Riyadh 9 power plant (محطة الكهرباء التاسعة) is an operating power station of at least 3760-megawatts (MW) in Riyadh, Saudi Arabia. It is also known as PP9.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Riyadh 9 power plant | Riyadh, Riyadh, Saudi Arabia | 24.948638, 47.063562 (exact)[1] |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- A1, A2, B1, B2, C-1, C-10, C-2, C-3, C-4, C-5, C-6, C-7, C-8, C-9, D-1, D-10, D-2, D-3, D-4, D-5, D-6, D-7, D-8, D-9, E-1, E-2, E-3, E-4, E-5, E-6, E-7, E-8, F-1, F-10, F-11, F-12, F-2, F-3, F-4, F-5, F-6, F-7, F-8, F-9: 24.948638, 47.063562
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year |
---|---|---|---|---|---|---|
A1 | Operating[2][3][4] | fossil gas: natural gas[3][5] | 340[6][7] | combined cycle[7] | not found | 1997[6] |
A2 | Operating[2][3][8] | fossil gas: natural gas[3][5] | 340[6][7] | combined cycle[7] | not found | 1998[6] |
B1 | Operating[2][3][8] | fossil gas: natural gas[3][5] | 340[6][7] | combined cycle[7] | not found | 1999[6] |
B2 | Operating[2][3][8] | fossil gas: natural gas[3][5] | 340[6][7] | combined cycle[7] | not found | 2000[6] |
C-1 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
C-10 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
C-2 | Operating[3][9] | fossil gas: natural gas[3][11][10] | 60[12][1][10] | gas turbine[12][1] | not found | 2007[10] |
C-3 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
C-4 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
C-5 | Operating[3][9] | fossil gas: natural gas[3][11][10] | 60[12][1][10] | gas turbine[12][1] | not found | 2007[10] |
C-6 | Operating[3][9] | fossil gas: natural gas[3][11][10] | 60[12][1][10] | gas turbine[12][1] | not found | 2007[10] |
C-7 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
C-8 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
C-9 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
D-1 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
D-10 | Operating[3][13][10] | fossil gas: natural gas[3][11] | 60[12][1] | gas turbine[12] | not found | 2007[10] |
D-2 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
D-3 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
D-4 | Operating[3][9][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12][1] | not found | 2007[10] |
D-5 | Operating[3][13][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12] | not found | 2007[10] |
D-6 | Operating[3][13][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12] | not found | 2007[10] |
D-7 | Operating[3][13][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12] | not found | 2007[10] |
D-8 | Operating[3][13][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12] | not found | 2007[10] |
D-9 | Operating[3][13][10] | fossil gas: natural gas[3][11][10] | 60[12][1] | gas turbine[12] | not found | 2007[10] |
E-1 | Operating[14][3][9] | fossil gas: natural gas[3][1] | 60[15][1] | gas turbine[1] | not found | 2004[15][1] |
E-2 | Operating[14][3][9] | fossil gas: natural gas[3][1] | 60[15][1] | gas turbine[1] | not found | 2004[15][1] |
E-3 | Operating[14][3][9] | fossil gas: natural gas[3][1] | 60[15][1] | gas turbine[1] | not found | 2004[15][1] |
E-4 | Operating[14][3][9] | fossil gas: natural gas[3][1] | 60[15][1] | gas turbine[1] | not found | 2004[15][1] |
E-5 | Operating[14][3][9] | fossil gas: natural gas[3][1] | 60[15][1] | gas turbine[1] | not found | 2004[15][1] |
E-6 | Operating[14][3][9] | fossil gas: natural gas[3][1] | 60[15][1] | gas turbine[1] | not found | 2004[15][1] |
E-7 | Operating[16][14][17][3] | fossil gas: natural gas[3][1] | 60[15][18] | gas turbine[19] | not found | 2004[16][15] |
E-8 | Operating[16][14][17][3] | fossil gas: natural gas[1] | 60[15][18] | gas turbine[19] | not found | 2004[16][15] |
F-1 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-10 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-11 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-12 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-2 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-3 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-4 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-5 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-6 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-7 | Operating[3][20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-8 | Operating[20][13] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
F-9 | Operating[13][3][20] | fossil gas: natural gas[3][5] | 60[12][18][5] | gas turbine[12][5] | not found | 2009[7] |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
A1 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
A2 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
B1 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
B2 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-1 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-10 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-2 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-3 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-4 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-5 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-6 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-7 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-8 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
C-9 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-1 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-10 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-2 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-3 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-4 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-5 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-6 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-7 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-8 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
D-9 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-1 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-2 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-3 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-4 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-5 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-6 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-7 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
E-8 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-1 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-10 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-11 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-12 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-2 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-3 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-4 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-5 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-6 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-7 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-8 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
F-9 | Saudi Electricity Co [100%][12][21][5][1] | Saudi Electricity Co [100.0%] |
Articles and Resources
References
- ↑ 1.000 1.001 1.002 1.003 1.004 1.005 1.006 1.007 1.008 1.009 1.010 1.011 1.012 1.013 1.014 1.015 1.016 1.017 1.018 1.019 1.020 1.021 1.022 1.023 1.024 1.025 1.026 1.027 1.028 1.029 1.030 1.031 1.032 1.033 1.034 1.035 1.036 1.037 1.038 1.039 1.040 1.041 1.042 1.043 1.044 1.045 1.046 1.047 1.048 1.049 1.050 1.051 1.052 1.053 1.054 1.055 1.056 1.057 1.058 1.059 1.060 1.061 1.062 1.063 1.064 1.065 1.066 1.067 1.068 1.069 1.070 1.071 1.072 1.073 1.074 1.075 1.076 1.077 1.078 1.079 1.080 1.081 1.082 1.083 1.084 1.085 1.086 1.087 1.088 1.089 1.090 1.091 1.092 1.093 1.094 1.095 1.096 1.097 1.098 1.099 1.100 1.101 1.102 1.103 1.104 https://web.archive.org/web/20210624171139/https://github.com/wri/global-power-plant-database/blob/13b6a3baaca73e84b1a549d14c274981abec775b/raw_source_files/WRI/Saudi%20Arabia.csv. Archived from the original on 24 June 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 2.3 https://www.power-technology.com/marketdata/riyadh-pp9-power-plant-block-a-b-saudi-arabia/?cf-view.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.18 3.19 3.20 3.21 3.22 3.23 3.24 3.25 3.26 3.27 3.28 3.29 3.30 3.31 3.32 3.33 3.34 3.35 3.36 3.37 3.38 3.39 3.40 3.41 3.42 3.43 3.44 3.45 3.46 3.47 3.48 3.49 3.50 3.51 3.52 3.53 3.54 3.55 3.56 3.57 3.58 3.59 3.60 3.61 3.62 3.63 3.64 3.65 3.66 3.67 3.68 3.69 3.70 3.71 3.72 3.73 3.74 3.75 3.76 3.77 3.78 3.79 3.80 3.81 3.82 3.83 3.84 3.85 https://web.archive.org/web/20201030203927/https://www.se.com.sa/en-us/Pages/OurActivitiesTowardsCommunity3.aspx. Archived from the original on 30 October 2020.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20221222210512/https://www.power-technology.com/projects/riyadh/. Archived from the original on 22 December 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 5.11 5.12 5.13 5.14 5.15 5.16 5.17 5.18 5.19 5.20 5.21 5.22 5.23 5.24 5.25 5.26 5.27 5.28 5.29 5.30 5.31 5.32 5.33 5.34 5.35 5.36 5.37 5.38 5.39 5.40 5.41 5.42 5.43 5.44 5.45 5.46 5.47 5.48 5.49 5.50 5.51 5.52 5.53 5.54 5.55 5.56 5.57 5.58 5.59 5.60 5.61 5.62 5.63 5.64 5.65 5.66 5.67 5.68 5.69 5.70 5.71 5.72 5.73 5.74 5.75 5.76 5.77 5.78 5.79 5.80 5.81 5.82 5.83 https://web.archive.org/web/20211125055103/https://www.ge.com/news/press-releases/ge-gains-additional-commitments-power-projects-saudi-arabia-expected-ge-scope-0. Archived from the original on 25 November 2021.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.0 6.1 6.2 6.3 6.4 6.5 6.6 6.7 (PDF) https://web.archive.org/web/20220529115513/https://johncockerill.com/wp-content/uploads/2020/04/John-Cockerill_Energy_HRSG_RIYADH.pdf. Archived from the original (PDF) on 29 May 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 7.16 7.17 7.18 7.19 https://www.saudconsult.com/en/projects/riyadh-power-plant-9.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 https://www.dmsprojects.net/saudi-arabia/projects/sec-pp9-combined-cycle-conversion/PRJ00022023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.00 9.01 9.02 9.03 9.04 9.05 9.06 9.07 9.08 9.09 9.10 9.11 9.12 9.13 9.14 9.15 9.16 9.17 9.18 9.19 https://web.archive.org/web/20220120083605/http://bemco-ipp.com/major-projects/243-riyadh-power-plant-no-9-combined-cycle-5-980-mw?tmpl=major-component&print=1. Archived from the original on 20 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.00 10.01 10.02 10.03 10.04 10.05 10.06 10.07 10.08 10.09 10.10 10.11 10.12 10.13 10.14 10.15 10.16 10.17 10.18 10.19 10.20 10.21 10.22 10.23 10.24 10.25 10.26 10.27 10.28 10.29 10.30 10.31 10.32 10.33 10.34 10.35 10.36 10.37 10.38 10.39 10.40 10.41 10.42 10.43 10.44 10.45 10.46 10.47 10.48 10.49 10.50 10.51 10.52 10.53 10.54 10.55 10.56 10.57 10.58 https://www.power-technology.com/marketdata/riyadh-pp9-power-plant-block-c-d-saudi-arabia/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.00 11.01 11.02 11.03 11.04 11.05 11.06 11.07 11.08 11.09 11.10 11.11 11.12 11.13 11.14 11.15 11.16 11.17 11.18 11.19 https://www.meed.com/new-sec-tender-puts-pp9-back-on-track/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 12.000 12.001 12.002 12.003 12.004 12.005 12.006 12.007 12.008 12.009 12.010 12.011 12.012 12.013 12.014 12.015 12.016 12.017 12.018 12.019 12.020 12.021 12.022 12.023 12.024 12.025 12.026 12.027 12.028 12.029 12.030 12.031 12.032 12.033 12.034 12.035 12.036 12.037 12.038 12.039 12.040 12.041 12.042 12.043 12.044 12.045 12.046 12.047 12.048 12.049 12.050 12.051 12.052 12.053 12.054 12.055 12.056 12.057 12.058 12.059 12.060 12.061 12.062 12.063 12.064 12.065 12.066 12.067 12.068 12.069 12.070 12.071 12.072 12.073 12.074 12.075 12.076 12.077 12.078 12.079 12.080 12.081 12.082 12.083 12.084 12.085 12.086 12.087 12.088 12.089 12.090 12.091 12.092 12.093 12.094 12.095 12.096 12.097 12.098 12.099 12.100 12.101 12.102 12.103 12.104 12.105 12.106 12.107 https://www.linkedin.com/in/muhammad-shoaib-khurshid-9301153b/?originalSubdomain=pk.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.00 13.01 13.02 13.03 13.04 13.05 13.06 13.07 13.08 13.09 13.10 13.11 13.12 13.13 13.14 13.15 13.16 13.17 https://web.archive.org/web/20210506220556/https://www.arabianbemco.com/major-projects/243-riyadh-power-plant-no-9-combined-cycle-5-980-mw?tmpl=major-component&print=1.
{{cite web}}
: Check|archive-url=
value (help); Missing or empty|title=
(help) - ↑ 14.0 14.1 14.2 14.3 14.4 14.5 14.6 14.7 https://web.archive.org/web/20240415211846/https://www.power-technology.com/data-insights/power-plant-profile-riyadh-pp9-power-plant-block-e-saudi-arabia/. Archived from the original on 15 April 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 15.00 15.01 15.02 15.03 15.04 15.05 15.06 15.07 15.08 15.09 15.10 15.11 15.12 15.13 15.14 15.15 https://www.meed.com/bemco-signs-up-for-riyadh-pp9-fast-track-job/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 16.0 16.1 16.2 16.3 https://web.archive.org/web/20220123152836/https://datasource.kapsarc.org/explore/dataset/electricity-generation-by-station-capacities-in-saudi-arabia/export/. Archived from the original on 23 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 17.0 17.1 https://data.opendatasoft.com/explore/embed/dataset/electricity-generation-by-station-capacities-in-saudi-arabia@kapsarc/table/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 18.00 18.01 18.02 18.03 18.04 18.05 18.06 18.07 18.08 18.09 18.10 18.11 18.12 18.13 https://www.spa.gov.sa/456224.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 19.0 19.1 https://www.alyaum.com/articles/116769/%D8%A7%D9%84%D9%85%D8%B4%D8%B1%D9%88%D8%B9-%D8%A7%D9%84%D8%AC%D8%AF%D9%8A%D8%AF.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 20.00 20.01 20.02 20.03 20.04 20.05 20.06 20.07 20.08 20.09 20.10 20.11 https://web.archive.org/web/20240415211936/https://www.power-technology.com/data-insights/power-plant-profile-riyadh-pp9-power-plant-block-f-saudi-arabia/. Archived from the original on 15 April 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 21.00 21.01 21.02 21.03 21.04 21.05 21.06 21.07 21.08 21.09 21.10 21.11 21.12 21.13 21.14 21.15 21.16 21.17 21.18 21.19 21.20 21.21 21.22 21.23 21.24 21.25 21.26 21.27 21.28 21.29 21.30 21.31 21.32 21.33 21.34 21.35 21.36 21.37 21.38 21.39 21.40 21.41 21.42 21.43 https://data.opendatasoft.com/explore/embed/dataset/list-of-power-plants-in-gcc-countries@kapsarc/table/?disjunctive.power_plant&disjunctive.city&disjunctive.country&disjunctive.state&basemap=jawg.sunny&location=5,24.0008,47.24.
{{cite web}}
: Missing or empty|title=
(help)
Additional data
To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.