Xiantao power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Xiantao power station (华润电力仙桃发电厂) is an operating power station of at least 1320-megawatts (MW) in Changtangkou Town Zengjiatai Villege, Xiantao, Hubei, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Xiantao power station | Changtangkou Town Zengjiatai Villege, Xiantao, Hubei, China | 30.371957, 113.567148 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 30.371957, 113.567148
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase II Unit 3 | permitted[1] | coal: unknown | 660[2] | ultra-supercritical[2] | – |
Phase II Unit 4 | permitted[1] | coal: unknown | 660[1] | ultra-supercritical[1] | – |
Unit 1 | operating | coal: unknown | 660 | ultra-supercritical | 2022 |
Unit 2 | operating | coal: unknown | 660 | ultra-supercritical | 2022 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase II Unit 3 | China Resources Power (Xiantao) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Phase II Unit 4 | China Resources Power (Xiantao) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Unit 1 | China Resources Power (Xiantao) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Unit 2 | China Resources Power (Xiantao) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Project-level coal details
- Permit(s): [2]
Background on Project
In 2015 China Resources Holding was permitted to build a 2 x 660 MW coal-fired power station in the city of Xiantao.[3][4]
The project was planned for completion in 2017,[5][6] but construction did not begin until March 2019.[7]
Unit 1 was connected to the grid by the end of June 2022,[8] and began operating July 10, 2022.[9]
Unit was connected to the grid on October 22, 2022,[10] and was operating by November 2022.[11]
In December 2022, a 2 x 660 MW Phase II expansion was announced at Xiantao power station.[12] In October 2023, Environmental Impact Assessment information was made available.[13] In November 2023, Phase II was reportedly preparing to start construction.[14]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 https://hbj.xiantao.gov.cn/xwzx/gsgg/202310/t20231031_4920940.shtml.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 https://web.archive.org/web/20240125143225/https://news.bjx.com.cn/html/20231120/1344489.shtml. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "华润电力拟建湖北仙桃火电项目", BJX News, 2012-12-10
- ↑ "省发改委关于华润仙桃电厂新建工程项目核准的通知,” DRC of Hubei Province, 2015-10-16
- ↑ "湖北省2014-2015年大型火电项目建设选优评议结果公示," 能源局电力处, 2014-06-27
- ↑ "总投资51亿元 湖北华润仙桃电厂试桩开机"湖北日报, 2016/1/11
- ↑ "华润电力仙桃电厂新建2×660MW燃煤机组工程主体建筑开工," 河南省第二建筑工程发展有限公司, 2019/3/13
- ↑ 华润仙桃电厂2×660MW燃煤机组工程1号机组首次并网一次成功, china5e, 2022-06-27
- ↑ "仙桃电厂1号机组顺利通过168试运," CR Power, 2022-07-17
- ↑ "华润仙桃电厂2×660MW超超临界燃煤机组工程2号机组首次并网一次成功," BJX, 2022-10-20
- ↑ "2×660MW!湖北仙桃电厂项目实现“双投”," BJX, 2022-11-11
- ↑ 华润电力仙桃电厂——一期投产发电,二期稳步推进 news.hubeidaily.net, December 26, 2022
- ↑ 华润电力(仙桃)有限公司二期2×660MW超超临界燃煤发电机组工程环境影响评价信息公告-仙桃市人民政府 hbj.xiantao.gov, October 31, 2023
- ↑ 计划投资53亿元!华润仙桃火电二期项目即将开工 news.bjx.com, November 20, 2023