Star Peak geothermal power plant

From Global Energy Monitor
This article is part of the
Global Geothermal Power Tracker, a Global Energy Monitor project.
Report an error

Star Peak geothermal power plant is an operating geothermal power plant in Pershing County, Nevada, United States.

Project Details

Table 1: Unit-level project details for Star Peak geothermal power plant

Unit name Status Commissioning year Nameplate capacity Technology
3500 Operating[1] 2022[1] 4 MW[1] Binary cycle[1]
5100A Operating[1] 2022[1] 5 MW[1] Binary cycle[1]
5100B Operating[1] 2022[1] 5 MW[1] Binary cycle[1]
5200 Operating[1] 2022[1] 5 MW[1] Binary cycle[1]
STEAM Operating[1] 2022[1] 3 MW[1] Binary cycle[1]

Location

Table 2: Unit-level location details for Star Peak geothermal power plant

Unit name Location Coordinates (WGS 84)
3500 Pershing County, Nevada, United States 40.5321, -118.272 (exact)
5100A Pershing County, Nevada, United States 40.5321, -118.272 (exact)
5100B Pershing County, Nevada, United States 40.5321, -118.272 (exact)
5200 Pershing County, Nevada, United States 40.5321, -118.272 (exact)
STEAM Pershing County, Nevada, United States 40.5321, -118.272 (exact)

The map below shows the exact locations of the geothermal power plant units:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit the Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 https://web.archive.org/web/20221028021258/https://www.eia.gov/electricity/data/eia860/. Archived from the original on 28 October 2022. {{cite web}}: Missing or empty |title= (help)