Talahao Coal Mine
This article is part of the CoalSwarm coverage of China and coal |
Sub-articles: |
Talahao Coal Mine (内蒙古伊泰煤炭股份有限公司塔拉壕煤矿) is located in Dongsheng of Ordos City in Inner Mongolia. The annual production capacity of it is designed to be 6 million tonnes(Mt) a year.
Location
The undated satellite photo below shows the coal mine located in Talahao Town, Dongsheng, Ordos, Inner Mongolia
Coal Mine Background
The construction started its preparation since June 2009. Until September 26th 2012, it was approved by the National Development and Reform Commission (NDRC) for construction, with a total production capacity of 6Mt/year.[1]
The construction work began starting from September 2013. In September 2016, it entered into the period of experimental operation.[2]
By December 2017, it successfully passed the completion and acceptance of work prior to official operation.[3]
Project Details
- Sponsor: Inner Mongolia Yitai Coal Co.
- Parent Company: Yitai Group (40.17%), B shares(40.18%), H shares(10.02%)
- Location: Talahao Town, Dongsheng, Ordos, Inner Mongolia
- GPS Coordinates: 39.79013,110.156685
- Status: Operating
- Production Capacity: 6 Mt/year
- Total Resource: 867.38Mt [4]
- Minable Reserves: 531.61Mt
- Coal Type: Bituminous
- Mine Size: 42.62 km2 [5]
- Mine Type: Underground
- Start Year: 2018
- Source of Financing:
Articles and resources
References
- ↑ "内蒙古自治区万利矿区塔拉壕煤矿项目通过核准"发改委, 2012/09/26
- ↑ "鄂尔多斯市三建设项目通过取水许可核验"黄河上中游管理局 , 2017/05/02
- ↑ "鄂尔多斯两煤炭项目竣工 年产量1000万吨"中国能源网 , 2018/02/06
- ↑ "内蒙古伊泰煤炭股份有限公司塔拉壕矿井竣工环境保护验收调查报告 "Page 44, 中华人民共和国生态环境部, 2017/08
- ↑ "内蒙古伊泰煤炭股份有限公司塔拉壕煤矿及选煤厂水土保持设施通过水利部验收"水利部, 2017/09/26