Guangxi Wuzhou Jinhai Stainless Steel Co Ltd (广西梧州市金海不锈钢有限公司) is an electric arc furnace (EAF) steel plant operating in Wuzhou, Guangxi, China.

Location

The map below shows the exact location of the plant in Wuzhou, Guangxi, China:

Loading map...
  • Location: No.2 Fengying Road, Wuzhou City, Guangxi Zhuang Autonomous Region
  • Coordinates (WGS 84): 23.518229, 111.235509 (exact)

Background

The company is the core enterprise of Wuzhou City's Stainless Steel Products Recycling Industry Park and is one of the key projects undertaken by the Wuzhou City government as part of the Guangdong industrial transfer. The total investment for this project is 1.08 billion RMB, and the first-phase construction project with a steel refining capacity of 600,000 tons has been completed and put into operation. The main processes completed in the first-phase construction project include stainless steel smelting, continuous casting, hot rolling, pickling, and cold rolling. The second-phase construction project will expand stainless steel hot (cold) rolling strip production capacity and increase pipe production lines.[1] Currently, the production capacity has been expanded to 1.5 million tons.[2]

Plant Details

Table 1: General Plant Details

Plant status Start date Workforce size Power source
Operating[3] 2010[3] 587[4] Southern Power Grid North Bay Power Supply Bureau in Guangxi [5]

Table 2: Ownership and Parent Company Information

Parent company Parent company GEM ID Owner Owner company GEM ID
Guangdong Jinhai Brilliant Group Co Ltd [100.0%] E100000123261 [100%] Guangxi Wuzhou Jinhai Stainless Steel Co., Ltd.[3] E100000127026

Table 3: Process and Products

Steel product category Steel products ISO 14001 Main production equipment Detailed production equipment
finished rolled[6] stainless steel hot-rolled coil (strip), stainless steel cold-rolled strip[6] 2021-06-29 00:00:00[7] EAF[6][8] EAF unknown[9]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status* Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
operating 1500 TTPA[9][6] 1500 TTPA[9][6]

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. "广西梧州市金海不锈钢有限公司".{{cite web}}: CS1 maint: url-status (link)
  2. "这家电炉炼钢厂,产能扩大到150万吨!". 冶金信息装备网. 2022-11-16.
  3. 3.0 3.1 3.2 https://www.qcc.com/firm/d77c14a4354ee7487c3f6a72422ac6bc.html. {{cite web}}: Missing or empty |title= (help)
  4. https://web.archive.org/web/20240119081928/https://aiqicha.baidu.com/acount/accessrestriction. Archived from the original on 19 January 2024. {{cite web}}: Missing or empty |title= (help)
  5. http://www.wuzhou.gov.cn/zjwz/zwdt_1/bmdt/t14053066.shtml. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 6.2 6.3 6.4 https://web.archive.org/web/20220318112312/http://www.gxind.com/company/895/companyinfo.htm. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  7. ZHUANG
  8. http://192406.fm086.com/Synopsis. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 https://web.archive.org/web/20230911151641/https://mp.weixin.qq.com/s?__biz=MjM5NTAyNzUzNg==&mid=2649120519&idx=3&sn=7b08fc9e45274e93d566cf90fdd4218a&chksm=beec3038899bb92e3359605a8d9d2465ab5be7b2c6f3fbbafdd2dd75e8c7778edf1986311d4f&scene=27. Archived from the original on 11 September 2023. {{cite web}}: Missing or empty |title= (help)

Resources