Talimarjan power station (Талимарджанская ТЭС (Russian)) is an operating power station of at least 1700-megawatts (MW) in Nuristan, Nishon, Qashqadaryo, Uzbekistan with multiple units, some of which are not currently operating. It is also known as Talimarjan 2 TPP (Units CC3, CC4), Tolimarjon, Talimarjan 1 TPP (Units CC1, CC2).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Talimarjan power station Nuristan, Nishon, Qashqadaryo, Uzbekistan 38.481232, 65.62977 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • CC1, CC2, CC3, CC4, ST1: 38.481232, 65.62977

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
CC1 Operating[2][3] fossil gas: natural gas[4][5] 450[6][5] combined cycle[2] not found[7] 2016[2][3]
CC2 Operating[2][3] fossil gas: natural gas[4][5] 450[6][5] combined cycle[2] not found[7] 2017[2][3]
CC3 Construction[8][9][10][11][12][13] fossil gas: natural gas[14] 532.5[8] combined cycle[8] not found[7] 2025 (planned)[15][8][16][17][13]
CC4 Construction[8][9][10][11][12][13] fossil gas: natural gas[14] 532.5[8] combined cycle[8] not found[7] 2025 (planned)[15][8][16][17][13]
ST1 Operating[2][3] fossil gas: natural gas[4][18] 800[6][19] steam turbine[4][20] not found[7] 2005[3][19]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
CC1 Thermal Power Stations JSC [100%][21][5] Thermal Power Stations JSC [100.0%]
CC2 Thermal Power Stations JSC [100%][21][5] Thermal Power Stations JSC [100.0%]
CC3 Thermal Power Stations JSC [100%][21][5] Thermal Power Stations JSC [100.0%]
CC4 Thermal Power Stations JSC [100%][21][5] Thermal Power Stations JSC [100.0%]
ST1 Thermal Power Stations JSC [100%][21][5] Thermal Power Stations JSC [100.0%]

Background

JSC "Thermal Power Plants" hosted the ceremony of signing an agreement between JSC "Talimarjan TPP" and INTECSA Ingeniera Industrial S.A. and Mitsubishi Corporation for the construction of CC3 and CC4 units. This project will be implemented at the expense of concessional loans from the Asian Development Bank. Two combined-cycle plants with a total capacity of at least 900 MW will be built by 2025.[22]

In February 2023, Mitsubishi Power, a power solutions brand of Mitsubishi Heavy Industries, Ltd. (MHI), received an order for two M701F gas turbines, two steam turbines, and auxiliary equipment for the project. In addition to providing the gas turbines and steam turbines, Mitsubishi Power will also provide technical advisers to the site to support installation, commissioning and the commercial operation of the units.[23]

The construction commenced in July 2023 and is expected to be completed by the end of 2025. The total installed capacity of the new units will reach 1,065 MW. The cost of the project is estimated to be USD 771.5 million. The new power generation facilities are aimed to provide reliable power supply to consumers in the Samarkand and Bukhara regions, seven pumping stations on the Karshi Main Canal and many other settlements. Once operational, the plant will additionally produce 8.5 million MWh of electricity per year.[24]

In July 2024, the construction was still in progress. All rebar and concrete work related to the foundation of the combined-cycle turbines had been completed. In addition to Intecsa Ingeniera Industrial S.A. andMitsubishi Corporation, construction specialists from Turkish Çalik Enerji have been engaged in the project.[25] The new units are expected to be commissioned in Q4 2025. The cost of the project has reached USD 945 million.[26]

Ownership

In September 2022, the Uzbek authorities signed an agreement with United Arab Emirates' Mubadala Investment Company and Abu Dhabi National Energy Company (TAQA) to set up a joint venture that will operate the Talimarjan power station. The volume of foreign investment will be about USD 1 billion, 700 million of which will be the repayment of loans that Talimarjan Thermal Power Plant JSC had attracted earlier.[27][28] The binding agreements will see Mubadala and TAQA each acquire a 40% stake in two gas-fired power plants and the assumption of associated operations and maintenance activities. Thermal Power Plants JSC will retain the remaining 20% stake in each plant.[29]

Articles and Resources

References

  1. https://www.google.com/maps/place/Talimarjon+IES/@38.4812345,65.6284686,875m/data=!3m1!1e3!4m5!3m4!1s0x3f494507cb0e37b7:0x971994c3576ec4e!8m2!3d38.4805873!4d65.6304323. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 https://web.archive.org/web/20210629215938/https://menafn.com/1101405556/Two-combined-cycle-plants-at-Talimarjan-TPP-in-Uzbekistans-Kashkadarya-switch-off-again. Archived from the original on 29 June 2021. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 https://web.archive.org/web/20230403060949/https://taltes.uz/ru/jamiyat-bugungi-kunda/. Archived from the original on 03 April 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 (PDF) https://web.archive.org/web/20211101223131/https://openjicareport.jica.go.jp/pdf/248099.pdf. Archived from the original (PDF) on 01 November 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 https://web.archive.org/web/20211025080256/https://aykan.uz/en/news/na-talimardzhanskoi-tes-pushchena-v-stroi-vtoraia-parogazovaia-ustanovka. Archived from the original on 25 October 2021. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 6.2 https://web.archive.org/web/20220912075138/https://interfax.com/newsroom/top-stories/83018/. Archived from the original on 12 September 2022. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 7.2 7.3 7.4 (PDF) https://web.archive.org/web/20220121015719/http://energo-cis.ru/wyswyg/file/Uzbekistan.pdf. Archived from the original (PDF) on 21 January 2022. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 8.2 8.3 8.4 8.5 8.6 8.7 https://web.archive.org/web/20221003063717/http://minenergy.uz/en/lists/view/77. Archived from the original on 03 October 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  9. 9.0 9.1 https://web.archive.org/web/20210629215830/https://taltes.uz/?page_id=1650&lang=ru. Archived from the original on 29 June 2021. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 https://web.archive.org/web/20211101224719/https://uz.sputniknews.ru/20201105/V-Uzbekistane-obyavlen-tender-na-modernizatsiyu-Talimardzhanskoy-TES-15330849.html. Archived from the original on 01 November 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  11. 11.0 11.1 https://web.archive.org/web/20220430084602/https://minenergy.uz/ru/news/view/895. Archived from the original on 30 April 2022. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 https://web.archive.org/web/20221121132652/https://www.gazeta.uz/ru/2022/11/17/talimarjan-tes/. Archived from the original on 21 November 2022. {{cite web}}: Missing or empty |title= (help)
  13. 13.0 13.1 13.2 13.3 https://web.archive.org/web/20230726074354/https://www.spot.uz/ru/2023/07/25/talimarjon-expand/. Archived from the original on 26 July 2023. {{cite web}}: Missing or empty |title= (help)
  14. 14.0 14.1 (PDF) https://web.archive.org/web/20210629213644/https://openjicareport.jica.go.jp/pdf/12119723.pdf. Archived from the original (PDF) on 29 June 2021. {{cite web}}: Missing or empty |title= (help)
  15. 15.0 15.1 https://web.archive.org/web/20220701174912/https://minenergy.uz/ru/news/view/1714. Archived from the original on 01 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  16. 16.0 16.1 https://web.archive.org/web/20221123094034/https://minenergy.uz/ru/news/view/2264. Archived from the original on 23 November 2022. {{cite web}}: Missing or empty |title= (help)
  17. 17.0 17.1 https://web.archive.org/web/20230210025147/https://power.mhi.com/news/20230209.html. Archived from the original on 10 February 2023. {{cite web}}: Missing or empty |title= (help)
  18. (PDF) https://web.archive.org/web/20220709150046/https://www.adb.org/sites/default/files/project-document/73055/43151-023-uzb-emr-01.pdf. Archived from the original (PDF) on 09 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  19. 19.0 19.1 (PDF) https://web.archive.org/web/20220810225520/http://www.inogate.org/documents/10%20Ravshan%20Artykov%20Uzbekenergo%20ENGLISH.pdf. Archived from the original (PDF) on 10 August 2022. {{cite web}}: Missing or empty |title= (help)
  20. https://web.archive.org/web/20210629220435/https://www.azernews.az/region/161422.html. Archived from the original on 29 June 2021. {{cite web}}: Missing or empty |title= (help)
  21. 21.0 21.1 21.2 21.3 21.4 https://tpp.uz/ru/page/proizvodstvennye-pokazateli. {{cite web}}: Missing or empty |title= (help)
  22. https://web.archive.org/web/20221123094034/https://minenergy.uz/ru/news/view/2264. {{cite web}}: |archive-url= requires |archive-date= (help); Missing or empty |title= (help)
  23. "Mitsubishi Power Receives Order from Uzbekistan for Two M701F Gas Turbines and Two Steam Turbines -- For Talimarjan-2 TPP Project in Uzbekistan --". Mitsubishi Power. February 9, 2023. Retrieved May 3, 2023.{{cite web}}: CS1 maint: url-status (link)
  24. "На Талимарджанской ТЭС начали строить новые энергоблоки на 1 ГВт". www.spot.uz. July 25, 2023. Retrieved November 6, 2023.{{cite web}}: CS1 maint: url-status (link)
  25. "В рамках инвестиционного проекта на Талимарджанская ТЭС продолжается строительство парогазовых установок №4-5 общей мощностью 1065 МВт". minenergy.uz. July 16, 2024. Retrieved November 15, 2024.{{cite web}}: CS1 maint: url-status (link)
  26. "Projects and modernization works". Thermal Power Plants JSC. Retrieved November 14, 2024.{{cite web}}: CS1 maint: url-status (link)
  27. "UAE's Mubadala, Taqa to invest $1 bln in Uzbekistan's Talimarjan power plant". Interfax. September 12, 2022. Retrieved November 6, 2023.{{cite web}}: CS1 maint: url-status (link)
  28. "Construction of 1 GW capacity power units launched at Talimarjan TPP". The Tashkent Times. July 27, 2023. Retrieved November 6, 2023.{{cite web}}: CS1 maint: url-status (link)
  29. "Mubadala, Taqa ink agreements to invest in Uzbekistan's power sector". gulfbusiness.com. September 11, 2022. Retrieved November 15, 2024.{{cite web}}: CS1 maint: url-status (link)