Xintian Tangshan LNG Terminal
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Xintian Tangshan LNG Terminal (新天唐山曹妃甸LNG接收站) is a LNG terminal with proposed, under construction and operating phases in Caofeidian Industrial Zone, Tangshan, Hebei, China.
Location
Project details
Phase 1
- Owner: Caofeidian Xintian Liquefaction Natural Gas Company 曹妃甸新天液化天然气有限公司[1]
- Parent company: China Suntien Green Energy Corporation Limited 新天绿色能源股份有限公司 51%, Hebei Construction Investment Group Co., Ltd. 河北建设投资集团有限责任公司 49%.
- Location: Caofeidian Industrial Zone, Tangsham, Hebei, China
- Coordinates: 38.93871897902525, 118.54011096026547 (exact)
- Capacity: 5 mtpa[2]
- Status: Operating[3]
- Type: Import
- Start year: 2023
Phase 2
- Owner: Caofeidian Xintian Liquefaction Natural Gas Company 曹妃甸新天液化天然气有限公司[1]
- Parent company: China Suntien Green Energy Corporation Limited 新天绿色能源股份有限公司 51%, Hebei Construction Investment Group Co., Ltd. 河北建设投资集团有限责任公司 49%.
- Location: Caofeidian Industrial Zone, Tangsham, Hebei, China
- Coordinates: 38.94433666057848, 118.54888853700375 (exact)
- Capacity: 3.5 mtpa
- Status: Construction
- Type: Import
- Start year:
Phase 3
- Owner: Caofeidian Xintian Liquefaction Natural Gas Company 曹妃甸新天液化天然气有限公司[1]
- Parent company: China Suntien Green Energy Corporation Limited 新天绿色能源股份有限公司 51%, Hebei Construction Investment Group Co., Ltd. 河北建设投资集团有限责任公司 49%.
- Location: Caofeidian Industrial Zone, Tangsham, Hebei, China
- Coordinates: 38.957077, 118.5646 (exact)
- Capacity: 3.5 mtpa
- Status: Proposed
- Type: Import
- Start year:
Background
In September 2018 Caofeidian Xintian Liquefaction Natural Gas Company announced plans to build the project in three phases, with completion of Phase I expected in October 2020.[4][5]
The EIA report of the project was approved by MEE in May 2019.[6] It was permitted by NDRC in October 2019, along with a 176-km transporting gas pipeline, and by July 28, 2020, the construction of the first phase of the LNG terminal has begun.[7]
Xintian Green Energy Company intends to issue shares in a non-public offering and raise funds not exceeding 5.11 billion yuan ($785.6 million). More than half of the raised money will be used to support the first and second phases of the LNG terminal project.[8]
According to its EIA report, the project includes 20 storage tanks with 200,000 cubic meters each. The annual circulating capacity will reach 17 million tonnes when all completed. But other news reports show the total capacity is 12 mtpa. [9] Phase I will build one wharf and 4 storage tanks. Phase II will complete another wharf and 8 storage tanks. Extra 8 storage tanks will be added in Phase III.[6]
Phase II reportedly began construction in July 2021.[10]
By January 2023, the construction of phase I and phase II is ongoing.[11]
In August 2023, S&P Global reported that Phase 1 started operations in June 2023.[3][12] Phase II is still under construction. [9]
From the satellite image, 12 storage tanks are visible for two phases. The third phase is also proposed.[13]
Articles and resources
References
- ↑ 1.0 1.1 1.2 "曹妃甸新天液化天然气有限公司 - 企查查". www.qcc.com. Retrieved 2021-04-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "LNG接收站首船到港 燃气产业布局完善 新天绿色能源(00956.HK)" (PDF). www.swsresearch.com. 2023-06-25.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 "https://www.spglobal.com/commodityinsights/en/market-insights/latest-news/lng/080823-chinas-zhejiang-energy-receives-first-lng-cargo-at-new-wenzhou-terminal".
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|title=
- ↑ 环渤海地区最大LNG项目落户唐山曹妃甸 总投资达320亿元, Xinhua.net, Jul. 11, 2019
- ↑ "曹妃甸将成为全国LNG接卸能力最大的港口". www.cbmf.org. 2019-11-08. Retrieved 2021-03-31.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 6.0 6.1 关于唐山LNG项目环境影响报告书的批复, 生态环境部, May 20, 2019
- ↑ 新天绿能:唐山LNG接收站项目目前第一阶段工程已开工建设 10jqka.com.cn, 07/08/2020
- ↑ 新天绿能募资建设唐山LNG接收站项目 Sohu.com, 12-25-2020
- ↑ 9.0 9.1 "河北曹妃甸新天LNG接收站项目二阶段工程建设稳步推进". h.xinhuaxmt.com. 2023-08-19.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "河北曹妃甸新天LNG项目二期工程开工建设 来源: 新华社". http://www.gov.cn/ 中国政府网. 2021-07-10.
{{cite web}}
: External link in
(help); line feed character in|website=
|title=
at position 21 (help)CS1 maint: url-status (link) - ↑ "河北曹妃甸新天LNG项目接收站工程建设正酣_图片新闻_中国政府网". www.gov.cn. 2023-01-04.
{{cite web}}
: CS1 maint: url-status (link) - ↑ sina_mobile (2023-06-26). "京津冀腹地大型LNG项目投产 新天绿能天然气业务再上新台阶". finance.sina.cn.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "京津冀腹地大型LNG项目投产 新天绿能天然气业务再上新台阶". finance.sina.cn. 2023-06-26.
{{cite web}}
: CS1 maint: url-status (link)