Zheneng Yueqing power station (浙能乐清发电厂) is an operating power station of at least 4520-megawatts (MW) in Hongqiao Town, Yueqing, Wenzhou, Zhejiang, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Zheneng Yueqing power station Hongqiao Town, Yueqing, Wenzhou, Zhejiang, China 28.1704074, 121.0889375 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6: 28.1704074, 121.0889375

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Phase I Unit 1 operating coal: bituminous 600 supercritical 2008
Phase I Unit 2 operating coal: bituminous 600 supercritical 2008
Phase II Unit 3 operating coal: bituminous 660 ultra-supercritical 2010
Phase II Unit 4 operating coal: bituminous 660 ultra-supercritical 2010
Phase III Unit 5 operating coal: bituminous 1000 ultra-supercritical 2023
Phase III Unit 6 operating coal: bituminous 1000 ultra-supercritical 2023

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 Zhejiang Zheneng Yueqing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [52.4%]; GD POWER Development Co Ltd [13.6%]; Wenzhou Industry Investment Group [13.2%]; China Shenhua Energy Co Ltd [10.0%]; other [4.5%]; Zhejiang Financial Development Co Ltd [1.5%]; Yueqing State Owned Investment Co Ltd [1.3%]; Pingyang Guocheng Holding Co Ltd [0.7%]; Rui'an State-owned Assets Investment Group Co Ltd [0.7%]; Rui'an Construction Development Investment Co Ltd [0.7%]; Cangnan County Urban Investment Group Co Ltd [0.7%]; Yongjia County State Owned Assets Investment Group Co Ltd [0.6%]
Phase I Unit 2 Zhejiang Zheneng Yueqing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [52.4%]; GD POWER Development Co Ltd [13.6%]; Wenzhou Industry Investment Group [13.2%]; China Shenhua Energy Co Ltd [10.0%]; other [4.5%]; Zhejiang Financial Development Co Ltd [1.5%]; Yueqing State Owned Investment Co Ltd [1.3%]; Pingyang Guocheng Holding Co Ltd [0.7%]; Rui'an State-owned Assets Investment Group Co Ltd [0.7%]; Rui'an Construction Development Investment Co Ltd [0.7%]; Cangnan County Urban Investment Group Co Ltd [0.7%]; Yongjia County State Owned Assets Investment Group Co Ltd [0.6%]
Phase II Unit 3 Zhejiang Zheneng Yueqing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [52.4%]; GD POWER Development Co Ltd [13.6%]; Wenzhou Industry Investment Group [13.2%]; China Shenhua Energy Co Ltd [10.0%]; other [4.5%]; Zhejiang Financial Development Co Ltd [1.5%]; Yueqing State Owned Investment Co Ltd [1.3%]; Pingyang Guocheng Holding Co Ltd [0.7%]; Rui'an State-owned Assets Investment Group Co Ltd [0.7%]; Rui'an Construction Development Investment Co Ltd [0.7%]; Cangnan County Urban Investment Group Co Ltd [0.7%]; Yongjia County State Owned Assets Investment Group Co Ltd [0.6%]
Phase II Unit 4 Zhejiang Zheneng Yueqing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [52.4%]; GD POWER Development Co Ltd [13.6%]; Wenzhou Industry Investment Group [13.2%]; China Shenhua Energy Co Ltd [10.0%]; other [4.5%]; Zhejiang Financial Development Co Ltd [1.5%]; Yueqing State Owned Investment Co Ltd [1.3%]; Pingyang Guocheng Holding Co Ltd [0.7%]; Rui'an State-owned Assets Investment Group Co Ltd [0.7%]; Rui'an Construction Development Investment Co Ltd [0.7%]; Cangnan County Urban Investment Group Co Ltd [0.7%]; Yongjia County State Owned Assets Investment Group Co Ltd [0.6%]
Phase III Unit 5 Zhejiang Zheneng Yueqing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [52.4%]; GD POWER Development Co Ltd [13.6%]; Wenzhou Industry Investment Group [13.2%]; China Shenhua Energy Co Ltd [10.0%]; other [4.5%]; Zhejiang Financial Development Co Ltd [1.5%]; Yueqing State Owned Investment Co Ltd [1.3%]; Pingyang Guocheng Holding Co Ltd [0.7%]; Rui'an State-owned Assets Investment Group Co Ltd [0.7%]; Rui'an Construction Development Investment Co Ltd [0.7%]; Cangnan County Urban Investment Group Co Ltd [0.7%]; Yongjia County State Owned Assets Investment Group Co Ltd [0.6%]
Phase III Unit 6 Zhejiang Zheneng Yueqing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [52.4%]; GD POWER Development Co Ltd [13.6%]; Wenzhou Industry Investment Group [13.2%]; China Shenhua Energy Co Ltd [10.0%]; other [4.5%]; Zhejiang Financial Development Co Ltd [1.5%]; Yueqing State Owned Investment Co Ltd [1.3%]; Pingyang Guocheng Holding Co Ltd [0.7%]; Rui'an State-owned Assets Investment Group Co Ltd [0.7%]; Rui'an Construction Development Investment Co Ltd [0.7%]; Cangnan County Urban Investment Group Co Ltd [0.7%]; Yongjia County State Owned Assets Investment Group Co Ltd [0.6%]

Background

Zheneng Yueqing power station is a six-unit coal-fired power plant with a total capacity of 2,520 MW in Zhejiang Province. The first two units, totaling 1,200 MW, were completed in 2008. Units 3 & 4, totaling 1,320 MW, were completed in 2010. The plant is majority-owned by Zhejiang Provincial Energy Group.[1][2]

Proposed expansion

In 2015, it was reported that there was a proposed 2 x 1,000 MW ultra-supercritical coal expansion at the power station.[3]

There was no further news on the proposed expansion until October 2020, when it was reported the new units were seeking permit approval.[4]

Construction for at least one unit was underway, although it was unclear when it began. According to one source, a commencement ceremony of "the third phase" was reportedly held in July 2021.[5] Other sources noted construction began in October 2020[6] or September 2021.[7] Construction of Unit 5 was presumed underway, and in turn, Unit 6 was presumed permitted.

As of June 2022, Unit 6 was also under construction, though the date entering construction remained unclear.[8]

In April 2023, Unit 5 was connected to the grid.[9][10] The unit officially began operating at the end of the month.[11]

In May 2023, construction of Unit 6 was complete, and testing was underway.[12] The unit was successfully connected to the grid.[13][14]

In June 2023, Unit 6 began operating.[15]

Articles and Resources

References

  1. "浙能乐清电厂3号机组投产发电," wenming.org, 2011-6-2
  2. "浙能乐清发电厂工程全部建成投产," 浙江日报, 2010-07-26
  3. "Zheneng Yueqing power station late start," reshi100, 2015-11-22
  4. "又一个百万电厂!浙能乐清电厂三期工程". news.bjx.com.cn. 2020-10-30. Retrieved 2021-01-05.{{cite web}}: CS1 maint: url-status (link)
  5. "乐清电厂三期主体工程开工建设," zhengcaiyun, 2021-08-02
  6. "北极星电力网新闻中心," 北极星电力网新闻中心, 2020/10/30
  7. "乐清电厂三期5号百万机组主体工程开工," 北极星电力网新闻中心, 2021/10/15
  8. 淘汰落后产能 实现绿色发展——浙能乐清电厂三期扩建工程进入施工高峰, Sina, 2022-05-25
  9. 乐清电厂三期5号机组首次并网发电, power.in-en.com, 2023-04-06
  10. 1000MW!乐清电厂三期5号机组首次并网发电, news.bjx.com, 2023-04-06
  11. 1000MW!浙能乐清电厂三期工程5号机组投运, news.bjx.com, 2023-04-28
  12. 【项目】火电|2×1000MW!浙能乐清电厂三期工程6号机组汽轮机冲转一次成功!/国内首套世界最大!冷能发电装置并网试验成功, mp.weixin.qq.com, 2023-05-22
  13. 【项目】火电|1000MW!安徽宿州钱营孜电厂二期开工!/2×1000MW!浙能乐清电厂三期工程6号机组首次并网发电, mp.weixin.qq.com, 2023-06-01
  14. 1000MW!乐清电厂三期6号机组首次并网发电, news.bjx.com, 2023-05-30
  15. 聚焦 | 浙江“大电源”上新!这家电厂百万机组实现“双投”, mp.weixin.qq.com, 2023-06-14

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.