Cangzhou Lingang Sanling Metal Co Ltd

From Global Energy Monitor
This article is part of the
Global Steel Plant Tracker, a project of Global Energy Monitor.
Download full dataset
Report an error
Sub-articles:

Cangzhou Lingang Sanling Metal Co Ltd (沧州临港三菱金属制品有限公司) is an electric arc furnace (EAF) steel plant operating in Cangzhou, Hebei, China.

Location

The map below shows the exact location of the plant in Cangzhou, Hebei, China:

Loading map...
  • Location: Lingang Economic Development District, Cangzhou City, Hebei Province
  • Coordinates (WGS 84): 38.311738, 117.457779 (exact)

Background

According to the announcement of capacity replacement, the company plans to build two 70-ton alloy steel electric furnaces, which are expected to be put into operation in December 2024, and one 100-ton electric furnaces will be eliminated at the same time.[1]

Plant Details

Table 1: General Plant Details

Phase Plant status Announced date Start date Workforce size
Main plant Operating[2] 1995[2] 311[3]
Expansion Announced[4] 2021-12[4] 2024[4]

Table 2: Ownership and Parent Company Information

Phase Parent company Parent company GEM ID Owner Owner company GEM ID
Main plant Cangzhou Lingang Sanling Metal Co Ltd [100%] E100000123261 [100%] Cangzhou Lingang Sanling Metal Co., Ltd.[2] E100000126397

Table 3: Process and Products

Phase Steel product category Steel products Steel sector end users ISO 14001 ISO 50001 Main production equipment Detailed production equipment
Main plant finished rolled[5] bar, round bar[5] automotive; tools and machinery[5] 2018-04-26 00:00:00[6] 2018-04-26 00:00:00[6] EAF[5] 2 EAF (2x70-tonne)[5]
Expansion finished rolled[5] bar, round bar[5] automotive; tools and machinery[5] EAF[5] 1 EAF (1x100-tonne)[4]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating 1000 TTPA[4][4] 1000 TTPA[4][4]
Expansion announced 1000 TTPA[4] 1000 TTPA[4]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status*
Main plant operating
Expansion announced

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. 沧州临港三菱金属制品有限公司技术改造项目产能置换方案公告,河北省工业信息化厅,December 1, 2021
  2. 2.0 2.1 2.2 https://www.qcc.com/firm/441ef59b5bdd1eccf9cef1e54af6e4cd.html. {{cite web}}: Missing or empty |title= (help)
  3. https://web.archive.org/web/20230928131347/https://aiqicha.baidu.com/company_detail_28793561882330. Archived from the original on 28 September 2023. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 https://web.archive.org/web/20220319174959/https://m.mysteel.com/21/1201/11/60A7CD45E632D731_abc.html. Archived from the original on 19 March 2022. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 https://web.archive.org/web/20220318235834/https://www.jiuyezhan.com/company/1098.html. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://web.archive.org/web/20231005193725/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E6%B2%A7%E5%B7%9E%E4%B8%B4%E6%B8%AF%E4%B8%89%E8%8F%B1%E9%87%91%E5%B1%9E%E5%88%B6%E5%93%81%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 05 October 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)

Resources