The Razlog-Bansko Gas Pipeline is a proposed natural gas pipeline in Bulgaria.[1]
Location
The proposed pipeline route runs along the northern slopes of the Pirin Mountains, along the southern slopes of the Rila Mountains, and to AGRS Razlog-Bansko.[1]
Project Details
- Owner: Bulgartransgaz
- Proposed capacity: 0.26 billion cubic meters per year[1]
- Length: 37 km / 23 miles[2]
- Diameter: 250 mm / 10 inches[2]
- Cost: €15.902 million (US$181.28 million)[2]
- Financing: A €195,500 grant from the Kozloduy International Decommissioning Support Fund; €14.767 million equity investment from Bulgartransgaz; additional €940,000 investment[2]
- Status: Proposed
- Start Year: 2025[2]
Background
In 2017, Bulgartransgaz launched an environmental impact assessment (EIA) procedure for a pipeline to supply Razlog and Bansko with gas. Two routes were proposed, one that is 34 km and another that is 39 km.[3]
According to the Bulgartransgaz 2021-2030 Ten Year Network Development Plan, "The project is funded by a grant under Kozloduy International Decommissioning Fund to the amount of EUR 195.5 thousand. Co-funding by Bulgartransgaz EAD is to the amount of EUR 14.767 million."[2]
As of March 2021, Bulgartransgaz lists the pipeline as one of its "Projects in progress." The "planned deadline for completion of the project" is 2023.[2]
Bulgartransgaz's 2022-2031 TYNDP states that the project is expected to start construction in 2022-23, with an expected commissioning date between 2024 and 2025.[4]
Articles and resources
References
- ↑ 1.0 1.1 1.2 2020-2029 TEN-YEAR NETWORK DEVELOPMENT PLAN OF BULGARTRANSGAZ EAD, Bulgartransgaz, March 2020
- ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 BULGARTRANSGAZ EAD (March 2021). "2021-2030 TEN-YEAR NETWORK DEVELOPMENT PLAN OF BULGARTRANSGAZ EAD" (PDF). bulgartransgaz.bg. Retrieved August 10, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "News - Bulgartransgaz Launched EIA Procedure for Gas Pipeline to Razlog and Bansko". www.publics.bg. Retrieved 2021-08-12.
- ↑ "2022-2031 TEN-YEAR NETWORK DEVELOPMENT PLAN OF BULGARTRANSGAZ EAD" (PDF). Bulgartransgaz. Apr, 2022. Retrieved Jul 12th, 2022.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help); line feed character in|title=
at position 19 (help)CS1 maint: url-status (link)