Qinghua Ejin Cogen power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Qinghua Ejin Cogen power station (庆华集团额济纳旗风光煤互补示范电厂) is an operating power station of at least 100-megawatts (MW) in Dalaihubu, Ejin, Alxa, Inner Mongolia, China. It is also known as 内蒙古庆华集团额济纳旗热电联产机组工程项目.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Qinghua Ejin Cogen power station | Dalaihubu, Ejin, Alxa, Inner Mongolia, China | 41.913656, 101.042068 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 41.913656, 101.042068
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating[1] | coal: unknown | 50 | unknown | 2023[2][3] |
Unit 2 | operating[1] | coal: unknown | 50 | unknown | 2023[2][3] |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Inner Mongolia Qinghua Group Xinneng Power Co Ltd [100%] | China Kingho Energy Group Ltd [46.6%]; Xinjiang Qinghua Entrepreneurship Consulting Co Ltd [38.2%]; Henan Provincial Investment Co [5.8%]; other [5.4%]; Henan Zhongyuan Expressway Co Ltd [3.1%]; Henan State-owned Assets Holding Operation Group Co Ltd [0.9%] |
Unit 2 | Inner Mongolia Qinghua Group Xinneng Power Co Ltd [100%] | China Kingho Energy Group Ltd [46.6%]; Xinjiang Qinghua Entrepreneurship Consulting Co Ltd [38.2%]; Henan Provincial Investment Co [5.8%]; other [5.4%]; Henan Zhongyuan Expressway Co Ltd [3.1%]; Henan State-owned Assets Holding Operation Group Co Ltd [0.9%] |
Background on Project
Qinghua Ejin Cogen power station is a 2 x 50 MW coal plant in Dalaihubu, Ejin Banner, sponsored by Inner Mongolia Qinghua Group.[4]
Construction reportedly began in April 2019.[5] Planet satellite imagery appeared to show a mostly complete plant by the second half of 2019, and it was presumed operating by 2021 based on imagery.
Articles and Resources
References
- ↑ 1.0 1.1 https://web.archive.org/web/20240125131025/https://www.planet.com/stories/41-91deg-n-101-04deg-e-qing-hua-ji-tuan-e-ji-na-qi-OMI-iU4SR. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 https://web.archive.org/web/20240125130914/https://www.planet.com/stories/41-91deg-n-101-04deg-e-qing-hua-ji-tuan-e-ji-na-qi-9Pg5Z84IR. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 https://web.archive.org/web/20240219021849/https://www.als.gov.cn/art/2023/1/31/art_123_478753.html. Archived from the original on 19 February 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "内蒙古自治区发展和改革委员会关于内蒙古庆华集团额济纳旗热电联产机组工程项目核准的批复," 内蒙古自治区发展和改革委员会, 2015-09-28
- ↑ "额济纳旗2×50MW热电联产项目续建工程签约," NMG News, 2019-03-20
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.