Zhoushan LNG Terminal

From Global Energy Monitor
Part of the
Global Gas Infrastructure Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Zhoushan LNG Terminal (新奥舟山LNG接收站) is an LNG terminal in Zheijang, China and is the first privately funded LNG terminal in China, owned by ENN.[1][2]

Location

Loading map...

Project details

Phase 1

  • Owner: ENN (Zhoushan) LNG Co., Ltd. 新奥 (舟山) 液化天然气有限公司[3]
  • Parent company: ENN Natural Gas Co., Ltd. 新奥天然气股份有限公司
  • Location: Dinghai Beichan, Zhoushan, Zheijang, China
  • Coordinates: 30.100617, 122.282508 (exact)
  • Capacity: 3 mtpa
  • Status: Operating
  • Type: Import
  • Cost: 5.8 billion RMB
  • Start year: 2018

Phase 2

  • Owner: ENN (Zhoushan) LNG Co., Ltd. 新奥 (舟山) 液化天然气有限公司[3]
  • Parent company: ENN Natural Gas Co., Ltd. 新奥天然气股份有限公司
  • Location: Dinghai Beichan, Zhoushan district, Zhejiang province, China[4]
  • Coordinates: 30.100617, 122.282508 (exact)[4]
  • Capacity: 2 mtpa[4]
  • Status: Operating[5]
  • Cost: 2.41 billion RMB[6]
  • Type: Import
  • Start year: 2021

Phase 3

  • Owner: ENN (Zhoushan) LNG Co., Ltd. 新奥 (舟山) 液化天然气有限公司[3]
  • Parent company: ENN Natural Gas Co., Ltd. 新奥天然气股份有限公司
  • Location: Dinghai Beichan, Zhoushan district, Zhejiang province, China[4]
  • Coordinates: 30.100617, 122.282508 (exact)[4]
  • Capacity: 5 mtpa[7]
  • Status: Construction[8]
  • Type: Import
  • Cost: 3.5 billion RMB[9]
  • Start year: 2024[10]
    • Originally 2023
    • Cxpected operation: September 2025
    • Construction start: December 2022[11]

Background

Phase 1

Permitted by NDRC in March 2015, the Zhoushan LNG Terminal began construction in January 2016. Phase I of the terminal is expected to be commissioned in 2018 with a receiving capacity of 3 mtpa.[12][13]

In late 2016, CIMC Enric completed two 160,000 cubic meter storage tanks for the LNG terminal.[14][15]

In October 2018 the terminal began commercial operations.[16] It was estimated to cost 5.8 billion RMB.[17]

Phase 2

A second phase expanding the terminal's capacity to 5 mtpa is expected to come online in 2021.[16] It began construction in Nov 2018. It will add two 160,000 cubic meter storage tanks.[18][19] Phase 2 is estimated to cost 2.4 billion RMB.[17] In April 2019 it was reported that the expansion would create an additional 7 mtpa of capacity and be completed by 2022.[20]

Phase 3

Phase 3 was mentioned in Zhejiang Province's 14th Five-Year Plan. It is slated for operation in 2024[10] and is estimated to cost 3.5 billion RMB.[9]

Phase 3 was permitted in March 2022. It includes 4 storage tanks with 220,000 cubic meters each. The capacity of phase 3 will be 3.5 mtpa.[21][22] Construction of phase 3 began in December 2022. [11] By January 2024, the construction is at advanced stage. The operation was expected in September 2025.[23]

Articles and resources

References

  1. China Approves LNG Bunkering Project in Zhoushan, LNG World News, August 2013
  2. China's first private LNG import terminal project in Zhejiang delayed, Abache Abreu, S&P Global Platts, February 2015
  3. 3.0 3.1 3.2 "新奥(舟山)液化天然气有限公司 - 企查查". www.qcc.com. Retrieved 2021-04-19.{{cite web}}: CS1 maint: url-status (link)
  4. 4.0 4.1 4.2 4.3 4.4 舟山爭奪戰打響,新奧慌了?浙江LNG接收站亂局, KK News, May 27, 2019
  5. "新奥股份(600803):舟山接收站潜力较大;直销气业务好于预期_公司研究_新浪财经_新浪网". stock.finance.sina.com.cn. Retrieved 2022-06-28.
  6. "https://www.qianzhan.com/analyst/detail/220/211015-71bfc2ec.html". qianzhan.com. Retrieved 2022-06-27. {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  7. "浙计经[1998] 0号". webcache.googleusercontent.com. Retrieved 2022-06-28.
  8. "https://www.cctd.com.cn/show-26-215575-1.html". cctd. {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  9. 9.0 9.1 "https://www.qianzhan.com/analyst/detail/220/211015-71bfc2ec.html". qianzhan.com. Retrieved 2022-06-28. {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  10. 10.0 10.1 "http://www.enn-ng.com/content/details28_723.html". enn-ng. Retrieved 2022-06-28. {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  11. 11.0 11.1 "新奥(舟山)LNG接收站三期项目开工-舟山港综合保税区三生企业服务". www.zgzsxq.com. 2022-12. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  12. ENN at a Glance, ENN Group, accessed July 2017
  13. "接收站建设助力液化天然气进口 为投产做最后的冲刺准备---吉林省能源信息服务平台--创视网". www.swpu.edu.cn. {{cite web}}: |first= missing |last= (help)CS1 maint: numeric names: authors list (link) CS1 maint: url-status (link)
  14. China Furthers LNG Bunkering Technologies, The Maritime Executive, January 2017
  15. "中国最全的LNG接收站进度表,没有之一," Sohu, 2018-01-08
  16. 16.0 16.1 China’s ENN starts commercial ops at Zhoushan LNG terminal, LNG World News, Oct. 19, 2018
  17. 17.0 17.1 谭欣雨. "Zhoushan terminal to fuel LNG sector". www.chinadaily.com.cn. Retrieved 2022-06-28.
  18. The third phase of Jiangsu Rudong LNG receiving station was officially opened! The second phase of the new Austrian Zhoushan LNG reception was approved!, Sohu, April 16, 2019
  19. 新奥舟山LNG接收站二期储罐气顶升成功 Tencent News, 12-11-2019
  20. Zhoushan terminal to fuel LNG sector, China Daily, Apr. 9, 2019
  21. "舟山LNG三期获核准 我省天然气保供基础再夯实----省发展改革委". fzggw.zj.gov.cn. 2022-03-22.{{cite web}}: CS1 maint: url-status (link)
  22. "新奥天然气股份有限公司关于 控股子公司投资建设舟山接收站三期项目的公告" (PDF). http://static.sse.com.cn. 2022-10-29. {{cite web}}: External link in |website= (help)CS1 maint: url-status (link)
  23. "新奥LNG接收站储罐项目实现"三顶"同升 三期项目将全面进入内罐安装阶段,预计2025年9月投产_舟山新闻_浙江网". www.chinazj.com.cn. 2024-01-29. Retrieved 2024-02-07.{{cite web}}: CS1 maint: url-status (link)

Related GEM.wiki articles

External resources

External articles