Ruoqiang County Cogen power station (巴州若羌县热电联产项目, 新疆特变楼兰若羌2×350MW热电联产项目) is a power station under construction in Ruoqiang, Bayingolin Mongol Autonomous Prefecture, Xinjiang, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Ruoqiang County Cogen power station Ruoqiang, Bayingolin Mongol Autonomous Prefecture, Xinjiang, China 38.950112, 88.32697 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 38.950112, 88.32697

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 construction coal: unknown 350 supercritical 2024 (planned)
Unit 2 construction coal: unknown 350 supercritical 2024 (planned)

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Xinjiang TBEA Loulan New Energy Co Ltd [100%] TBEA Co Ltd [85.8%]; Xinjiang Joinworld Co Ltd [14.2%]
Unit 2 Xinjiang TBEA Loulan New Energy Co Ltd [100%] TBEA Co Ltd [85.8%]; Xinjiang Joinworld Co Ltd [14.2%]

Project-level coal details

  • Permit(s): , 新发改批复〔2022〕154号[1]

Background

The 2 × 350 MW cogen units were reportedly granted permission to build on 27 September 2022.[2]

In November 2022, it was reported that Xinjiang TBEA Loulan New Energy Company (a subsidiary of Xinjiang Tianchi Energy Co and TBEA) had invested in the construction of the 700 MW Ruoqiang power plant.[3] Construction of Unit 1 allegedly began in March 2023.[4] The supercritical power station's construction was expected to be complete in 2024, with operation anticipated in June of that year.[5]

Articles and Resources

References

  1. https://web.archive.org/web/20240125142043/https://sthjt.xinjiang.gov.cn/xjepd/sthjt_hjyxpj/202307/6bd517de669646029396183164463179.shtml. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. "巴州若羌县2×35万千瓦热电联产项目取得自治区发改委核准批复". 北极星火力发电网. 2022-09-30. Retrieved 2023-02-06.
  3. "特变电工:拟投建若羌2×350MW热电联产项目". BJX. 2022-11-28.
  4. 中国能建浙江火电承建的新疆若羌热电联产1号机组主体工程开工, BJX, 2023-03-07
  5. 新疆若羌热电联产1号机组主体工程开工, China Power, 2023-03-07

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.