Tambeyskoye-Bovanenkovo Gas Pipeline
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Tambeyskoye-Bovanenkovo Gas Pipeline (магистральный газопровод от Тамбейского месторождения до СМГ «Бованенково-Ухта» (1 нитка)) is a proposed gas pipeline.[1]
Location
The pipeline will run from the Tambeyskoye Oil and Gas Field to the Karskaya compressor station, Yamalo-Nenets Autonomus Okrug, where it would connect to Bovanenkovo-Ukhta Gas Pipeline, Segment 1 (Bovanenkovo-Ukhta 1 Gas Pipeline).
Project details
- Operator: Gazprom Dobycha Tambey[1]
- Owner: Gazprom Dobycha Tambey[2]
- Parent company: Gazprom PJSC, RusGazDobycha JSC[3]
- Capacity: 38.4 bcm/y[1]
- Length:
- Diameter: 1,400 mm[1]
- Status: Proposed[1]
- Start Year:
- Cost:
- Financing:
- Associated infrastructure: Tambeyskoye Oil and Gas Field, Bovanenkovo-Ukhta Gas Pipeline
Background
The proposed pipeline will connect the Tambeyskoye oil and gas field to the Bovanenkovo-Ukhta 1 Gas Pipeline at the Karskaya compressor station. Comprehensive engineering surveys have been completed in 2024.[1] A tender for performing archaeological research is scheduled to be announced by Gazprom in July 2024.[4]
Route
The pipeline will run from the Tambeyskoye oil and gas field (more specifically, North-Tambeyskoye) to the Karskaya compressor station, Yamalo-Nenets Autonomus Okrug, where it would connect to Bovanenkovo-Ukhta Gas Pipeline, Segment 1 (Bovanenkovo-Ukhta 1 Gas Pipeline).
To find the starting point for the route, a segment 33 km was traced from the Tambey village to the north; that is the approximate location of the North-Tambeyskoye oil and gas field, according to official documents.[1]
To find the end point for the route, a GPS coordinate for Karskaya compressor station was obtained[5] and used as a mid-point on the route since as of July 2024 the compressor station was still under construction.[1] Finally, the route was connected to the operating Bovanenkovo-Ukhta 1 Gas Pipeline at the Gas Distribution Point 1, where Bovanenkovo-Ukhta 1 Gas Pipeline originates.[6]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 "ПРОЕКТНАЯ ДОКУМЕНТАЦИЯ" (PDF). gazdobtambey.ru. February 2024. Retrieved June 25, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "О компании". Gazrpom Dobycha Tambey. 2023. Retrieved June 25, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "ПРИНЯТО РЕШЕНИЕ О СОЗДАНИИ СОВМЕСТНОГО ПРЕДПРИЯТИЯ ООО «ТАМБЕЙ ГАЗДОБЫЧА»" (PDF). nedra.gazprom.ru. May 2021. Retrieved June 25, 2025.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Выполнение археологических исследований (проведение историко-культурной экспертизы путем археологической разведки земель подлежащих воздействию строительных и иных работ) по объекту «Обустройство меловых отложений Тамбейского месторождения. Магистральный газопровод от Тамбейского месторождения до СМГ «Бованенково – Ухта» (1 нитка)». Участок перетрассировки в районе КС «Карская»". zakupki.kontur.ru. June 21, 2024. Retrieved June 26, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Линейная компрессорная станция КС Карская". Energybase.ru. July 17, 2024. Retrieved July 17, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Relation: Бованенково — Ухта 1 (8197672)". OpenStreetMap. July 17, 2024. Retrieved July 17, 2024.
{{cite web}}
: CS1 maint: url-status (link)