Hbis Laoting Steel Co Ltd (河钢乐亭钢铁有限公司(唐钢新区), 唐钢新区) is a steel plant in Tangshan, Hebei, China that operates blast furnace (BF), basic oxygen furnace (BOF), and electric arc furnace (EAF) technology.
Location
The map below shows the exact location of the plant in Tangshan, Hebei, China:
Loading map...
{"type":"HYBRID","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"600px","height":"500px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"visitedicon":"","wmsoverlay":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"cluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","fullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.257823,"lon":119.033567,"icon":""}]}
- Location: Economic Development Zone, laoting Couty, Tangshan City, Hebei Province
- Coordinates (WGS 84): 39.257823, 119.033567 (exact)
Background
The company's Phase 1 project has been fully put into operation. The existing main production equipment and facilities include one mechanized raw material yard, two 360m² sintering machines, two 760m² belt-type pelletizing roasting machines, four 600t/d lime kilns, three 2922m³ blast furnaces, one 200t dephosphorization furnace, three 100-ton converters, two 200-ton converters, one 2050mm hot rolling production line, two high-speed wire production lines, one high bar production line, one medium bar production line, one structural steel production line, and related supporting facilities.
In December 2021, the company decided to implement the Phase 2 project in two parts. The first part involves the construction of one 3200 cubic meters blast furnace, one 230-ton converter, one 500 square meters belt-type sintering machine, two lime kilns, one dolomite kiln, and one 1580mm hot-rolled strip steel production line. The second part includes the construction of two 120-ton electric furnaces, two ESP hot-rolled production lines, two hot dip galvanizing production lines using thermal basic acid process, and one 1550mm cold-rolled production line.[1]
During the construction of the first part, environmental protection acceptance was conducted in three phases according to the construction progress. The first phase has been completed in April 2024, primarily including the construction of one lime kiln (Kiln No. 8) and its associated pre-kiln storage, the lime processing operations (comprising one desulfurizer production line, two finished product crushing lines, and three hydrated lime production lines), as well as a 1600 mm twin-stream slab caster and its supporting facilities.[2]
Low-emissions/green steelmaking
This steel plant is associated with a green steel project tracked in the Green Steel Tracker. Details about the project are included below.
Table 1: Green Steel Project Details
All references for the above data are available in the Green Steel Tracker.
|
Project 1
|
Project name
|
Paradigm project
|
Company
|
HBIS Group
|
Company has climate goals?
|
Yes
|
Location
|
Xuan Hua, Zhangjiakou, Hebei province, China
|
Project website
|
Site
|
Project scale
|
Full scale
|
Project status
|
Operating
|
Year to be online
|
2021
|
Technology to be used
|
NG-DRI to H-DRI
|
Technology details
|
Gas mixture composed by 30% of coke oven gas from existing integrated plant and 70% of hydrogen from external sources
|
Iron production capacity (million tonnes per year)
|
1
|
Steel production capacity (million tonnes per year)
|
Not stated
|
CO2 capture (million tonnes CO2 per year)
|
Not stated
|
Hydrogen generation capacity (MW)
|
Not applicable
|
Investment size (m USD)
|
Not stated
|
Actual start year
|
2023
|
Partners
|
Tenova
|
Date of announcement
|
2020-11-23
|
Plant Details
Table 2: General Plant Details
Start date
|
Workforce size
|
Power source
|
2020[3]
|
9607[4][5]
|
Rooftop Distributed Photovoltaic Power Generation[6]
|
Table 3: Ownership and Parent Company Information
State-owned entity status
|
Parent company
|
Parent company PermID
|
Parent company GEM ID
|
Owner
|
Owner company PermID
|
Owner company GEM ID
|
Partial
|
HBIS Co Ltd [69.1%]; HBIS Group Co Ltd [7.7%]; Hebei Province Jicai Lndustryl Equity Lnvestment Fund Co Ltd [7.0%]; China Everbright Group Ltd [6.5%]; Gansu Provincial State-owned Assets Investment Group Co Ltd [3.0%]; Tangshan City Development Group Co Ltd [2.9%]; Gansu Financial Holding Group Co Ltd [2.0%]; unknown [0.9%]; Gansu Highway Aviation Tourism Investment Group Co Ltd [0.8%]
|
unknown [69.1%]; 5000022648 [7.7%]; unknown [7.0%]; 5000038293 [6.5%]; 5000611771 [3.0%]; unknown [2.9%]; unknown [2.0%]; not applicable [0.9%]; unknown [0.8%]
|
E100000123542 [69.1%]; E100000124529 [7.7%]; E100000128826 [7.0%]; E100000128904 [6.5%]; E100000000189 [3.0%]; E100000124528 [2.9%]; E100000128905 [2.0%]; E100000132388 [0.9%]; E100000129075 [0.8%]
|
HBIS Laoting Steel Co Ltd [100%][7]
|
unknown
|
E100000123169 [100%]
|
Table 4: Process and Products
Table 5: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
1Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1
|
Basic oxygen furnace steelmaking capacity
|
Electric arc furnace steelmaking capacity
|
Nominal crude steel capacity (total)
|
announced
|
–
|
1800[9]
|
1800[9]
|
construction
|
2250[9]
|
–
|
2250[9]
|
operating
|
7450[10]
|
–
|
7450[10]
|
Table 6: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
Table 7: Upstream Products Production Capacities (thousand tonnes per annum)
Sinter
|
Coke
|
Pellets
|
5097[8]
|
NF
|
3706[8]
|
Table 8: Actual Plant-level Crude Steel Production by Year (thousand tonnes per annum)
Year
|
BOF production
|
EAF production
|
Other/unknown steel production
|
2019
|
unknown
|
unknown
|
unknown
|
2020
|
unknown
|
unknown
|
unknown
|
2021
|
unknown
|
unknown
|
unknown
|
2022
|
unknown[13]
|
–[13]
|
unknown[13]
|
2023
|
–
|
–
|
unknown
|
Table 9: Actual Plant-level Crude Iron Production by Year (thousand tonnes per annum)
Year
|
BF production
|
DRI production
|
Other/unknown iron production
|
2019
|
unknown
|
unknown
|
unknown
|
2020
|
unknown
|
unknown
|
unknown
|
2021
|
unknown
|
unknown
|
unknown
|
2022
|
unknown
|
–
|
unknown
|
2023
|
–
|
–
|
unknown
|
Unit Details
Table 10: Blast Furnace Details
Unit name
|
Status
|
Announced date
|
Construction date
|
Start date
|
Current size
|
Current capacity (ttpa)
|
Decarbonization technology
|
Most recent relining
|
BF 1
|
operating[14]
|
–
|
–
|
2020[14]
|
2922.0 m3[15][16]
|
2440[12]
|
unknown
|
2022-11-11[17]
|
BF 2
|
operating[18]
|
–
|
–
|
2020[18]
|
2922.0 m3[15][16]
|
2440[12][11]
|
unknown
|
–
|
BF 3
|
operating[19]
|
–
|
–
|
2021[19]
|
2922.0 m3[15][16]
|
2440[12][11]
|
unknown
|
–
|
unknown BF (1)
|
construction[9]
|
2021[9]
|
2022[9]
|
–
|
3200.0 m3[9]
|
2670[9]
|
unknown
|
–
|
Table 11: Electric Arc Furnace Details
Unit name
|
Status
|
Announced date
|
Current capacity (ttpa)
|
Current size (tonnes)
|
unknown EAF (1)
|
announced[9]
|
2021[9]
|
900[9]
|
120.0[9]
|
unknown EAF (2)
|
announced[9]
|
2021[9]
|
900[9]
|
120.0[9]
|
Table 12: Electric Arc Furnace Feedstock Details
Unit name
|
Scrap-based
|
% scrap
|
% DRI
|
% HBI
|
% sponge iron (unknown if DRI or HBI)
|
% basic/merchant pig iron
|
% granulated pig iron
|
% pig iron (unknown if basic/merchant or granulated
|
% other iron
|
unknown EAF (1)
|
yes[20]
|
>0[20]
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown EAF (2)
|
yes[20]
|
>0[20]
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown
|
unknown
|
Table 13: Basic Oxygen Furnace Details
Unit name
|
Status
|
Announced date
|
Construction date
|
Current capacity (ttpa)
|
Current size
|
unknown BOF (1)
|
operating[16]
|
–
|
–
|
1150[10]
|
100.0 tonnes[21]
|
unknown BOF (2)
|
operating[16]
|
–
|
–
|
1150[10]
|
100.0 tonnes[21]
|
unknown BOF (3)
|
operating[16]
|
–
|
–
|
1150[10]
|
100.0 tonnes[21]
|
unknown BOF (4)
|
operating[16]
|
–
|
–
|
2000[10]
|
200.0 tonnes[21]
|
unknown BOF (5)
|
operating[16]
|
–
|
–
|
2000[10]
|
200.0 tonnes[21]
|
unknown BOF (6)
|
construction[22][9]
|
2021[9]
|
2024[22]
|
2250[9]
|
230.0 tonnes[9]
|