Texas Eastern Transmission (TETCO) Gas Pipeline

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Texas Eastern Transmission (TETCO) Gas Pipeline is an operating natural gas pipeline with additional expansions that are proposed and operating.[1]

Location

The pipeline runs from the Gulf of Mexico in Texas and Louisiana up through Mississippi, Arkansas, Tennessee, Missouri, Kentucky, Illinois, Indiana, Ohio, and Pennsylvania to deliver gas in the New York City area.

Loading map...

Project details

  • Operator: Texas Eastern Transmission LP
  • Owner: Enbridge[2]
  • Parent company: Enbridge
  • Capacity: 11,690 Million cubic feet per day[3]
  • Length: 8825 mi[3]
  • Status: Operating[3]
  • Start year: 1942

Background

Texas Eastern Transmission (TETCO) is operated by Texas Eastern Transmission, LP, which is owned by Enbridge.[4]

Spectra Energy and Conocophillips have proposed a joint expansion project called the TEMAX Project that would add 33 miles of pipeline to the system, stretching from Clarington, Ohio to Delta, Pennsylvania. It would add 395 million cubic feet per day of capacity and cost $500 million. The project includes construction of pipeline, looping and replacement of compressor stations and is is preparing to pre-file with FERC.[5]

In January of 2019 an explosion in the pipeline injured two people and destroyed two homes in Noble County, Ohio.[6]

Expansion projects

TEMAX Pipeline Expansion

In 2008, Spectra and ConocoPhillips announced a proposed pipeline called the TEMAX Pipeline. Gas would run through the TETCO Pipeline system, forming an agreement to deliver up to 395 million cubic feet per day of Rocky Mountain natural gas to the U.S. Northeast through the planned pipeline expansion. The expansion will start in Clarington, Ohio, running through Spectra’s Texas Eastern Transmission pipeline system to Delta, Pennsylvania.[7][8]

There have been no development updates since 2008 and the project is presumed to be cancelled.

  • Operator: Texas Eastern Transmission[9]
  • Owner: Spectra; ConocoPhillips
  • Parent company: Spectra; ConocoPhillips
  • Capacity: 395 MMcf/d
  • Length: 33 mi
  • Status: Cancelled
  • Start year:

Texas Eastern Appalachia to Market (TEAM)

The pipeline project includes the installation of new pipeline and upgrading of existing pipeline and compressors along the TETCO system. There have been multiple TEAM expansions.

In October 2008, TETCO held an open season for the TEAM expansion project.[10] In September 2011, FERC published the environmental assessment of Texas Eastern Appalachia to Market 2012 Expansion Project. The project involved installation of 17.3 miles of 36-inch-diameter natural gas transmission pipeline in Greene, Fayette, Franklin, Adams and Fulton Counties, Pennsylvania. TETCO also proposed to abandon approximately 11.3 miles of 24-inch-diameter pipeline in Franklin and Adams Counties, Pennsylvania.[11] In October 2012, TETCO completed the expansion.

  • Operator: TETCO
  • Current capacity: 200 Mmcf/d[9]
  • Length: 17.3 miles / 28 km[9]
  • Diameter: 36 inches[9]
  • Status: Operating
  • Start Year: 2012
  • Cost: US $197 million[9]


In November 2014, TETCO completed TETCO TEAM 2014 expansion. TEAM 2014 involved construction of approximately 33.4 miles of 36-inch-diameter natural gas transmission pipeline comprised of seven separate pipeline loops in Pennsylvania, and modification of existing pipeline facilities in Pennsylvania, West Virginia, Ohio, Kentucky, Tennessee, Alabama, and Mississippi.[12][13]

Loading map...
  • Operator: TETCO
  • Current capacity: 600 Mmcf/d[9]
  • Proposed capacity:
  • Length: 34 miles / 55 km[9]
  • Diameter: 36 inches[9]
  • Status: Operating
  • Start Year: 2014
  • Cost: US $500 million[9]


In November 2021, TETCO completed the installation of additional looping on the segment in Westmoreland, Berks, Fayette counties, Pennsylvania

  • Operator: TETCO
  • Current capacity: 18 Mmcf/d[9]
  • Length: 1 mile / km[9]
  • Diameter: 30 inches[9]
  • Status: Operating
  • Start Year: 2021
  • Cost: US $22 million[9]

Ohio Pipeline Energy Network (OPEN) Gas Pipeline

The pipeline runs from Columbiana County, Ohio, to Monroe County, Ohio.

Loading map...
  • Operator: Texas Eastern Transmission LP
  • Owner: Enbridge
  • Parent Company: Enbridge
  • Current capacity: 550 Million cubic feet per day[14][15][16]
  • Length: 76 miles / 122 km[14]
  • Diameter: 30 inches[14][17]
  • Status: Operating
  • Start Year: 2015[9]
  • Cost: $468 million[14][16]

In December 2011, Chesapeake Energy, American Electric Power and Spectra Energy Corp announced a pipeline expansion of the Texas Eastern system, connecting Utica and Marcellus shale in Ohio to markets in East and South.[18][19] U.S. Federal Energy Regulatory Commission approved the project on 02 December, 2014.[20] Ohio Pipeline Energy Network project was originally scheduled to become operational in November 2015, but the mainline portion of the project, which is the reverse flow along part of the existing TETCO mainline began service in mid-September.[21]

Texas Eastern Appalachian Lease (TEAL) Gas Pipeline

The extension would begin near the village of Bern, Ohio and turn north at Clarington, Ohio.

Loading map...

The Texas Eastern Appalachian Lease (TEAL) pipeline would be operated by Texas Eastern Transmission, LP, which is owned by Enbridge.[22] The TEAL project would include installation of a 4.4-mile pipeline loop in Ohio, a 1,790 feet of pipeline to connect with the Nexus Gas Transmission pipeline in Ohio, and additional natural gas compressor facilities in Ohio.[23]

The Phase 1 and Phase 2 of the expansion project was completed in November 2018 and April 2019, respectively, beginning service in 2018 and 2019.[24][9]

  • Operator: Texas Eastern Transmission, LP
  • Owner: Enbridge
  • Parent Company: Enbridge
  • Current capacity: 950 Million cubic feet per day[9]
  • Length: 5 miles / 8 km[9]
  • Status: Operating
  • Start Year: 2019[9]
  • Cost: US $185 million[9]

Cameron Expansion

In 2019, Texas Eastern Transmission applied for an expansion project in Louisiana called the Cameron Expansion Project.[9] According to the U.S. Energy Information Administration, as of April 2021 the project had been approved but had not yet entered construction.[9] In September 2021 it was reported that the project was under construction and would be commissioned within two months.[25] The project was completed in December 2021.[9]

  • Operator: Texas Eastern Transmission LP[26]
  • Owner: Enbridge
  • Parent company: Enbridge
  • Capacity: 750 MMcf/d[26]
  • Length: 0.2 mi[26]
  • Length: 20 in[26]
  • Length: US$149 million[26]
  • Status: Operating
  • Start year: 2021[26]

Middlesex Expansion

The expansion project interconnects with the Transco Gas Pipeline and the Transco Gas Pipeline's Woodbridge Lateral, ultimately delivering natural gas to 725 MW Woodbridge Energy Center combined cycle power plant. The expanded capacity is in New Jersey, USA. Developers have applied with the Federal Energy Regulatory Commission.[26]

According to the U.S. Energy Information Administration, as of April 2021 the project was under construction.[26] It was completed in September 2021.[26]

Loading map...
  • Operator: Texas Eastern Transmission LP[26]
  • Owner: Enbridge
  • Parent company: Enbridge
  • Capacity: 264 MMcf/d[26]
  • Length: 1.75 mi[26]
  • Diameter: 16, 20 in[26]
  • Cost: US$52 million[26]
  • Status: Operating[9]
  • Start year: 2021[26]

Venice Extension Project

Loading map...


The extension project is intended to expand TETCO's infrastructure to connect to facilitate delivery to Plaquemines LNG Terminal and better connect to Gulf Coast LNG export markets.[27]

  • Operator: Texas Eastern Transmission LP[26]
  • Owner: Enbridge
  • Parent company: Enbridge
  • Capacity: 1260 MMcf/d[26]
  • Length: 3 mi[26]
  • Diameter: 42 in[26]
  • Cost: US$360.3 million[26]
  • Status: Proposed[26]
  • Start year: 2024[26]

Articles and resources

References

  1. Texas Eastern Transmission (TETCO) Gas Pipeline, Enbridge website, accessed January 2018
  2. "https://infopost.enbridge.com/infopost/TEHome.asp?Pipe=TE". {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  3. 3.0 3.1 3.2 Enbridge’s Energy Infrastructure Assets Enbrdige, July 22, 2020
  4. Company Overview of Texas Eastern Transmission, LP, Bloomberg, accessed January 2018
  5. Planned Projects, Pipeline News, accessed October 2018
  6. Enbridge pipeline explosion in Ohio damages homes, sends flames shooting into sky, Global News, accessed January 2019
  7. Spectra, Conoco in Rockies gas shipment pact, Reuters, May 21, 2008
  8. Planned Pipelines, Pipeline News, accessed October 2018
  9. 9.00 9.01 9.02 9.03 9.04 9.05 9.06 9.07 9.08 9.09 9.10 9.11 9.12 9.13 9.14 9.15 9.16 9.17 9.18 9.19 9.20 9.21 9.22 "Natural Gas Data - U.S. Energy Information Administration (EIA)". www.eia.gov. Retrieved 2023-08-28.
  10. "Texas Eastern Appalachia to Market - Wikimarcellus". waytogoto.com. Retrieved 2023-08-30.
  11. "Federal Register :: Request Access". www.federalregister.gov. Retrieved 2023-08-30.
  12. "Federal Register :: Request Access". www.federalregister.gov. Retrieved 2023-08-30.
  13. "Spectra Energy Names TEAM 2014 Expansion Anchor Shippers". Hart Energy. 13 April, 2012. Retrieved 30 August, 2023. {{cite web}}: Check date values in: |access-date= and |date= (help)CS1 maint: url-status (link)
  14. 14.0 14.1 14.2 14.3 "New pipeline to carry Ohio gas". The Columbus Dispatch. Retrieved 2023-08-28.
  15. "NEXUS natural gas pipeline pushed back to 2017". Canton Repository. Retrieved 2023-08-28.
  16. 16.0 16.1 "Ohio Gulf Coast Pipeline Project Approved". www.psgincs.com. 03 December, 2021. Retrieved 2023-08-28. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  17. "Texas transmission company proposing $486M pipeline in eastern Ohio". Ohio Gas Association. 06 February, 2014. Retrieved 28 August, 2023. {{cite web}}: Check date values in: |access-date= and |date= (help)CS1 maint: url-status (link)
  18. "New pipeline to carry Ohio gas". The Columbus Dispatch. Retrieved 2023-08-28.
  19. "Texas Eastern To Develop Ohio Pipeline Energy Network Project". pgjonline.com. Retrieved 2023-08-28.
  20. "Ohio Gulf Coast Pipeline Project Approved". www.psgincs.com. 03 December, 2021. Retrieved 2023-08-28. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  21. "Sharing insights elevates their impact". S&P Global. 2015-09-22. Retrieved 2023-08-28.
  22. Texas Eastern Appalachian Lease Project, Enbridge, accessed January 2018.
  23. Nexus Gas Transmission, TEAL, DTE Lease, and Vector Lease, Permitting Dashboard, accessed January 2018
  24. Plans to put into service remainder of TEAL gas pipeline, World Pipelines, Oct. 25, 2018
  25. Enbridge’s Cameron Extension Pipeline Project Nearing Completion, Pipeline & Gas Journal, Sep. 14, 2021
  26. 26.00 26.01 26.02 26.03 26.04 26.05 26.06 26.07 26.08 26.09 26.10 26.11 26.12 26.13 26.14 26.15 26.16 26.17 26.18 26.19 26.20 26.21 Natural Gas Data, Pipeline Projects Energy Information Agency, accessed July 21, 2020
  27. "https://www.enbridge.com/projects-and-infrastructure/projects/venice-extension-project". {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)

Related GEM.wiki articles

External resources

External articles

Wikipedia also has an article on Texas Eastern Transmission (TETCO) Gas Pipeline (Texas Eastern Transmission Pipeline). This article may use content from the Wikipedia article under the terms of the Creative Commons Attribution-ShareAlike 3.0 Unported License.