Sabal Trail Gas Transmission Pipeline
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Sabal Trail Gas Transmission Pipeline is an operating natural gas pipeline in the southern United States.[1]
Location
The pipeline runs from Alexander City, Alabama, to Reunion, Florida.[2]
Project Details
- Operator: Sabal Trail Transmission, LLC (100%)[3]
- Owner: Sabal Trail Transmission, LLC (100%)[3]
- Parent: Enbridge (50%), Nextera Energy (42.5%), Duke Energy (7.5%)[4][5]
- Capacity: 830 million cubic feet per day[6]
- Length: 516 miles / 830 km[1][6]
- Diameter: 24-inches, 36-inches[3]
- Cost: US$3.2 billion[6]
- Status: Operating[1]
- Start Year: 2017[1][6]
Background
The project was developed in three phases. Sabal Trail Project Phase I included approximately 516 miles of interstate natural gas pipeline (86 miles in Alabama, 162 miles in Georgia, 268 miles in Florida) and, initially, at least two compressor stations at the beginning and end of the pipeline system.[7] A total of five stations along the pipeline was constructed by 2021. The entire pipeline will be capable of transporting one billion cubic feet per day or more of natural gas to serve local distribution companies, industrial users and natural gas-fired power generators in the Southeast markets.[8]
Sabal Trail Transmission, LLC (“Sabal Trail” is a joint venture of Enbridge, NextEra Energy, Inc. and Duke Energy and Duke Energy of Florida ("DEF").[4]
The Phase I of the pipeline entered commercial operation in June 2017.[9]
Environmental Concerns and Protests
In October 2014, a group of residents demonstrated protest against the pipeline.[10] In July 2015, around 40 protesters gathered at the Sabal Gas Transmission office citing concerns regarding the proximity of the pipelines with residential areas.[11] In November 2016, protesters gathered at the pipeline construction site raising awareness regarding pollution problems and possible threats to Georgia's water, residents, downstream aquatic life and animals. The demonstration was sponsored by WWALS Watershed Coalition.[12] Environmental concerns were raised against the project stating that the project threatened habitats of endangered species including crocodiles, manatees and sea turtles along its route.[13]
FERC ruling on GHG emissions
In August 2017 the U.S. Court of Appeals for the District of Columbia Circuit ruled that FERC failed to adequately consider climate impacts before approving the project.[14] In February 2018 FERC completed a supplementary review of the pipeline's impact and found that it would cause a 3.6 to 9.9 percent increase over Florida's 2015 emissions.[14] FERC has declined to set a standard for what constitutes "significant" impact on climate change, and in March 2018 FERC by a 3-2 vote reauthorized the pipeline.[15]
Financing
In April 2018, refinancing of the project's debt took place with the issuing of US$1.5 billion in bonds arranged by MUFG, Mizuho, Barclays and Citi.[16] The amount of initial financing and its sources for the US$3.2 billion project are not known.
Expansion Projects
Sabal Trail Project, Phase II
The expansion project will effect Alabama, Georgia, and Florida, USA. It will deliver natural gas to Florida Power and Light (FPL) and Duke Energy of Florida (DEF). It does not include adding any additional miles of pipeline.[6]
- Operator: Sabal Trail Transmission, LLC (100%)[3]
- Owner: Sabal Trail Transmission, LLC (100%)[3]
- Parent: Enbridge (50%), Nextera Energy (42.5%), Duke Energy (7.5%)[4][5]
- Capacity: 170 million cubic feet per day[6]
- Length:
- Status: Operating[17]
- Start Year: 2020[6]
Florida Power and Light Expansion Project/Phase III
According to the U.S.'s Energy Information Administration (EIA), the expansion will deliver natural gas to Florida Power and Light (FPL) and Duke Energy of Florida (DEF). The expansion project has been approved by the Federal Energy Regulatory Commission (FERC) and will add 75 million cubic feet per day.[6] The expansion will pass through Alabama, Georgia, and Florida.[18]
This phase of the project was scheduled to begin service on May 01, 2021. On April 7, 2021, Sabal Trail filed a request for an extension of time, until May 1, 2023, to complete construction of the project and place Phase III of the remaining facilities—two compressor units—into service. FERC granted that requested extension of time . On March 10, 2023, Sabal Trail Transmission LLC again requested the U.S. Federal Energy Regulatory Commission to grant an extension of time, until May 1, 2025, to complete Phase III of their Sabal Trail Project.[19]
- Operator: Sabal Trail Transmission, LLC (100%)[3]
- Owner: Sabal Trail Transmission, LLC (100%)[3]
- Parent: Enbridge (50%), Nextera Energy (42.5%), Duke Energy (7.5%)[4][5]
- Capacity: 75 million cubic feet per day[6]
- Length:
- Status: Proposed/Delayed[6]
- Start Year: 2025[18]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 Sabal Trail Gas Transmission Pipeline, Enbridge, accessed September 2017
- ↑ National Energy and Petrochemical Map , FracTracker, February 28, 2020
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 3.6 Enbridge’s Energy Infrastructure Assets Enbrdige, July 22, 2020
- ↑ 4.0 4.1 4.2 4.3 Spectra Energy Partners, LP. "Sabal Trail Transmission, LLC Announces Pricing of $1.5 Billion Debt Offering". www.prnewswire.com. Retrieved 2023-08-11.
- ↑ 5.0 5.1 5.2 "LINK® Informational Postings". infopost.enbridge.com. Retrieved 2023-08-11.
- ↑ 6.0 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 Natural Gas Data, Pipeline Projects Energy Information Agency, August 11, 2023
- ↑ "Sabal Trail Transmission Project". Hydrocarbons Technology. Retrieved 11 August, 2023.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ Sabal Trail Transmission, Sabal Trail Transmission, accessed January, 2018
- ↑ Sabal Trail put into commercial service, Suwanee Democrat, Jul. 7, 2017
- ↑ Joe Adgie, The Valdosta Daily Times. "Residents protests Sabal Trail". Valdosta Daily Times. Retrieved 2023-08-11.
- ↑ Carlton Fletcher. "Albany pipeline protesters take cause to Sabal Trail office | PHOTO GALLERY". Albany Herald. Retrieved 2023-08-11.
- ↑ Vaughn, Derrek (18 November, 2016). "WWALS Watershed Coalition protests pipeline". Valdosta Daily Times. Retrieved 2023-08-11.
{{cite news}}
: Check date values in:|date=
(help) - ↑ "Sinkhole raises collapse concerns at pipeline drilling site". First Coast News. Retrieved 18 June, 2017.
{{cite news}}
: Check date values in:|access-date=
(help) - ↑ 14.0 14.1 FERC splits on climate review, reapproves Sabal Trail, E&E News, Mar. 15, 2018
- ↑ ORDER ON REMAND REINSTATING CERTIFICATE AND ABANDONMENT, FERC, 162 FERC ¶ 61,233, Mar. 14, 2018
- ↑ Sabal Trail Pipeline (832KM) Refinancing 2018, IJGlobal, accessed Aug. 18, 2020
- ↑ In the first half of 2020, about 5 Bcf/d of natural gas pipeline capacity entered service U.S. Energy Information Agency, Aug. 24, 2020
- ↑ 18.0 18.1 U.S. natural gas pipeline projects, U.S. Energy Information Administration, April 29, 2021
- ↑ "Federal Register :: Request Access". www.federalregister.gov. Retrieved 2023-08-11.