Fujian Sanbao Steel Co Ltd

From Global Energy Monitor
This article is part of the
Global Steel Plant Tracker, a project of Global Energy Monitor.
Download full dataset
Report an error
Sub-articles:

Fujian Sanbao Steel Co Ltd (福建三宝钢铁有限公司), also known as Zhangzhou Sanbao Iron and Steel Co., is a blast furnace-basic oxygen furnace (BF-BOF) and electric arc furnace (EAF) steel plant operating in Zhangzhou, Fujian, China.

Location

The map below shows the exact location of the plant in Zhangzhou, Fujian, China:

Loading map...
  • Location: Punan Town, Xiangcheng District, Zhangzhou City, Fujian Province
  • Coordinates (WGS 84): 24.635769, 117.603677 (exact)

Background

According to the capacity replacement plan in November 2018, the company plans to build a 1700m3 BF and a 1350m3 BF.[1][2] In November 2020, the 1700m3 BF was officially put into operation.[3]The 630m3 BF was demolished in September 2021.[4][5]

According to the announcement of capacity replacement in June 2021, it is planned to build 2 EAF (2x105-tonne)with a capacity of 1575 thousand tonnes per annum and remove 2 EAF (1x70-tonne, 1x90-tonne) with a capacity of 1760 thousand tonnes per annum.[6] The New #1 EAF has started to operate on January 16, 2023.[7]

The company completed the on-site verification of the pre-commissioning consistency of the Steelmaking Capacity Replacement (#2 EAF) project in March 2024.[8]

Plant Details

Table 1: General Plant Details

Phase Plant status Announced date Construction date Start date Pre-retirement announcement date Retired date Workforce size Power source
Main plant Operating[9] 1999[10] 3384[11] Rooftop Distributed Photovoltaic Power Generation[12]
Closure Retired[13] 2021-07[14] 2023[13] Rooftop Distributed Photovoltaic Power Generation[15]
Closure Operating pre-retirement[14] 2021-07[14] 2024[16] Rooftop Distributed Photovoltaic Power Generation[15]
Expansion Operating[13] 2021-07[14] 2023[13] Rooftop Distributed Photovoltaic Power Generation[15]
Expansion Construction[17][14] 2021-07[14] 2022[17] 2024[14] Rooftop Distributed Photovoltaic Power Generation[15]

Table 2: Ownership and Parent Company Information

Phase Parent company Parent company GEM ID Owner Owner company PermID Owner company GEM ID
Main plant Sanbao Group Co Ltd [100.0%] E100000123261 [96.9%]; E100000001753 [3.1%] Fujian Sanbao Steel Co., Ltd.[9] 4298346618 E100000126246

Table 3: Process and Products

Phase Steel product category Steel products Steel sector end users ISO 14001 ISO 50001 Main production equipment Detailed production equipment
Main plant semi-finished; finished rolled[18] steel strands, billets, high-strength fasteners, corrosion-resistant hot-rolled coils, hot-rolled ribbed steel bars, hot-rolled round steel bars[18] automotive; building and infrastructure; energy; tools and machinery; transport[18] 2010-11-18 00:00:00[19][20] 2019-01-02 00:00:00[19][20] BF, BOF, EAF[21] 2 BOF(2x100-tonne); 2 EAF(1x105-tonne, 1x90-tonne)[22]
Closure semi-finished; finished rolled[18] steel strands, billets, high-strength fasteners, corrosion-resistant hot-rolled coils, hot-rolled ribbed steel bars, hot-rolled round steel bars[18] automotive; building and infrastructure; energy; tools and machinery; transport EAF[16] 1 EAF (1x70-tonne)[16]
Closure semi-finished; finished rolled[18] steel strands, billets, high-strength fasteners, corrosion-resistant hot-rolled coils, hot-rolled ribbed steel bars, hot-rolled round steel bars[18] automotive; building and infrastructure; energy; tools and machinery; transport EAF[16] 1 EAF (1x90-tonne)[16]
Expansion semi-finished; finished rolled[18] steel strands, billets, high-strength fasteners, corrosion-resistant hot-rolled coils, hot-rolled ribbed steel bars, hot-rolled round steel bars[18] automotive; building and infrastructure; energy; tools and machinery; transport EAF[16] 1 EAF (1x105-tonne)[16]
Expansion semi-finished; finished rolled[18] steel strands, billets, high-strength fasteners, corrosion-resistant hot-rolled coils, hot-rolled ribbed steel bars, hot-rolled round steel bars[18] automotive; building and infrastructure; energy; tools and machinery; transport EAF[16] 1 EAF (1x105-tonne)[16]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Basic oxygen furnace steelmaking capacity Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating 4620 TTPA[18][18] 4620 TTPA[18][18]
Closure retired 770 TTPA[16] 770 TTPA[16]
Closure operating pre-retirement 990 TTPA[16] 990 TTPA[16]
Expansion operating 788 TTPA[16] 788 TTPA[16]
Expansion construction 788 TTPA[16] 788 TTPA[16]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Blast furnace capacity Nominal iron capacity (total)
Main plant operating 2500 TTPA[23][23] 2500 TTPA[23][23]
Closure retired
Closure operating pre-retirement
Expansion operating
Expansion construction

Blast Furnace Details

Table 6: Blast Furnace Details

Unit name Status Announced date Construction date Start date Current size Current capacity (ttpa) Decarbonization technology Most recent relining
2 operating[22] unknown unknown 2013[24] 1080 m³[23] 1040[23] unknown 2020-09-02[25]
New 1 operating[22] unknown unknown 2020-11-05 00:00:00[26] 1700 m³[23] 1460[23] unknown unknown

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. mysteel (2018-11-01). "福建三宝钢铁有限公司炼铁产能置换方案_综合资讯". news.mysteel.com. Retrieved 2022-09-29.{{cite web}}: CS1 maint: url-status (link)
  2. "福建三宝钢铁有限公司". www.cslpc.org. 2021-7-13. Retrieved 2022-09-29. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  3. 福建三宝钢铁1700立方米高炉正式投产,新浪网,November 13, 2020
  4. 三宝钢铁举行高炉拆除仪式 拆除产能置换退出设备,三宝集团, September 16, 2021
  5. "福建三宝钢铁有限公司炼铁产能置换方案",世界金属导报,November 2, 2018
  6. 关于福建三宝钢铁有限公司变更产能置换方案的公告,福建省工业和信息化厅,July 16, 2021
  7. "三宝集团新1号电炉顺利竣工投产". finance.sina.com.cn. Retrieved 2023-07-06.
  8. "市工信局组织召开三宝钢铁炼钢产能置换项目投产前一致性核实会议". 漳州市工业和信息化局. 2024-03-09.
  9. 9.0 9.1 https://web.archive.org/web/20220110201931/https://www.qcc.com/firm/97a8032beef1585092261645412e051b.html. Archived from the original on 10 January 2022. {{cite web}}: Missing or empty |title= (help)
  10. https://web.archive.org/web/20220120131432/https://www.qcc.com/firm/8b39390deed756e1bf5b928cadf26867.html. Archived from the original on 20 January 2022. {{cite web}}: Missing or empty |title= (help)
  11. https://web.archive.org/web/20220204144708/https://www.qcc.com/firm/8b39390deed756e1bf5b928cadf26867.html. Archived from the original on 04 February 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  12. https://xunbiaobao.baidu.com/biddingDetail?id=db994c71f4c45d565e8c5677f56494d8f3c8c272&source=seoo. {{cite web}}: Missing or empty |title= (help)
  13. 13.0 13.1 13.2 13.3 https://finance.sina.com.cn/money/future/indu/2023-01-16/doc-imyakpnk9013817.shtml. {{cite web}}: Missing or empty |title= (help)
  14. 14.0 14.1 14.2 14.3 14.4 14.5 14.6 https://m.mysteel.com/21/0716/11/38C42D1BDDCCD930_abc.html. {{cite web}}: Missing or empty |title= (help)
  15. 15.0 15.1 15.2 15.3 https://web.archive.org/web/20231116203407/https://xunbiaobao.baidu.com/biddingDetail?id=db994c71f4c45d565e8c5677f56494d8f3c8c272&source=seo. Archived from the original on 16 November 2023. {{cite web}}: Missing or empty |title= (help)
  16. 16.00 16.01 16.02 16.03 16.04 16.05 16.06 16.07 16.08 16.09 16.10 16.11 16.12 16.13 16.14 16.15 16.16 http://bj.kjzxfw.com/zhengcexinxi/index/detail/_Yj0MN0AQ_T_N.html. {{cite web}}: Missing or empty |title= (help)
  17. 17.0 17.1 https://www.sohu.com/a/566855563_121076653. {{cite web}}: Missing or empty |title= (help)
  18. 18.00 18.01 18.02 18.03 18.04 18.05 18.06 18.07 18.08 18.09 18.10 18.11 18.12 18.13 18.14 https://web.archive.org/web/20220114135630/http://www.fj-sanbao.com/products. Archived from the original on 14 January 2022. {{cite web}}: Missing or empty |title= (help)
  19. 19.0 19.1 https://web.archive.org/web/20220121225919/http://fj-sanbao.com/products/certificate. Archived from the original on 21 January 2022. {{cite web}}: Missing or empty |title= (help)
  20. 20.0 20.1 https://web.archive.org/web/20240115062418/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E4%B8%89%E5%AE%9D%E9%9B%86%E5%9B%A2&fromIndex=true. Archived from the original on 15 January 2024. {{cite web}}: Missing or empty |title= (help)
  21. https://web.archive.org/web/20220207192044/https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml. Archived from the original on 07 February 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  22. 22.0 22.1 22.2 https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml;http://news.gqsoso.com/qihuo/202109/16127407.html. {{cite web}}: Missing or empty |title= (help)
  23. 23.0 23.1 23.2 23.3 23.4 23.5 23.6 23.7 https://news.mysteel.com/18/1101/14/FF6C5ECC4F8C47FD.html. {{cite web}}: Missing or empty |title= (help)
  24. https://web.archive.org/web/20230328022512/http://www.fj-sanbao.com/about/history. Archived from the original on 28 March 2023. {{cite web}}: Missing or empty |title= (help)
  25. https://web.archive.org/web/20230831185618/http://www.f139.cn/news/detail/7728462.html. Archived from the original on 31 August 2023. {{cite web}}: Missing or empty |title= (help)
  26. https://web.archive.org/web/20210411104103/https://finance.sina.com.cn/money/future/indu/2020-11-13/doc-iiznezxs1632609.shtml. Archived from the original on 11 April 2021. {{cite web}}: Missing or empty |title= (help)

Resources