Tianchi Changji cogen power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Tianchi Changji cogen power station (天池能源昌吉热电) is an operating power station of at least 700-megawatts (MW) in Erliugong Town, Zhundong, Changji, Xinjiang, China with multiple units, some of which are not currently operating. It is also known as 天池能源昌吉州准东火电机组项目 (Unit 3 & 4), 特变电工新疆天池能源五彩湾2×660兆瓦项目 (Unit 3 & 4), 新疆准能投资有限公司准东2×660MW火电项目 (Unit 3 & 4), 新疆准东五彩湾2×660MW火电项目 (Unit 3 & 4).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Tianchi Changji cogen power station Erliugong Town, Zhundong, Changji, Xinjiang, China 44.004362, 87.171961 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4: 44.004362, 87.171961

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 operating coal: unknown 350 supercritical 2017
Unit 2 operating coal: unknown 350 supercritical 2017
Unit 3 construction coal: unknown 660 ultra-supercritical 2026 (planned)
Unit 4 construction coal: unknown 660 ultra-supercritical 2026 (planned)

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Xinjiang Tianchi Energy Co Ltd [100%] TBEA Co Ltd [85.8%]; Xinjiang Joinworld Co Ltd [14.2%]
Unit 2 Xinjiang Tianchi Energy Co Ltd [100%] TBEA Co Ltd [85.8%]; Xinjiang Joinworld Co Ltd [14.2%]
Unit 3 Xinjiang Tianchi Energy Co Ltd [100%] TBEA Co Ltd [85.8%]; Xinjiang Joinworld Co Ltd [14.2%]
Unit 4 Xinjiang Tianchi Energy Co Ltd [100%] TBEA Co Ltd [85.8%]; Xinjiang Joinworld Co Ltd [14.2%]

Project-level coal details

  • Permit(s):

Background

Tianchi Changji cogen power station is a 2 x 350 supercritical coal plant in Changji Hui AP, Xinjiang province. It was permitted in September 2014,[1] and construction began in 2015. Operation is planned for 2017.[2]

Unit 1 began operating in March 2017.[3] Commissioning of unit 2 began in June 2017.[4]

Expansion proposed

In July 2022, it was reported to that according to province's "14th Five-Year Plan" from April 2022, an additional 2 x 660 MW was under consideration.[5] By August 2022, a consortium was awarded a bid to build, operate, and maintain the units.[6]

Articles and Resources

References

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.