Zhuhai LNG Terminal

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Zhuhai LNG Terminal (珠海LNG接收站, 珠海金湾LNG接收站) is a LNG terminal in Guangdong, China, with phases that are operating and under construction.

Location

Loading map...

Project Details

Phase 1

  • Owner: Guangdong Zhuhai Golden Bay LNG Ltd. (广东珠海金湾液化天然气有限公司)[1]
  • Parent company: CNOOC Gas and Electricity Group Co., Ltd. 30.00%, Guangzhou Development Gas Investment Co., Ltd. 25.00%, Guangdong Energy Group Natural Gas Co., Ltd. 25.00%, Guangdong Yue-Hong Kong Energy Development Co., Ltd. 8.00%, Jiangmen Urban Construction Group Co., Ltd. 3.00%, Zhuhai Special Economic Zone Electric Power Development Group Co., Ltd. 3.00%, Zhongshan Xingzhong Energy Development Co., Ltd. 3.00%, Foshan Huatuoneng Energy Investment Co., Ltd. 3.00%.
中海石油气电集团有限责任公司 30.00%
广州发展燃气投资有限公司 25.00%
广东能源集团天然气有限公司 25.00%
广东粤港能源发展有限公司 8.00%
江门市城建集团有限公司 3.00%
珠海经济特区电力开发集团有限公司 3.00%
中山兴中能源发展股份有限公司 3.00%
佛山市华拓能能源投资有限公司 3.00%
  • Location: Gaolan Island, Zhuhai, Guangdong, China
  • Coordinates: 21.90599, 113.219326 (exact)
  • Capacity: 3.5 mtpa
  • Status: Operating
  • Type: Import
  • Start year: 2013

Phase 2

  • Owner: Guangdong Zhuhai Golden Bay LNG Ltd. (广东珠海金湾液化天然气有限公司)[1]
  • Parent company: CNOOC Gas and Electricity Group Co., Ltd. 30.00%, Guangzhou Development Gas Investment Co., Ltd. 25.00%, Guangdong Energy Group Natural Gas Co., Ltd. 25.00%, Guangdong Yue-Hong Kong Energy Development Co., Ltd. 8.00%, Jiangmen Urban Construction Group Co., Ltd. 3.00%, Zhuhai Special Economic Zone Electric Power Development Group Co., Ltd. 3.00%, Zhongshan Xingzhong Energy Development Co., Ltd. 3.00%, Foshan Huatuoneng Energy Investment Co., Ltd. 3.00%.
  • Location: Gaolan Island, Zhuhai, Guangdong, China
  • Coordinates: 21.90599, 113.219326 (exact)
  • Capacity: 3.5 mtpa
  • Status: Construction
  • Type: Import
  • Start year: 2024[2]
    • Originally 2023

Background

Zhuhai LNG Terminal is an LNG terminal in Guangdong, China.[3][4]

Phase I of the Zhuhai LNG Terminal began construction in October 2010,[5] and was completed in 2013 with three 160,000 cubic meter tanks and a receiving capacity of 3.5 mpta.[3] [6]The terminal will supply natural gas to the cities of Guangzhou, Foshan, Zhuhai, Zhongshan and Jiangmen.[7] A 3.5-mtpa Phase Two of the project was proposed.[8] In May 2020, Phase Two began the invitation to tender for the social stability risk assessment service, signaling the start of the second phase of the LNG terminal project.[9]

Phase 2 received permit for construction in May 2021.[10] It began construction in June 2021, including five storage tanks with 270,000 cubic meters each. The capacity of phase 2 is 3.5 mtpa.[11] The operating date was set at the end of 2023. By February 2023,[10] the construction is ongoing.[11]

金湾绿能港(珠海LNG)二期项目于2021年6月开工建设,同时建设5座27万立方米液化天然气储罐及配套设施;2024年建成投产后,金湾绿能港(珠海LNG)二期项目将成为华南地区规模最大的天然气储运基地,年处理能力可达700万吨,折合气态天然气约100亿立方米。按照1户居民每月用气30立方米计算,100亿立方米天然气大约可供近3000万户居民使用1年。[11]

As of September 2023, the construction is still ongoing, and a new start year was reported as 2024.[2]As of December 2023, 81.6% of the construction has been completed according to the local media.[12]

Articles and resources

References

  1. 1.0 1.1 广东珠海金湾液化天然气有限公司 QCC.com
  2. 2.0 2.1 "https://www.argusmedia.com/en/news/2404382-viewpoint-china-poised-to-remain-lng-demand-centre". {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  3. 3.0 3.1 Zhuhai LNG Terminal, A Barrel Full, accessed April 2017
  4. 中国海油珠海LNG项目一期工程 广东珠海金湾液化天然气有限公司 China Association of Construction Enterprise Mangement website
  5. 中国海油珠海LNG项目一期工程开工 source: sasac.gov.cn. 文章来源:中国海洋石油总公司, 2010-10-22.
  6. "中海油珠海LNG成功接卸首船气-新闻-能源资讯-中国能源网-来源:中国海洋石油报". www.china5e.com. 2013-11-01.{{cite web}}: CS1 maint: url-status (link)
  7. CNOOC delays commission of Zhuhai LNG terminal to late October, Ricki Wang, ICIS, September 2013
  8. 中海油珠海LNG接收站 Zhuhai Government website, 11-06-2020
  9. "广东珠海LNG扩建项目二期工程社会稳定性风险评估服务公开询价公告_OILUP油气淘". www.oilup.com. 2020-05-21. Retrieved 2021-03-31.{{cite web}}: CS1 maint: url-status (link)
  10. 10.0 10.1 "珠海LNG扩建项目二期工程获批 计划6月动工--深圳特区报--新浪网". k.sina.com.cn. 2021-05-10.{{cite web}}: CS1 maint: url-status (link)
  11. 11.0 11.1 11.2 "粤港澳大湾区首座27万立方米 LNG 储罐外罐主体结构完工 设计建造技术国际领先--"珠海金湾"微信公众号". www.jinwan.gov.cn. 2023-02-08.{{cite web}}: CS1 maint: url-status (link)
  12. "珠海金湾"绿能港"二期项目完成81% 预计2024年建成投产--凤凰网广东珠海". gd.ifeng.com. 2023-12-16.{{cite web}}: CS1 maint: url-status (link)