Vijay Coal Mine
This article is part of the Global Coal Mine Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Related-articles: |
Vijay Coal Mine is an operating coal mine in Kendai, Korba, Chhattisgarh, India.
Location
Table 1: Project-level location details
Mine Name | Location | Coordinates (WGS 84) |
---|---|---|
Vijay Coal Mine | Kendai, Korba, Chhattisgarh, India | 22.854326, 82.32114 (exact) |
The map below shows the exact location of the coal mine:
Project Details
Table 2: Project status
Status | Status Detail | Opening Year | Closing Year |
---|---|---|---|
Operating | – | – | – |
Table 3: Operation details
Capacity (Mtpa) | Production (Mtpa) | Year of Production | Mine Type | Mining Method | Mine Size (km2) | Mine Depth (m) | Workforce Size |
---|---|---|---|---|---|---|---|
0[1] | 0.5[2] | 2022[2] | Underground | – | 4.38 | 300* | 674* |
Table 4: Coal resources and destination
Total Reserves (Mt) | Year of Total Reserves Recorded | Total Resources (Mt) | Coalfield | Coal Type | Coal Grade | Primary Consumer/ Destination |
---|---|---|---|---|---|---|
8.337[1] | 2022[1] | – | Sendurgar | Subbituminous | Thermal | – |
Table 5: Ownership and parent company
Owner | Parent Company | Headquarters |
---|---|---|
South Eastern Coalfields Ltd | Coal India Ltd [100.0%] | India |
Note: The above section was automatically generated and is based on data from the Global Coal Mine Tracker April 2024 release and the September supplement.
Background on Mine
The Vijay Coal Mines is a cluster of three mines Vijay East(planned), Vijay West (operational) and Vijay Central to be merged with Vijay West as Opencast. Vijay West mine project has a designed capacity of 0.5 MTPA on a mining lease area of 438.10 ha. It is operated by South Eastern Coalfields Limited. The project received its environment clearance on 15 April 2009.[3]
Vijay West is now proposed to be combined with the Vijay Central mine, which was earlier allotted to Prakash Industries and Coal India Limited as joint venture[4], and was cancelled by the Supreme Court in Coalgate scam. The new mine Vijay West/Vijay Central will be an opencast mine and peak capacity of 3 MTPA[5].
Vijay East part of the Vijay coal block remains in the planning stage for now.
Expansion Details
- Status: Proposed
- Size of Expansion: 3 MTPA
- Permits and Applications: Ministry of coal press information, 30 July 2018
Articles and Resources
Additional data
To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 (PDF) https://www.secl-cil.in/writereaddata/FINAL_VIJAY%20WEST%20UG_CHIRIMIRI%20AREA%20EAS%2021-22.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 (PDF) https://d3u7ubx0okog7j.cloudfront.net/documents/SECL_Annual_Report_2022-23.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ Environment Clearance for Vijay West Underground Coal Mine Project , MoEF&CC India, 15 April 2009
- ↑ summary of the Vijay Central mine, Ministry of coal, accessed on 21 April, 2020
- ↑ Ministry of coal press information, 30 July 2018