Aktobe Generatsiya steel plant (Cталеплавильный завод ТОО «Актобе Генерация»), also known as Aktobe Generatsia steel plant, is a steel plant in Aktobe, Kazakhstan that operates blast furnace (BF) and basic oxygen furnace (BOF) technology.

Location

The map below shows the approximate location of the plant in Aktobe, Kazakhstan:

Loading map...
  • Location: Aktobe, Kazakhstan
  • Coordinates (WGS 84): 50.355117, 57.145119 (approximate)

Background

Construction of the plant was initially announced in 2022, but the project was delayed due to insufficient technical conditions for connecting to the gas pipeline network. In early 2024, it was reported that construction efforts had resumed. Aktobe Generatsiya stated that they were working with potential equipment and energy resource suppliers, as well as addressing key technical and economic factors. The construction of the plant is expected to commence in 2025.[1][2]

Plant Details

Table 1: General Plant Details

Announced date Construction date Start date Workforce size Power source Iron ore source
2022[1] 2025[3] 2026-02[1][4] 2600[5] Captive combined gas-fired power plant[5] unknown

Table 2: Ownership and Parent Company Information

Parent company Parent company PermID Parent company GEM ID Owner Owner company PermID Owner company GEM ID
Aktobe Generatsiya LLC [100.0%] unknown [100.0%] E100001012067 [100.0%] Aktobe Generatsiya LLC [100%][4] unknown E100001012067 [100%]

Table 3: Process and Products

Steel product category Steel products Main production equipment
crude, semi-finished[5] bloom, billet[5][3] BF; BOF

Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)

1Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1 Basic oxygen furnace steelmaking capacity Nominal crude steel capacity (total)
announced 818[5] 818[5]

Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)

1Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1 Blast furnace capacity Nominal iron capacity (total)
announced 728[5] 728[5]

Table 6: Upstream Products Production Capacities (thousand tonnes per annum)

Ferronickel Sinter
NF[5] 1300[5]

Unit Details

Table 7: Blast Furnace Details

Unit name Status Announced date Construction date Start date Current size Current capacity (ttpa)
unknown BF (1) announced[3][4] 2022[1][4] 2025[3] 2026[4] 800.0 m3[5] 728[5]

Table 8: Basic Oxygen Furnace Details

Unit name Status Announced date Construction date Start date Current capacity (ttpa) Current size
BOF 1 announced[3][5][4] 2022[1][4] 2025[3] 2026[4] 409[5] 50.0 tonnes[5]
BOF 2 announced[3][5][4] 2022[1][4] 2025[3] 2026[4] 409[5] 50.0 tonnes[5]

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 https://web.archive.org/web/20221108102841/https://aktobetimes.kz/novosti/9189-jekspert-novyj-zavod-v-aktobe-mozhet-ostavit-ilek-bez-vody.html. Archived from the original on 2022-11-08. {{cite web}}: Missing or empty |title= (help)
  2. "В Казахстане вернулись к строительству уникального производства". LS. March 20, 2024. Retrieved October 2, 2024.{{cite web}}: CS1 maint: url-status (link)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 https://agmpnews.kz/v-kazahstane-vernulis-k-stroitelstvu-unikalnogo-proizvodstva/. {{cite web}}: Missing or empty |title= (help)
  4. 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 https://web.archive.org/web/20231113194938/https://www.gov.kz/memleket/entities/aktobe-zher-paidalanuy/press/article/details/106958?lang=ru. Archived from the original on 2023-11-13. {{cite web}}: Missing or empty |title= (help)
  5. 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 5.11 5.12 5.13 5.14 5.15 5.16 5.17 (PDF) https://web.archive.org/web/20240119094225/https://www.gov.kz/uploads/2023/1/4/1e32591c375b8c5d0b54ac60fdce5cf5_original.5251522.pdf. Archived from the original (PDF) on 2024-01-19. {{cite web}}: Missing or empty |title= (help)

Resources