Xuzhou Huamei power station (徐矿华美电厂) is an operating power station of at least 700-megawatts (MW) in Pangzhuang coal mine, Quanshan, Xuzhou, Jiangsu, China with multiple units, some of which are not currently operating. It is also known as Xuzhou Pangzhuang power station.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Xuzhou Huamei power station | Pangzhuang coal mine, Quanshan, Xuzhou, Jiangsu, China | 34.34116, 117.104751 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 34.34116, 117.104751
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Phase I Unit 1 | retired | coal: bituminous | 55 | subcritical | 2005 | 2016 |
Phase I Unit 2 | retired | coal: bituminous | 55 | subcritical | 2005 | 2016 |
Phase II Unit 3 | operating | coal: bituminous | 350 | supercritical | 2016 | – |
Phase II Unit 4 | operating | coal: bituminous | 350 | supercritical | 2016 | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Xuzhou Huamei Kengkou Environmental Protection Thermoelectricity Co Ltd [100%] | Xuzhou Coal Mining Group Corp [100.0%] |
Phase I Unit 2 | Xuzhou Huamei Kengkou Environmental Protection Thermoelectricity Co Ltd [100%] | Xuzhou Coal Mining Group Corp [100.0%] |
Phase II Unit 3 | Jiangsu Huamei Thermal Power Co Ltd [100%] | Jiangsu Xukuang Energy Co Ltd [100.0%] |
Phase II Unit 4 | Jiangsu Huamei Thermal Power Co Ltd [100%] | Jiangsu Xukuang Energy Co Ltd [100.0%] |
Background
The two existing coal-fired units of Xuzhou Huamei power station, totaling 110 MW, were brought online in 2005. They have since been retired. The plant is owned by Xuzhou Mining Group.[1]
Description of Expansion
Xuzhou Coal Mining is developing two additional coal-fired units at this plant, with a total planned capacity of 700 MW. The new units are scheduled to be completed in 2015. With the completion of the new units, the two older units will be shut down under the policy of "Big Pressure on the Small."[2][3]
The plant was completed in 2016.[4]
Articles and Resources
References
- ↑ "徐矿“上大压小”热电联产新建项目补充可研报告通过审查",江苏省能源投资有限公司, 2013-5-16
- ↑ Liuyun Xia, "共建共享谱就和谐乐章——江苏华美热电公司创建“幸福企业”纪实," Digital Press, accessed September 2015
- ↑ "徐矿华美热电二期“上大压小”热电联产项目获批复,"Polaris power grid News, 2015/2/5
- ↑ "江苏徐矿:“两条腿”探新路," 2016-06-02
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.