Weiqiao Huji power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Weiqiao Huji power station (魏桥集团惠民胡集自备电厂) is an operating power station of at least 2640-megawatts (MW) in Huji Town, Huimin, Binzhou, Shandong, China. It is also known as 魏桥第四热电厂.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Weiqiao Huji power station | Huji Town, Huimin, Binzhou, Shandong, China | 37.3594471, 117.7770746 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase II Unit 5, Phase II Unit 6, Phase II Unit 7, Phase II Unit 8: 37.3594471, 117.7770746
- Phase I Unit 1, Phase I Unit 2, Phase I Unit 3, Phase I Unit 4: 37.347901, 117.781587
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase I Unit 1 | operating | coal: unknown | 330 | subcritical | 2015 |
Phase I Unit 2 | operating | coal: unknown | 330 | subcritical | 2015 |
Phase I Unit 3 | operating | coal: unknown | 330 | subcritical | 2014 |
Phase I Unit 4 | operating | coal: unknown | 330 | subcritical | 2014 |
Phase II Unit 5 | operating | coal: unknown | 330 | subcritical | 2016 |
Phase II Unit 6 | operating | coal: unknown | 330 | subcritical | 2016 |
Phase II Unit 7 | operating | coal: unknown | 330 | subcritical | 2016 |
Phase II Unit 8 | operating | coal: unknown | 330 | subcritical | 2016 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase I Unit 2 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase I Unit 3 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase I Unit 4 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase II Unit 5 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase II Unit 6 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase II Unit 7 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Phase II Unit 8 | Binzhou Green Energy Thermal Power Co Ltd [100%] | Hongqiao Investment (Hong Kong) [94.5%]; other [5.5%] |
Project-level captive use details
- Captive industry use (heat or power): both
- Captive industry: Aluminum
- Non-industry use: both
Background
Weiqiao Huji power station is a 4 x 330 MW subcritical coal plant at Binzhou prefecture, owned by Shandong Weiqiao Group. Units 3-4 began operating in 2014.[1] Units 1-2 were completed in 2015.[2][3]
Proposed expansion
Shandong Weiqiao Group is constructing an additional units 5-8 at the power station, totaling 1,320 MW (four units of 330 MW each).[4]
The units were commissioned in 2016.[5][6]
Shandong Weiqiao Group found to have built 45 coal-fired units without necessary permits
In August and September 2017, China's central government Environmental Protection Inspection Group 3 (中央第三环境保护督察组) spent a month in Shandong Province, to inspect the province's environmental protection work. In its final inspection report, the Group found that Shandong Weiqiao Group illegally built 45 coal power units in Shandong.[7]
In May 2018, the Shandong Provincial government responded to the inspection report with a plan to address the wrongdoings. According to the province, 33 of Weiqiao's 45 illegal coal power plants had since completed the necessary procedures to receive environment clearance and continue operating; 12 of the plants did not complete any procedures and should stop construction and operation immediately. Among the 12 units, 4 units should stop construction, and 8 units should stop operation, although they are not named.[8]
Articles and Resources
References
- ↑ "魏桥胡集电厂项目4号机组完成168小时满负荷试运行," 中国火力发电网, 2014-08-27
- ↑ "环境保护部公告," China MEP, 2015年06月23日
- ↑ "努力开拓 不断进取: 公司胡集4*350MW2#机组电仪安装开工," 2015-8-27
- ↑ "山东惠民县胡集电厂二期工程开工建设," aladdiny.com, 2014/9/22
- ↑ "【基层动态】山东分公司胡集项目7号机组正式投入商业运营," Sep 26, 2016
- ↑ "山东胡集电厂二期工程8号锅炉汽包正式安装就位," 中国电力化工网, 2016-03-03
- ↑ "魏桥因自备电厂再遭点名 违规建设发电机组45台," Jiemian, 2018/05/31
- ↑ "山东省公开中央环境保护督察整改方案," China MEP, 2018年05月29日
Additional data