Wanneng Jiangbu power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Wanneng Jiangbu power station (皖能新疆江布电厂) is an operating power station of at least 1320-megawatts (MW) in Dajing, Qitai, Changji, Xinjiang, China. It is also known as Lu'an Zhundong power station, 潞安准东电厂2×660MW工程, 潞安协鑫新疆准东发电厂.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Wanneng Jiangbu power station Dajing, Qitai, Changji, Xinjiang, China 44.7026, 89.6784 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 44.7026, 89.6784

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 operating coal: unknown 660 ultra-supercritical 2023
Unit 2 operating coal: unknown 660 ultra-supercritical 2023

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Xinjiang Lu'an GCL Zhundong Energy Co Ltd [100%] An Hui Wenergy Co Ltd [53.0%]; Shaanxi ENERGY Investment Co Ltd [46.0%]; other [1.0%]
Unit 2 Xinjiang Lu'an GCL Zhundong Energy Co Ltd [100%] An Hui Wenergy Co Ltd [53.0%]; Shaanxi ENERGY Investment Co Ltd [46.0%]; other [1.0%]

Background on Project

Wanneng Jiangbu power station (previously stored as Lu'an Zhundong, 潞安协鑫新疆准东发电厂) is a 2 x 660 MW ultra-supercritical power station under construction in Qitai County. It is planned for operation by 2017.[1][2][3]

Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity

In 2016 China's National Energy Administration issued "scale control" (coal-fired capacity limits) on particular "sending out" locations that feed ultra-high voltage (UHV) long-distance power lines, including Inner Mongolia (Xilingong), Inner Mongolia (Ordos), Shaanxi, Ningxia, Shanxi, and Xinjiang.[4]

As of January 2017, the affected area includes this power station, which may be scaled down as a result. For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.

2017: Plant postponed by government

In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[5]

Lu'an Zhundong power station Units 1-2 are among the halted coal-burning units,[5] and also appeared on an updated list of halted projects released in September 2017.[6]

For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.

2020: Project revived

In March 2020, Luan Group and GCL Group held a symposium to promote the construction of the plant.[7] Construction resumed in May 2020.[8]

Unit 1 connected to the grid at the end of July 2023[9][10] and went into commercial operation on 9 September 2023.[11][12] Unit 2 successfully completed 168 trail run on 28 August 2023.[13]

Articles and Resources

References

  1. "新疆准东"疆电外送"千万千瓦级煤电基地项目集中开工," 亚心网, 2015年04月10日
  2. "潞安准东电厂(2×660MW)工程环境影响评价公众参与第二次公示," 2015-04-09
  3. "新疆潞安协鑫准东电厂2#机组锅炉房顺利开挖," 2015-10-12
  4. "能源局下发13省市新建火电机组停建清单(附文件)," Polaris, Jan 16, 2017
  5. 5.0 5.1 "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
  6. "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
  7. "潞安集团与协鑫集团共商推进准东电厂项目建设事宜," 北极星电力网新闻中心, 2020/3/31
  8. "【建设公司】新疆潞安协鑫准东电厂项目有序开展复工生产工作," 建设公司, 2020-05-07
  9. 新疆皖能江布电厂 (2023-07-31). "皖能新疆江布电厂1号机组首次并网一次成功". 皖能集团网站. Retrieved 2023-8-30. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  10. 皖能集团 (2023-08-01). "皖能新疆江布电厂2×660MW工程项目1号机组首次并网一次成功". 火电之声. Retrieved 2023-8-30. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  11. "皖能江布电厂2×660MW新建项目1号机组168满负荷试运行圆满成功,两台机组全部投入商业运营". 火电之声. 2023-09-10. Retrieved 2023-9-14. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  12. 皖能集团 杨敬佩 (023-09-11). "2×660MW!新疆皖能江布电厂两台机组全部投运". 北极星火力发电网. Retrieved 2023-9-14. {{cite web}}: Check date values in: |access-date= and |date= (help)CS1 maint: url-status (link)
  13. "集团公司致信祝贺江布电厂2号机组顺利通过168小时满负荷试运行". 皖能集团网站. 2023-08-30. Retrieved 2023-08-30.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.