Qidong LNG Terminal (广汇能源启东LNG接收站转运站), also called Guanghui LNG Terminal, is an LNG import terminal in Jiangsu, China.
Location
Project details
Phases 1 and 2
- Owner: Guanghui ENERGY General Logistics Development Co., Ltd. 广汇能源综合物流发展有限责任公司[1]
- Parent company: Guanghui Energy Co., Ltd. 99%, Xinjiang Guanghui Clean Energy Technology Co., Ltd. 1%.
广汇能源股份有限公司 | 99% |
新疆广汇清洁能源科技有限责任公司 | 1% |
- Location: Qidong, Nantong, Jiangsu Province, China
- Coordinates: 32.041846, 121.746907 (exact)
- Capacity:
- Phase 1 and 2: 1.15 mtpa
- Status: Operating[2]
- Type: Import
- Start year:
- Phase I: 2017
- Phase II: 2018
Background
Qidong LNG Terminal (广汇能源启东LNG接收站转运站) is an LNG import terminal in Jiangsu, China.[3] The terminal received its first shipment on 4 June 2017.[4] Its original receiving capacity is 0.6 mpta, with two 50,000 cubic meters storage tanks. In November 2018 an additional 160,000 cubic meter storage tank was commissioned, raising the terminal's capacity to 1.15 mtpa.[5] A further expansion under Phases 3 would raise capacity to 3 mtpa, and this is under construction and scheduled for completion in 2020.[5]
In Phase 3, the fourth storage tank with 160,000 cubic meter volume began construction in May 2018[2] and was commissioned in June 6, 2020.[6]
In February 2020, phase 4, a fifth storage tank with 200,000 cubic meters of volume was permitted for construction by Jiangsu Provincial Development and Reform Commission. [7] The construction began in May 2020.[6] The fifth storage tank was commissioned in October 2022. [8]
In March 2021, phase 5, a sixth storage tank with 200,000 cubic meter of volume was permitted for construction by Jiangsu Provincial Development and Reform Commission. [9] The operating date is set at the end of 2023. It will increase the LNG storage capacity to 820,000 cubic meters.[10] The construction of the sixth storage tank began in August 2021. [11]
After the fifth and sixth storage tanks' completion, the total receiving capacity of Qidong LNG Terminal is going to reach 5 mtpa.[12][13]
广汇能源启东LNG接收站除在建项目外还在进行7号20万方储罐可研编制和2号泊位相关手续办理工作。整个泊位建设工期约两年,届时公司将具备两个大型泊位,可接收国际主流船型,具备超1000万吨/年的周转能力,[14]
The seventh storage tank with 200,000 cubic meter is proposed.[15] The prospective receiving capacity is 10 mtpa after the expansion is completed[16].
The sixth storage tank was completed and went operation in November 2023. [17]
Expansion projects
Phase 3
- Owner: Guanghui ENERGY General Logistics Development Co., Ltd. 广汇能源综合物流发展有限责任公司[1]
- Parent company: Guanghui Energy Co., Ltd. 99%, Xinjiang Guanghui Clean Energy Technology Co., Ltd. 1%.
- Location: Qidong, Nantong, Jiangsu Province, China
- Coordinates: 32.041846, 121.746907 (exact)
- Capacity: 1.85 mtpa
- Status: Operating
- Type: Import
- Start year: 2020
Phase 4
- Owner: Guanghui ENERGY General Logistics Development Co., Ltd. 广汇能源综合物流发展有限责任公司[1]
- Parent company: Guanghui Energy Co., Ltd. 99%, Xinjiang Guanghui Clean Energy Technology Co., Ltd. 1%.
- Location: Qidong, Nantong, Jiangsu Province, China
- Coordinates: 32.041846, 121.746907 (exact)
- Capacity: 2 mtpa
- Status: Operating [18]
- Type: Import
- Start year: 2022
Phase 5
- Owner: Guanghui ENERGY General Logistics Development Co., Ltd. 广汇能源综合物流发展有限责任公司[1]
- Parent company: Guanghui Energy Co., Ltd. 99%, Xinjiang Guanghui Clean Energy Technology Co., Ltd. 1%.
- Location: Qidong, Nantong, Jiangsu Province, China
- Coordinates: 32.041846, 121.746907 (exact)
- Capacity: 5 mtpa (Phase 5 and proposed phase 6)
- Status: Operating[16][17]
- Type: Import
- Start year: 2023
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 leslie. "广汇能源综合物流发展有限责任公司 - 企查查". www.qcc.com. Retrieved 2021-04-19.
- ↑ 2.0 2.1 "媒体聚焦:广汇能源--本文来源:能源平说". www.ghnygf.com. Retrieved 2023-02-17.
{{cite web}}
: CS1 maint: url-status (link) - ↑ eo封面 | 闯入者广汇 View.inews.qq.com, 8 August 2017
- ↑ Qidong LNG terminal receives first shipment Interfax Global Energy, 12 June 2017
- ↑ 5.0 5.1 广汇能源启东LNG接收站迎重要进展 16万方储罐明年一季度将投用, SCTN, Mar. 8, 2019
- ↑ 6.0 6.1 ""来不及解释了,先上车再说"广汇启东LNG接收站发展介绍 --国际船舶海工网". www.ishipoffshore.com. 2021-02-28. Retrieved 2021-03-30.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "广汇能源关于收到江苏省发展和改革委员会核准启东LNG接收站项目扩建5#20万立方米LNG储罐批复的公告". quotes.money.163.com. 2020-02-04. Retrieved 2021-03-30.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "【大干一百天 奋进新征程】公司广汇启东5#20万立方LNG储罐成功投产 - 中国五环工程有限公司". www.cwcec.com. 2022-10-12.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 省发改委信息员1 (2021-3-11). "江苏省发展和改革委员会 行政许可公示 南通港吕四港区广汇能源LNG分销转运站扩建6#20万立方LNG储罐工程项目". jsdrc.jiangsu.gov.cn. Retrieved 2021-03-30.
{{cite web}}
: Check date values in:|date=
(help)CS1 maint: url-status (link) - ↑ "广汇能源启东LNG接收站6#20万方LNG储罐项目顺利完成穹顶浇筑-国际燃气网". gas.in-en.com. 2023-01-23.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "广汇能源2022年第三季度业绩说明会--上证路演". roadshow.sseinfo.com. 2022-11-28.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "能源保供再添力量广汇启东LNG接收站6#20万立LNG储罐升顶成功----江苏海事局". https://www.js.msa.gov.cn. 2022-12-07.
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|website=
- ↑ "广汇能源:公司启东LNG接收站项目期初规划的一、二、三期工程及配套LNG气化、海水取排水及启通天然气管线等项目均已投产运行,现整体可达到300万吨/年的LNG周转能力_互动". www.sohu.com. 2021-10-29.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "外引内培 双轮驱动 跑出广汇能源高质量发展"加速度"---来源 : 吕四港经济开发区--启东市人民政府". www.qidong.gov.cn. 2023-07-05.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 彭玉章. "江苏海事局 图片新闻 能源保供再添力量广汇启东LNG接收站6#20万立LNG储罐升顶成功". webcache.googleusercontent.com. Retrieved 2023-02-13.
- ↑ 16.0 16.1 "广汇能源:公司启东LNG接收站项目期初规划的一、二、三期工程及配套LNG气化、海水取排水及启通天然气管线等项目均已投产运行,现整体可达到300万吨/年的LNG周转能力_互动". www.sohu.com. Retrieved 2022-06-27.
- ↑ 17.0 17.1 "总罐容量增至82万方!广汇能源启东海上综合能源基地第六座LNG储罐竣工!_集团要闻-新疆广汇实业投资(集团)有限责任公司". www.guanghui.com. 2023-12-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "广汇能源股份有限公司 关于江苏南通港吕四港区LNG接收站项目四期工程 5#20万立方米LNG储罐投入试运行的公告" (PDF). /www.sse.com.cn. 2022-10-11.
{{cite web}}
: CS1 maint: url-status (link)