Sulb Bahrain Al Hidd steel plant
From Global Energy Monitor
(Redirected from Sulb Bahrain steel plant)
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Sulb Bahrain Al Hidd steel plant (شركة صلب (Arabic)) is a direct reduced iron-electric arc furnace (DRI-EAF) steel plant operating in Al Hidd, Muharraq, Bahrain.
Location
The map below shows the exact location of the plant in Al Hidd, Muharraq, Bahrain:
- Location: Al Hidd, Bahrain
- Coordinates (WGS 84): 26.198152, 50.679893 (exact)
Background
Sulb Bahrain Al Hidd steel plan started operating in 2012. It is a joint venture between Foulath Holding Company and Yamato Kogyo Company. [1] In 2023, the company commissioned SMS group to revamp the plants 130 tons electric arc furnace to enhance its efficiency and productivity.[2]
Plant Details
Table 1: General Plant Details
Plant status | Announced date | Start date |
---|---|---|
Operating[3] | 2009[4] | 2012[3] |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Parent company GEM ID | Owner | Owner company GEM ID |
---|---|---|---|---|
Foulath Holding BSCC [50.0%]; Yamato Kogyo Co Ltd [50.0%] | 5001427072 [50%]; 4295878941 [50%] | E100000130965 [50%]; E100001010196 [50%] | SULB Bahrain[3] | E100000131139 |
Table 3: Process and Products
Steel product category | Steel products | Steel sector end users | ISO 14001 | ISO 50001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|---|
crude; semi-finished; finished rolled[5] | beams, columns, channels, angles, flat sheets, flat bars, billets, DRI[5] | automotive; building and infrastructure; energy; transport[6] | 2022[7] | 2022[8] | DRI, EAF[5] | 1 Midrex DRI plant (1.6 MTPA, began in 2013); 1 EAF (130 tons)[5][9][10] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Capacity operating status* | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|
operating | 1100 TTPA[11] | 1100 TTPA[11] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Capacity operating status* | Sponge iron/DRI capacity | Nominal iron capacity (total) |
---|---|---|
operating | 1600 TTPA[11] | 1600 TTPA[11] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Pellets |
---|
12000 TTPA[12] |
Table 7: Actual Crude Steel Production by Year (thousand tonnes per annum)
Year | EAF Production | Total (all routes) |
---|---|---|
2020 | – | – |
2021 | – | – |
2022 | 1270 TTPA[13] | 1270 TTPA |
Table 8: Actual Crude Iron Production by Year (thousand tonnes per annum)
Year | DRI Production | Total (all routes) |
---|---|---|
2020 | – | – |
2021 | – | – |
2022 | 1620 TTPA[13] | 1620 TTPA |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "SULB". www.sulb.com.bh. Retrieved 2023-09-27.
- ↑ shivani dhruv. "SULB commissions SMS group for the modernisation of an electric arc". technicalreviewmiddleeast.com. Retrieved 2023-09-27.
- ↑ 3.0 3.1 3.2 https://web.archive.org/web/20221211144708/http://sulb.com.bh/. Archived from the original on 11 December 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230505194918/https://www.sulb.com.bh/. Archived from the original on 05 May 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 5.3 https://web.archive.org/web/20221211144708/http://sulb.com.bh/. Archived from the original on 11 December 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230505194918/https://www.sulb.com.bh/. Archived from the original on 05 May 2023.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20221211144708/http://sulb.com.bh/. Archived from the original on 11 December 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://www.sulb.com.bh/files/certificates/ISO%2050001%20(SULB%20Bahrain).pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220320173526/https://www.midrex.com/about-midrex/midrex-plants/. Archived from the original on 20 March 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230331185838/https://min-met.com/blog/sulb-to-modernize-electric-arc-furnace-and-four-strand-concast/. Archived from the original on 31 March 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 11.2 11.3 https://web.archive.org/web/20221211144708/http://sulb.com.bh/. Archived from the original on 11 December 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://www.zawya.com/en/markets/bahrain-steel-achieves-record-production-in-2021-k9msnoe8.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 https://web.archive.org/web/20240119005422/https://www.steelguru.com/steel/2023-sulb-companys-soaring-steel-success. Archived from the original on 19 January 2024.
{{cite web}}
: Missing or empty|title=
(help)