project phase and expected to include two stages of construction completing in 2020 with a receiving capacity of 5-6 mpta.[5] A marine environmental impact assessment report hearing was held In December of 2016, with support of the project to move forward.[6][7]
The Project was listed into National Natural Gas Development 13th Five-Year-Plan.[8]
The provincial government of Ningxia Autonomous Region where Hanas Group is based was seeking cooperation with Fujian government on this project. [9][10]
The project received permit for construction from the provincial authority in December 2021.[11] According to the permit document, the project will have two storage tanks with 200,000 cubic meters each. The receiving capacity is 5.65 mpta and the total investment is 5.26 billion yuan ($780 million).[11]
Phase 1 planned to start construction in May 2023, with an expected commissioning three years later.[4] The combined receiving capacity for both phases is 10 mtpa.[4]
In October 2023, a news report indicates the actual construction will start "next year", in 2024.[12]
Articles and resources
References
- ↑ "莆田哈纳斯液化天然气有限公司 - 企查查". www.qcc.com. Retrieved 2021-04-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "莆田哈纳斯 - 哈纳斯". www.hanaslngpt.com. Retrieved 2024-01-24.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "莆田哈纳斯液化天然气有限公司 - 企查查". www.qcc.com. Retrieved 2021-04-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 4.0 4.1 4.2 "https://www.seetao.com/details/211992.html".
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|title=
- ↑ 5.0 5.1 Putian LNG Terminal, Hanas company page, accessed April 2017
- ↑ State Oceanic Administration held Hanas Putian liquefied Natural gas (LNG) Project Reclamation Marine Environmental Impact Assessment Report Hearing Hanas company page, accessed June 29, 2017
- ↑ "中国最全的LNG接收站进度表,没有之一," Sohu, 2018-01-08
- ↑ "莆田LNG接收站项目-哈纳斯集团". www.hanaspipeline.com. Retrieved 2021-04-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "吴秀章考察调研哈纳斯莆田LNG接收站项目 - 莆田新闻 - 东南网". pt.fjsen.com. 2019-05-10. Retrieved 2021-04-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "闽宁两地积极合作,加速打造莆田LNG进口接收站项目-哈纳斯集团". www.hanas.com. 2020-11-24. Retrieved 2021-04-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 11.0 11.1 "【关于哈纳斯莆田液化天然气接收站项目核准的批复(发改能源〔2021〕1814号)】-国家发展和改革委员会". www.ndrc.gov.cn. 2021-12-14.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "哈纳斯莆田液化天然气接收站项目一期工程进入全面建设阶段,标志着闽宁协作迈入新的里程,续写新的篇章——"双向奔赴"山海情". 新福建网 www.newfj.com.cn. 2023-10-10.
{{cite web}}
: CS1 maint: url-status (link)