Baicheng Fuda Bar Rolling Co Ltd (白城市富达棒材轧制有限公司) is an electric arc furnace (EAF) steel plant operating in Baicheng, Jilin, China.

Location

The map below shows the exact location of the plant in Baicheng, Jilin, China:

Loading map...
  • Location: Zhujiang Road, Baicheng Industrial Park, Jilin Province
  • Coordinates (WGS 84): 45.593303, 122.895588 (exact)

Background

According to the announcement of capacity replacement, the company planned to build a 105-ton electric furnace, and two 40-ton electric furnaces will be retired at the same time.[1]

The company was fined 50,000 RMB for failing to promptly disclose information related to solid waste pollution prevention and environmental protection concerning the solid waste it generated.[2]

Plant Details

Table 1: General Plant Details

Phase Plant status Announced date Construction date Start date Pre-retirement announcement date Retired date Workforce size Power source
Main plant Operating[3] 2009[3] 32[3] State Power Investment Corporation Jilin Longhua Baicheng Combined Heat and Power Plant.[4]
Closure Retired[5] 2021-12[6] 2022-10[5] State Power Investment Corporation Jilin Longhua Baicheng Combined Heat and Power Plant.[4]
Expansion Construction[5] 2021-12[6] 2022-10[5] State Power Investment Corporation Jilin Longhua Baicheng Combined Heat and Power Plant.[4]

Table 2: Ownership and Parent Company Information

Phase Parent company Parent company GEM ID Owner Owner company GEM ID
Main plant Baicheng Fuda Bar Rolling Co Ltd [100%] E100000123261 [100%] Baicheng Fuda Bar Rolling Co., Ltd.[3] E100000127199

Table 3: Process and Products

Phase Steel product category Steel products Main production equipment Detailed production equipment
Main plant finished rolled[3] bar[3] EAF[6] 2 EAF (2x40-tonne)[6]
Closure finished rolled[3] bar[3] EAF[6] 2 EAF (2x40-tonne)[6]
Expansion finished rolled[3] bar[3] EAF[6] 1 EAF (1x105-tonne)[6]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating
Closure retired 800 TTPA[6][6] 800 TTPA[6][6]
Expansion construction 788 TTPA[6] 788 TTPA[6]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status*
Main plant operating
Closure retired
Expansion construction

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. 白城市富达棒材轧制有限公司钢铁产能置换方案公告,吉林省工业信息化厅,December 3, 2021
  2. "白城市生态环境局行政处罚决定书(白环罚字〔2022〕1号)". 白城市生态环境局. 2022-07-29.
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 https://www.qcc.com/firm/87f40239ca1fac04192706cf350a5908.html. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 https://web.archive.org/web/20231127202951/https://news.bjx.com.cn/html/20170623/832911.shtml. Archived from the original on 27 November 2023. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 https://mp.weixin.qq.com/s?__biz=MzI1MzM1MDcwMQ==&mid=2247712853&idx=1&sn=253b2b5e174b01bb6986b6062eed1697&chksm=e9d80617deaf8f01b744c1d1852b584be6c60af6f4845221110741077db080c93383793ed322&scene=27. {{cite web}}: Missing or empty |title= (help)
  6. 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 https://factory.mysteel.com/21/1203/13/326B7411A0FAF1A6.html. {{cite web}}: Missing or empty |title= (help)

Resources