Changzhou Eastern Special Steel Co Ltd
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Changzhou Eastern Special Steel Co Ltd (常州东方特钢有限公司), also known as Jiangsu Jinkai Steel Co., Ltd., is a blast furnace-basic oxygen furnace (BF-BOF) and electric arc furnace (EAF) steel plant operating in Changzhou, Jiangsu, China.
Location
The map below shows the exact location of the plant in Changzhou, Jiangsu, China:
- Location: No. 5 Dongfang Road, Huangli Town, Wujin District, Changzhou City, Jiangsu Province
- Coordinates (WGS 84): 31.602554, 119.724256 (exact)
Background
As the company failed to pass the preliminary review by Jiangsu Province due to voluntary abandonment of the regulatory announcement, and has now been included in the list of steel companies to be revoked.[1]
According to the capacity replacement plan in December 2019, the company plans to build a 1820m3 blast furnace and two 100-tonne basic oxygen furnaces (BOF).[2]The Environment Impact Assessment report of the project was approved in November 2022.[3]
Plant Details
Table 1: General Plant Details
Phase | Plant status | Announced date | Start date | Pre-retirement announcement date | Workforce size | Power source |
---|---|---|---|---|---|---|
Main plant | Operating[4] | – | 2010[5] | – | 2670[4] | Changzhou Power Supply Company[6] |
Expansion | Announced[7][8] | 2019-12[7] | – | – | – | – |
Closure | Operating pre-retirement[7][8] | – | – | 2019-12[7] | – | Changzhou Power Supply Company[6] |
Table 2: Ownership and Parent Company Information
Phase | Parent company | Parent company GEM ID | Owner | Owner company GEM ID |
---|---|---|---|---|
Main plant | Changzhou Dongrun Special Steel Co Ltd [90.0%]; persons [10.0%] | E100000123261 [100%] | Changzhou Eastern Special Steel Co., Ltd.[4] | E100000126487 |
Table 3: Process and Products
Phase | Steel product category | Steel products | Steel sector end users | ISO 14001 | ISO 50001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|---|---|
Main plant | finished rolled[5][9] | bar, continuous casting rounds, T-shaped guide rail steel, H-shaped steel[5][9] | tools and machinery[10] | 2022[10] | 2023[10] | BF, BOF, EAF[5] | 2 BOF (2x80-tonne); 2 EAF (2x50-tonne)[11] |
Expansion | finished rolled[5][9] | bar, continuous casting rounds, T-shaped guide rail steel, H-shaped steel[5][9] | tools and machinery[10] | – | – | BF, BOF[7] | 2 BOF (2x100-tonne)[7] |
Closure | finished rolled[5][9] | bar, continuous casting rounds, T-shaped guide rail steel, H-shaped steel[5][9] | tools and machinery[10] | – | – | BF, BOF, EAF[7] | 4 BOF (4x40-tonne); 1 EAF (1x50 tonne)[7] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Basic oxygen furnace steelmaking capacity | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|---|
Main plant | operating | – | 360 TTPA[7] | 360 TTPA[7] |
Expansion | announced | 2300 TTPA[7][7] | – | 2300 TTPA[7][7] |
Closure | operating pre-retirement | 2400 TTPA[7][7][7][7] | 360 TTPA[7] | 2760 TTPA[7][7][7][7][7] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|---|
Main plant | operating | – | – |
Expansion | announced | 1560 TTPA[7] | 1560 TTPA[7] |
Closure | operating pre-retirement | 1560 TTPA[7][7][7] | 1560 TTPA[7][7][7] |
Blast Furnace Details
Table 6: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Retired date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|---|
1 | operating pre-retirement[11] | unknown | unknown | unknown | unknown | 550 m³[11] | 520[7] | unknown | 2023-09-25[12] |
2 | operating pre-retirement[11] | unknown | unknown | unknown | unknown | 550 m³[11] | 520[7] | unknown | unknown |
3 | operating pre-retirement[11] | unknown | unknown | unknown | unknown | 550 m³[11] | 520[7] | unknown | 2021-02-02[13] |
unknown | announced[7] | 2019-12[7] | unknown | unknown | – | 1820 m³[7] | 1560[7] | unknown | unknown |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ 全国规范钢铁企业拟增至263家(附全名单及其装备), 北极星大气网, Retrieved on: Jul. 16, 2020
- ↑ 关于常州东方特钢有限公司产能置换方案的公告,江苏省工业和信息化厅,December 25, 2019
- ↑ "江苏省生态环境厅 建设项目(核与辐射除外)环评 省生态环境厅关于常州东方特钢有限公司炼铁、炼钢减量置换升级改造项目环境影响报告书的批复". sthjt.jiangsu.gov.cn. 2022-11-25. Retrieved 2023-01-03.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 4.0 4.1 4.2 https://www.qcc.com/firm/12bb8671b6189fe3be58819928b20610.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.7 https://web.archive.org/web/20220113211259/http://www.czdftg.com/jieshao/qiyejianjie/. Archived from the original on 13 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.0 6.1 https://web.archive.org/web/20231129193556/https://www.3haojob.com/aj/164117289066.html. Archived from the original on 29 November 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 7.16 7.17 7.18 7.19 7.20 7.21 7.22 7.23 7.24 7.25 7.26 7.27 7.28 7.29 7.30 7.31 7.32 7.33 7.34 7.35 7.36 7.37 7.38 https://info.lgmi.com/html/201912/25/6404.htm.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 http://sthjt.jiangsu.gov.cn/art/2022/11/25/art_83568_10684708.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 9.2 9.3 9.4 9.5 https://web.archive.org/web/20220126183455/http://www.czdftg.com/chanpinfuwu/zx/. Archived from the original on 26 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 10.2 10.3 10.4 https://web.archive.org/web/20240119065445/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E5%B8%B8%E5%B7%9E%E4%B8%9C%E6%96%B9%E7%89%B9%E9%92%A2%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 19 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 11.2 11.3 11.4 11.5 11.6 https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml;https://www.primetals.com/cn/%E6%96%B0%E9%97%BB%E6%8A%A5%E9%81%93/%E6%96%B0%E9%97%BB/primetals-technologies-completes-first-ultra-low-emission-technology-project-for-bof-off-gas-at-changzhou-eastran.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://www.zallsteel.com/news/article/detail?id=11641.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://www.sohu.com/a/447959172_120207616#google_vignette.
{{cite web}}
: Missing or empty|title=
(help)