ArcelorMittal Pecém steel plant (CSP - Companhia Siderúrgica do Pecém), also known as CSP Pecém steel plant (predecessor), is a steel plant in São Gonçalo do Amarante, Ceará, Brazil that operates blast furnace (BF) and basic oxygen furnace (BOF) technology.
Location
The map below shows the exact location of the plant in São Gonçalo do Amarante, Ceará, Brazil:
- Location: Rod CE 155, Km 11.5, Pecém, São Gonçalo do Amarante, CE 62674-000, Brazil
- Coordinates (WGS 84): -3.585917, -38.858932 (exact)
Background
Originally founded as Companhia Siderúrgica do Pecém, the CSP plant is Brazil's most modern integrated steel plant and the first in the country's Northeast region. Occupying a 571-hectare site at the Pecém Industrial and Port Complex (CIPP) in the Brazilian state of Ceará, it specializes in the production and export of high quality rolled steel products for the naval, oil & gas, automotive, and construction industries.[1]
CSP was founded in 2008 as a joint venture between Brazilian mining and logistics company Vale (NYSE: VALE) and the South Korean companies Dongkuk Steel and Posco (NYSE: PKX). Steel production at the plant started in July 2016.[1]
In March 2023, international steel giant ArcelorMittal purchased the CSP plant for approximately US $2.2 billion.[2]
Plant Details
Table 1: General Plant Details
Start date | Workforce size | Power source |
---|---|---|
2016[3] | 2500[4] | onsite 218MW gas-fired power plant[5][6] |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Parent company GEM ID | Owner | Owner company PermID | Owner company GEM ID |
---|---|---|---|---|---|
ArcelorMittal SA; small shareholder(s) | 5000030092; not applicable | E100000000687; E100001015587 | ArcelorMittal Brasil SA[7][8][9] | 4295859712 | E100001000493 |
Table 3: Process and Products
Steel product category | Steel products | Steel sector end users | ISO 14001 | ISO 50001 | Responsible steel | Main production equipment |
---|---|---|---|---|---|---|
semi-finished, finished rolled[10] | slab, plate[10][3][11] | automotive, building and infrastructure, energy, transport[3] | 2023-10-25[12] | unknown[13] | unknown[14] | BF; BOF |
Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
Capacity operating status1 | Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|
operating | 3000[15][8][16][17][18][19] | 3000[15][8][16][17][18][19] |
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
Capacity operating status1 | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|
operating | 3192[20] | 3192[20] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Ferronickel | Sinter | Coke | Pellets |
---|---|---|---|
NF | 4747[21] | 1130[21] | 0[22] |
Table 7: Actual Plant-level Crude Steel Production by Year (thousand tonnes per annum)
Year | BOF production | Total (all routes) |
---|---|---|
2019 | 2866[23] | 2866[23] |
2020 | 2743[10] | 2743[10] |
2021 | 2811[24] | 2811[24] |
2022 | 2794[25] | 2794[25] |
2023 | 3000[26][27] | 3000[26][27] |
Table 8: Actual Plant-level Crude Iron Production by Year (thousand tonnes per annum)
Year | BF production | Total (all routes) |
---|---|---|
2019 | 2904[28] | 2904[28] |
2020 | 2779[28] | 2779[28] |
2021 | 2860[29] | 2860[29] |
2022 | 2781[30] | 2781[30] |
2023 | 2986[21] | 2986[21] |
Unit Details
Table 9: Blast Furnace Details
Unit name | Status | Construction date | Start date | Furnace manufacturer and model | Current size | Current capacity (ttpa) | Decarbonization technology |
---|---|---|---|---|---|---|---|
BF 1 | operating[8] | 2022-07[31] | 2016[32][16][20] | POSCO[31] | 3800.0[33] | 3192[20] | unknown |
Table 10: Basic Oxygen Furnace Details
Unit name | Status | Current capacity (ttpa) | Current size |
---|---|---|---|
unknown BOF (1) | operating[21] | 1500[8][17][15][19] | 300.0 tonnes[34][11] |
unknown BOF (2) | operating[21] | 1500[16][18] | 300.0 tonnes[34][11] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 "Our History – CSP". CSP. Retrieved 2020-07-31.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "ArcelorMittal completes acquisition of CSP in Brazil". ArcelorMittal. March 9, 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 3.2 https://web.archive.org/web/20211211142440/http://www.cspecem.com/en/about-us/your-history/. Archived from the original on 2021-12-11.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://brasil.arcelormittal.com/sala-imprensa/noticias/brasil/arcelormittal-unidade-pecem-completa-8-anos-com-214-mt-de-placas-de-aco-produzidas-do-ceara-para-o-brasil-e-o-mundo.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "Termelétrica da Siderúrgica entra em operação - Negócios". Diário do Nordeste. 2016-10-15. Archived from the original on 2024-01-25.
- ↑ https://web.archive.org/web/20220127020053/https://www.cspecem.com/pt-br/2017/07/termeletrica-da-csp-ja-gerou-1-150-000-mwh/. Archived from the original on 2022-01-27.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20230120045745/https://www.steelorbis.com/steel-news/latest-news/brazil-approves-arcelormittals-acquisition-of-csp-for-22-billion-1275005.htm. Archived from the original on 2023-01-20.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 8.3 8.4 "ArcelorMittal agrees acquisition of CSP in Brazil". ArcelorMittal. 2022-07-28. Archived from the original on 2022-09-29.
- ↑ "ArcelorMittal completes acquisition of CSP in Brazil". ArcelorMittal. 2023-03-09. Archived from the original on 2024-01-25.
- ↑ 10.0 10.1 10.2 10.3 "Pocket Yearbook - A Siderurgia em Números 2021" (PDF). Instituto Aço Brasil. 2021-06-30. Archived from the original (PDF) on 2022-01-20.
- ↑ 11.0 11.1 11.2 (PDF) https://web.archive.org/web/20220119142707/https://www.alacero.org/sites/default/files/revista/pagina/al562_nuevas_plantas_latinoamericanas.pdf. Archived from the original (PDF) on 2022-01-19.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://brasil.arcelormittal.com/certificados-politicas/pecem/meio-ambiente/certificado-sistema-de-gestao-ambiental.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "Certificates and Policies". ArcelorMittal. Archived from the original on 2021-12-28.
- ↑ https://www.responsiblesteel.org/issued-certificates-and-ongoing-audits.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 15.0 15.1 15.2 https://web.archive.org/web/20240110014039/http://www.aecipp.com.br/pt-br/associados/arcelormittal-pecem. Archived from the original on 2024-01-10.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 16.0 16.1 16.2 16.3 https://web.archive.org/web/20220811030808/https://www.cspecem.com/pt-br/sobre-a-csp/nossa-historia/. Archived from the original on 2022-08-11.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 17.0 17.1 17.2 https://web.archive.org/web/20220813190714/https://www.cspecem.com/en/about-us/steel-productive-process/.
{{cite web}}
: Check|archive-url=
value (help); Missing or empty|title=
(help) - ↑ 18.0 18.1 18.2 https://web.archive.org/web/20221126120359/https://www.cspecem.com/pt-br/sobre-a-csp/processo-de-producao-do-aco/. Archived from the original on 2022-11-26.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 19.0 19.1 19.2 https://web.archive.org/web/20240110013934/https://www.primetals.com/press-media/news/brazilian-customer-csp-to-improve-safety-and-plant-performance-with-new-relining-machine-from-primetals-technologies?setLang=1&cHash=4558261501e8eb846a46751abbcb473d. Archived from the original on 2024-01-10.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 20.0 20.1 20.2 20.3 https://web.archive.org/web/20180605105217/https://abmproceedings.com.br/ptbr/article/inicio-e-estabilizacao-da-operacao-do-alto-forno-1-da-csp. Archived from the original on 2018-06-05.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 21.0 21.1 21.2 21.3 21.4 21.5 (PDF) https://www.acobrasil.org.br/site/wp-content/uploads/2024/07/Anuario_Completo_2024.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "Fact Book 2023" (PDF). ArcelorMittal. 2024-04-22. Archived from the original (PDF) on 2024-06-10.
- ↑ 23.0 23.1 "Pocket Yearbook - A Siderurgia em Números 2020" (PDF). Instituto Aço Brasil. 2020-04-30. Archived from the original (PDF) on 2021-12-30.
- ↑ 24.0 24.1 "Pocket Yearbook - A Siderurgia em Números 2022" (PDF). Instituto Aço Brasil. 2022-06-30. Archived from the original (PDF) on 2022-06-25.
- ↑ 25.0 25.1 "Pocket Yearbook - Indústria do Aço em Números 2023" (PDF). Instituto Aço Brasil. 2023-06-30. Archived from the original (PDF) on 2024-01-19.
- ↑ 26.0 26.1 "Brazil's ArcelorMittal Pecem reaches design capacity". News — GMK Center. 2024-01-24. Archived from the original on 2024-02-14.
- ↑ 27.0 27.1 (PDF) https://www.acobrasil.org.br/site/wp-content/uploads/2024/06/Mini_anuario_2024_AcoBrasil.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 28.0 28.1 28.2 28.3 "Brazil Steel Databook - Anuário Estatístico 2021" (PDF). Instituto Aço Brasil. 2021-07-31. Archived from the original (PDF) on 2022-01-20.
- ↑ 29.0 29.1 "Brazil Steel Databook - Anuário Estatístico 2022" (PDF). Instituto Aço Brasil. 2022-07-31. Archived from the original (PDF) on 2022-07-22.
- ↑ 30.0 30.1 "Brazil Steel Databook - Anuário Estatístico 2023" (PDF). Instituto Aço Brasil. 2023-07-31. Archived from the original (PDF) on 2023-08-10.
- ↑ 31.0 31.1 https://www.yumpu.com/en/document/read/13753841/steel-plant.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20210727110107/https://g1.globo.com/ceara/noticia/siderurgica-do-pecem-celebra-inicio-oficial-das-operacoes-no-ceara.ghtml. Archived from the original on 2021-07-27.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://www.noticiasdemineracao.com/produ%C3%A7%C3%A3o/news/1133929/sider%C3%BArgica-da-vale-cear%C3%A1-come%C3%A7a-opera%C3%A7%C3%B5es-alto-forno.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 34.0 34.1 https://web.archive.org/web/20220319200315/http://www.cspecem.com/en/about-us/steel-productive-process/. Archived from the original on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help)