Shenhai New power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Shenhai New power station (华润沈海热电厂等容量替换异地扩建项目) is an operating power station of at least 700-megawatts (MW) in Dadong, Shenyang, Liaoning, China. It is also known as 沈阳华润热电有限公司异地扩建2x350MW热电联产项目.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Shenhai New power station | Dadong, Shenyang, Liaoning, China | 41.91694, 123.514711 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 41.91694, 123.514711
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | Operating | coal: unknown | 350 | subcritical | 2024 |
Unit 2 | Operating[1] | coal: unknown | 350 | subcritical | 2024 (planned) |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Shenyang Huarun Thermal Power Co Ltd [100%] | China Resources Power Holdings Co Ltd [54.1%]; BOOM GO GROUP Ltd [39.3%]; Liaoning Grace Group Co Ltd [6.6%] |
Unit 2 | Shenyang Huarun Thermal Power Co Ltd [100%] | China Resources Power Holdings Co Ltd [54.1%]; BOOM GO GROUP Ltd [39.3%]; Liaoning Grace Group Co Ltd [6.6%] |
Background
Shenhai New power station is a proposed 2 x 350 MW coal plant in Dadong. It was planned to be a replacement of the 600 MW Shenhai power station that was commissioned in 1991. Both plants are majority-owned by China Resources.[2][3]
In 2020, the sponsor company had secured land use.[4]
Bidding information throughout 2022 indicated the project was undergoing preparation work.[5][6][7]
This project was actively moving forward based on bidding details,[8] but no details were available regarding permitting.
Construction of the power station began in March 2023 and was ongoing as of May 2023. Operation of the two units was expected in 2024.[9]
Articles and Resources
References
- ↑ "沈阳华润热电异地扩建2×350MW热电联产项目2号机组投产-北极星火力发电网". news.bjx.com.cn. 2024-12-19. Archived from the original on 2025-01-07. Retrieved 2024-12-19.
- ↑ "华润沈海热电厂2017年底或将搬迁改造," 北极星电力网新闻中心, 2013-7-31
- ↑ "沉寂了六年终于定了!沈海热电厂搬迁至朱尔屯," 北极星电力网新闻中心, 2019/11/19
- ↑ "定了!沈海热电厂异地重建选址进一步明确 占地约28.5万平," leju, 2020-10-12
- ↑ "华润热电异地扩建2×350MW热电联产项目勘察设计中标结果公告," BJX, 2022-03-15
- ↑ "沈阳华润热电异地扩建2×350MW热电联产项目影响评估招标," BJX, 2022-02-11
- ↑ "沈阳华润热电有限公司异地扩建2×350MW热电联产项目主体建筑招标," BJX, 2022-11-04
- ↑ "哈电集团汽轮机公司成功中标沈阳华润热电两台350MW热电联产工程汽轮机设备," Harbin, 2022-08-24
- ↑ "沈阳华润热电异地扩建项目“加速跑”," ln.chinanews.com, 2023-05-04