Shenmu Shenxin power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Shenmu Shenxin power station (信发神木神信热电厂) is a power station under construction in Jinjie, Shenmu, Yulin, Shaanxi, China. It is also known as 神木神信热电2x660MW发电工程.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Shenmu Shenxin power station | Jinjie, Shenmu, Yulin, Shaanxi, China | 38.688762, 110.239962 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 38.688762, 110.239962
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | construction | coal: unknown | 660 | ultra-supercritical | 2024 (planned) |
Unit 2 | construction | coal: unknown | 660 | ultra-supercritical | 2024 (planned) |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Shenmu Shenxin Thermal Power Co Ltd [100%] | Ningbo SHENDIAN Enterprise Management Partnership LP [100.0%] |
Unit 2 | Shenmu Shenxin Thermal Power Co Ltd [100%] | Ningbo SHENDIAN Enterprise Management Partnership LP [100.0%] |
Project-level coal details
- Permit(s): 陕发改能电力〔2021〕196号[1]
Background on Project
Shenmu Shenxin power station is a proposed 2 x 660 MW coal plant in Jinjie Town (Jinjiezhen), Shenmu County. Unit 1 was permitted for construction in February 2021.[2][3] In March 2022, a permitting quota for one 660 MW unit which belonged to Hengli Energy was transferred to the proposed power project. [4] By April 2022, it appeared both units were permitted (陕发改能电力[2022]557 号). In August 2022, the Environmental Impact Assessment report for both units had also been approved.[5][6]
Construction reportedly began in September 2022,[7] and by November 2022, the supercritical project's ground foundation was nearly complete.[8] In July 2023, reports stated that construction was still in full swing.[9] Planet satellite imagery showed significant progress in the power station's construction from January to July of 2023.
The power project was expected to be ready for operation in February 2024.[7]
Articles and Resources
References
- ↑ https://sndrc.shaanxi.gov.cn/fgwj/2021nwj/eayEja.htm.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "660MW!神木神信电厂首台机组获得核准批复" 北极星电力网新闻中心, 2021/4/29
- ↑ 陕西省发展和改革委员会关于神木神信热电有限公司首台1×660MW超超临界机组项目节能报告的审查意见 Shaanxi Provincial Development and Reform Commission, 2021-08-06
- ↑ 关于榆神恒力电厂首台机组调整建设的公示 Shaanxi Government, 2022-03-03
- ↑ 关于神木神信热电有限公司2×660MW发电工程环境影响报告书的批复 Sohu, 2022-08-09
- ↑ 关于神木神信电厂第二台66 万千瓦机组核准的批复 Xinfa Group, April 2022
- ↑ 7.0 7.1 陕北最高的间冷塔!预计2024年2月具备运转条件 Yiyouliao, accessed: July 2023
- ↑ 【一线动态】神木神信热电有限公司2×660MW发电工程基础施工进入尾声 陕西建工, 2022-11-04
- ↑ 【项目】火电|2×1000MW!襄阳宜城首台机组通过168!/2x660MW!神木神信电厂建设如火如荼 MP Weixin, 2023-07-15