Aktobe Generatsiya steel plant
This article is part of the Global Iron and Steel Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Aktobe Generatsiya steel plant (Cталеплавильный завод ТОО «Актобе Генерация»), also known as Aktobe Generatsia steel plant, is a steel plant in Aktobe, Kazakhstan that operates blast furnace (BF) and basic oxygen furnace (BOF) technology.
Location
The map below shows the approximate location of the plant in Aktobe, Kazakhstan:
- Location: Aktobe, Kazakhstan
- Coordinates (WGS 84): 50.355117, 57.145119 (approximate)
Background
Construction of the plant was initially announced in 2022, but the project was delayed due to insufficient technical conditions for connecting to the gas pipeline network. In early 2024, it was reported that construction efforts had resumed. Aktobe Generatsiya stated that they were working with potential equipment and energy resource suppliers, as well as addressing key technical and economic factors. The construction of the plant is expected to commence in 2025.[1][2]
Plant Details
Table 1: General Plant Details
Announced date | Construction date | Start date | Workforce size | Power source | Iron ore source |
---|---|---|---|---|---|
2022[1] | 2025[3] | 2026-02[1][4] | 2600[5] | Captive combined gas-fired power plant[5] | unknown |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Parent company GEM ID | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|---|---|
Aktobe Generatsiya LLC [100.0%] | unknown [100.0%] | E100001012067 [100.0%] | Aktobe Generatsiya LLC [100%][4] | unknown | E100001012067 [100%] |
Table 3: Process and Products
Steel product category | Steel products | Main production equipment |
---|---|---|
crude, semi-finished[5] | bloom, billet[5][3] | BF; BOF |
Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
Capacity operating status1 | Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|
announced | 818[5] | 818[5] |
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
Capacity operating status1 | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|
announced | 728[5] | 728[5] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Ferronickel | Sinter |
---|---|
NF[5] | 1300[5] |
Unit Details
Table 7: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current size | Current capacity (ttpa) |
---|---|---|---|---|---|---|
unknown BF (1) | announced[3][4] | 2022[1][4] | 2025[3] | 2026[4] | 800.0 m3[5] | 728[5] |
Table 8: Basic Oxygen Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current capacity (ttpa) | Current size |
---|---|---|---|---|---|---|
BOF 1 | announced[3][5][4] | 2022[1][4] | 2025[3] | 2026[4] | 409[5] | 50.0 tonnes[5] |
BOF 2 | announced[3][5][4] | 2022[1][4] | 2025[3] | 2026[4] | 409[5] | 50.0 tonnes[5] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 https://web.archive.org/web/20221108102841/https://aktobetimes.kz/novosti/9189-jekspert-novyj-zavod-v-aktobe-mozhet-ostavit-ilek-bez-vody.html. Archived from the original on 2022-11-08.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "В Казахстане вернулись к строительству уникального производства". LS. March 20, 2024. Retrieved October 2, 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 https://agmpnews.kz/v-kazahstane-vernulis-k-stroitelstvu-unikalnogo-proizvodstva/.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 https://web.archive.org/web/20231113194938/https://www.gov.kz/memleket/entities/aktobe-zher-paidalanuy/press/article/details/106958?lang=ru. Archived from the original on 2023-11-13.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 5.11 5.12 5.13 5.14 5.15 5.16 5.17 (PDF) https://web.archive.org/web/20240119094225/https://www.gov.kz/uploads/2023/1/4/1e32591c375b8c5d0b54ac60fdce5cf5_original.5251522.pdf. Archived from the original (PDF) on 2024-01-19.
{{cite web}}
: Missing or empty|title=
(help)