Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Yongji power station (永济发电厂) is an operating power station of at least 1300-megawatts (MW) in Zhongshan East Street, Yongji, Yuncheng, Shanxi, China with multiple units, some of which are not currently operating. It is also known as 蒲光电厂一期 (New unit 1, New unit 2), Tongmei Yongji power station, 晋能控股永济热电 (Unit 2, Unit 3, Unit 4, Unit 5, Unit 6), 晋能控股漳泽电力蒲州发电厂 (New unit 1, New unit 2, New unit 3, New unit 4), 蒲州热电厂 (New unit 3, New unit 4).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Yongji power station | Zhongshan East Street, Yongji, Yuncheng, Shanxi, China | 34.8559852, 110.4706728 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- New unit 1, New unit 2, New unit 3, New unit 4, Unit 2, Unit 3, Unit 4, Unit 5, Unit 6: 34.8559852, 110.4706728
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
New unit 1 | operating | coal: bituminous | 300 | subcritical | 2006 | – |
New unit 2 | operating | coal: bituminous | 300 | subcritical | 2007 | – |
New unit 3 | operating | coal: bituminous | 350 | supercritical | 2015 | – |
New unit 4 | operating | coal: bituminous | 350 | supercritical | 2016 | – |
Unit 2 | retired | coal: unknown | 100 | unknown | 2004 | 2007 |
Unit 3 | retired | coal: bituminous | 50 | subcritical | 1988 | 2011 |
Unit 4 | retired | coal: bituminous | 50 | subcritical | 1989 | 2011 |
Unit 5 | retired | coal: unknown | 50 | unknown | 1990 | 2007 |
Unit 6 | retired | coal: unknown | 50 | unknown | 1999 | 2007 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
New unit 1 | Jinkong Electric Power Puzhou Thermal Power Shanxi Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [65.0%]; Shaanxi Coal and Chemical Industry Co Ltd [35.0%] |
New unit 2 | Jinkong Electric Power Puzhou Thermal Power Shanxi Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [65.0%]; Shaanxi Coal and Chemical Industry Co Ltd [35.0%] |
New unit 3 | Jinkong Electric Power Puzhou Thermal Power Shanxi Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [65.0%]; Shaanxi Coal and Chemical Industry Co Ltd [35.0%] |
New unit 4 | Jinkong Electric Power Puzhou Thermal Power Shanxi Co Ltd [100%] | Jinneng Holding Shanxi Electric Power Co Ltd [65.0%]; Shaanxi Coal and Chemical Industry Co Ltd [35.0%] |
Unit 2 | Datong Coal Mine Group Yongji Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [58.7%]; China Cinda Asset Management Co Ltd [30.1%]; Jinneng Holding Group Co Ltd [6.5%]; other [4.7%] |
Unit 3 | Datong Coal Mine Group Yongji Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [58.7%]; China Cinda Asset Management Co Ltd [30.1%]; Jinneng Holding Group Co Ltd [6.5%]; other [4.7%] |
Unit 4 | Datong Coal Mine Group Yongji Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [58.7%]; China Cinda Asset Management Co Ltd [30.1%]; Jinneng Holding Group Co Ltd [6.5%]; other [4.7%] |
Unit 5 | Datong Coal Mine Group Yongji Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [58.7%]; China Cinda Asset Management Co Ltd [30.1%]; Jinneng Holding Group Co Ltd [6.5%]; other [4.7%] |
Unit 6 | Datong Coal Mine Group Yongji Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [58.7%]; China Cinda Asset Management Co Ltd [30.1%]; Jinneng Holding Group Co Ltd [6.5%]; other [4.7%] |
Background
The first seven units of Yongji power station, totaling 380 MW, were commissioned from 1973 to 2000. Units 1-2 were retired in 1990, and units 3-7 retired in 2013. Units 8-9, totaling 600 MW, known as 晋能控股漳泽电力蒲州发电厂 were brought online between 2006 to 2007[1]. The plant is owned by Datong Coal Mining Group.[2]
Description of Expansion
Datong Coal planned two additional coal-fired units at this plant, units 10-11, with a total capacity of 700 MW. Construction began in 2013 and operation is planned for 2015-2016.[3][4]
Articles and Resources
References
- ↑ "华圣铝业、新时速等50个永济企业2012年最新简介", 永济人民政府网, 2012-10-19
- ↑ "同煤集团将大力推进三大煤电基地建设", 新华网山西频道, 2013-01-31
- ↑ "山西永济2×30万千瓦热电联产项目稳步推进", 北极星电力网新闻, 2014-06-06
- ↑ "山西永济热电工程4号机组空冷钢平台安装圆满完成," 2015-08-20
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.