Tonghua Xuangang power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Tonghua Xuangang power station (晋能控股漳泽电力同华轩岗发电厂) is an operating power station of at least 1320-megawatts (MW) in Xuangang, Yuanping, Xinzhou, Shanxi, China with multiple units, some of which are not currently operating. It is also known as Tongfa Xuangang power station.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Tonghua Xuangang power station | Xuangang, Yuanping, Xinzhou, Shanxi, China | 38.9151455, 112.4765897 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 38.9151455, 112.4765897
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase I Unit 1 | operating | coal: bituminous | 660 | supercritical | 2010 |
Phase I Unit 2 | operating | coal: bituminous | 660 | supercritical | 2010 |
Phase II Unit 3 | pre-permit[1] | coal: bituminous | 660 | ultra-supercritical | – |
Phase II Unit 4 | pre-permit | coal: bituminous | 660 | ultra-supercritical | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Shanxi Zhangzhe POWER Tonhua Generation Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [95.0%]; Shanxi State-Owned Capital Investment and Operation Co Ltd [2.9%]; Jinneng Group Co Ltd [1.1%]; other [0.7%]; Jinneng Holding Group Co Ltd [0.3%] |
Phase I Unit 2 | Shanxi Zhangzhe POWER Tonhua Generation Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [95.0%]; Shanxi State-Owned Capital Investment and Operation Co Ltd [2.9%]; Jinneng Group Co Ltd [1.1%]; other [0.7%]; Jinneng Holding Group Co Ltd [0.3%] |
Phase II Unit 3 | Shanxi Zhangzhe POWER Tonhua Generation Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [95.0%]; Shanxi State-Owned Capital Investment and Operation Co Ltd [2.9%]; Jinneng Group Co Ltd [1.1%]; other [0.7%]; Jinneng Holding Group Co Ltd [0.3%] |
Phase II Unit 4 | Shanxi Zhangzhe POWER Tonhua Generation Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [95.0%]; Shanxi State-Owned Capital Investment and Operation Co Ltd [2.9%]; Jinneng Group Co Ltd [1.1%]; other [0.7%]; Jinneng Holding Group Co Ltd [0.3%] |
Background
The two existing coal-fired units of Tonghua Xuangang power station, totaling 1,320 MW, were brought online in 2010. The plant is owned by Datong Coal Mining Group.[2][3]
Description of Expansion
Datong Coal is currently planning to build two additional coal-fired units at this plant, with a total planned capacity of 1,320 MW. The new units were scheduled to be completed in 2015,[4][5] but as of June 2015 the units have yet to receive environmental clearance for construction.[6]
Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
In January 2017 China's National Energy Administration suspended over 100 planned and under-construction coal power projects with a total capacity of over 100GW in 13 provinces, including Tonghua Xuangang. It is unclear when or if the projects will be revived.[7]
For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
2019: Project revived
In April 2019, Zhangze Power said that units 3-4 had been removed from the central government's list of postponed projects.[8]
As of July 2020, the expansion was expected to begin construction in 2021.[9]
In July 2022, with no apparent developments in over two years, Units 3 and 4 were presumed to be shelved.
Articles and Resources
References
- ↑ https://web.archive.org/web/20240327060638/https://news.bjx.com.cn/html/20240208/1361092.shtml. Archived from the original on 27 March 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "同煤集团同华发电公司轩岗2x660MW坑口电厂双机投产", 同煤网站, 2010-07-08
- ↑ "大同煤矿集团同华发电有限公司轩岗电厂(2×660MW)二期扩建工程环境影响评价第二次公示", 忻州在线, 2013-08-22
- ↑ "央企首次退出地方火电 大同煤业接手漳泽电力", 网易财经, 2011-10-29
- ↑ "漳泽电力:关于共同出资设立同华二期发电项目公司的关联交易公告", 中国互联网新闻中心, 2014-03-29
- ↑ "一路奋进铸辉煌——同华发电公司创业纪实," sxzdthfd.com, Jun 16, 2015
- ↑ "能源局下发13省市新建火电机组停建清单(附文件)," Polaris, Jan 16, 2017
- ↑ "漳泽电力:2018年年度报告," Zhangze Power, 2019年04月26日
- ↑ "同华轩岗电厂二期2×66万千瓦项目预计2021年开工," news.bjx.com, 2020-07-14