Qinzhou power station (国投钦州发电厂) is an operating power station of at least 3360-megawatts (MW) in 3 Guoying Ave, Qinnan, Qinzhou, Guangxi, China. It is also known as SDIC Qinzhou power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Qinzhou power station 3 Guoying Ave, Qinnan, Qinzhou, Guangxi, China 21.7004655, 108.6243063 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 21.7004655, 108.6243063

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Phase I Unit 1 operating coal: bituminous 630 supercritical 2007
Phase I Unit 2 operating coal: bituminous 630 supercritical 2007
Phase II Unit 3 operating coal: bituminous 1050 ultra-supercritical 2016
Phase II Unit 4 operating coal: bituminous 1050 ultra-supercritical 2016

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 SDIC Qinzhou Electric POWER Co Ltd [100%] SDIC Power Holdings Co Ltd [61.0%]; Guangxi Investment Group Co Ltd [32.2%]; Industrial and Commercial Bank of China Ltd [2.9%]; Guangxi Guangtou New Energy Industry Development Fund Partnership LP [2.6%]; other [1.3%]
Phase I Unit 2 SDIC Qinzhou Electric POWER Co Ltd [100%] SDIC Power Holdings Co Ltd [61.0%]; Guangxi Investment Group Co Ltd [32.2%]; Industrial and Commercial Bank of China Ltd [2.9%]; Guangxi Guangtou New Energy Industry Development Fund Partnership LP [2.6%]; other [1.3%]
Phase II Unit 3 SDIC Qinzhou Electric POWER Co Ltd [100%] SDIC Power Holdings Co Ltd [61.0%]; Guangxi Investment Group Co Ltd [32.2%]; Industrial and Commercial Bank of China Ltd [2.9%]; Guangxi Guangtou New Energy Industry Development Fund Partnership LP [2.6%]; other [1.3%]
Phase II Unit 4 SDIC Qinzhou Electric POWER Co Ltd [100%] SDIC Power Holdings Co Ltd [61.0%]; Guangxi Investment Group Co Ltd [32.2%]; Industrial and Commercial Bank of China Ltd [2.9%]; Guangxi Guangtou New Energy Industry Development Fund Partnership LP [2.6%]; other [1.3%]

Background

The first two coal-fired units of Qinzhou power station, totaling 1,260 MW, were brought online in 2007. The plant is owned by State Development & Investment Corporation (SDIC).[1][2]

Phase II Expansion

In 2012, SDIC said it planned to add two additional coal-fired units at the plant with a total planned capacity of 2,100 MW. The units are projected to be completed in 2015.[3][4]

The two units were completed by September 2016, along with the Qinzhou Port Coal Terminal at Beibu Gulf Port.[5] [6]

Proposed Phase III Expansion & Relocation

In March 2020, a 2 x 1,000MW coal-fired expansion at the power station was listed as a preliminary project in the Guangxi "Energy Network Infrastructure Plan 2020-2022" (《广西“能源网”基础设施建设大会战实施方案(2020-2022年)》).[7]

In December 2020, one new 660 MW unit was permitted for construction at the power station. Another 660 MW unit was proposed.[8]

The ceremony for construction beginning was held in December 2020, but did not mark the start of actual construction.[9]

The ceremony for the first load of construction was then held December 21, 2021. The ceremony was now for 4 x 660 MW power station phase, even though only one unit was previously permitted for construction. The proposal was relocated to approximately 7 km away from the first and second phases.[10]

Additional information is available at the Qinzhou-III power station page.

Plant Details for Units 1-4

  • Sponsor: SDIC Huajing Power Holdings Co
  • Parent company: SDIC
  • Location: Qinnan District, Qinzhou Prefecture, Guangxi Zhuang Autonomous Region, China
  • Coordinates: 21.7004655, 108.6243063 (exact)
  • Status: Operating
  • Gross capacity: 3,360 MW (Units 1 & 2: 630 MW, Units 3 & 4: 1,050 MW)
  • Type: Supercritical (Units 1 & 2), Ultra-Supercritical (Units 3 & 4)
  • Start year: 2007 (Units 1 & 2), 2016 (Units 3 & 4)
  • Coal type:
  • Coal source:
  • Source of financing:

Articles and Resources

References

  1. "国投钦州发电有限公司"SDIC
  2. "国投钦州发电一期工程正式竣工投产"BJX News, 2007-12-04
  3. "国投钦州电厂二期工程启动暨国投钦州港煤码头工程开工仪式隆重举行", 国家开发投资公司, 2012-10-18
  4. "国投电力:钦州电厂二期扩建工程获发改委核准", 网易财经, 2014-07-24
  5. "国投钦州电厂二期投产、煤炭码头重载试车成功,龙门风电项目启动," SDIC, Sep 12, 2016
  6. "广西钦州电厂二期扩建工程3号机组顺利通过168小时试运行," China Energy Engineering Group Guangdong Electric Power Design Institute Co, 2016-8-01
  7. "总投资445.6亿元!广西2020-2022年将推进7个煤电项目," Sohu, 2020-03-04
  8. "国投钦州电厂三期1号机组项目获得核准批复 - 北极星火力发电网". news.bjx.com.cn. 2020-12-31. Retrieved 2021-01-05.{{cite web}}: CS1 maint: url-status (link)
  9. "国投钦州电厂三期项目动工仪式," 中国火力发电网, 2020-12-29
  10. "开工!国投钦州电厂三期项目举行奠基暨主厂房第一罐混凝土浇筑仪式," 中国(广西)自由贸易试验区钦州港片区协调指导局, 2021-12-22