Inner Mongolia Gas Pipeline Network

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Inner Mongolia Gas Pipeline Network 内蒙古输气管网 is a pipeline network with gas pipelines that are operating, in construction, and proposed in Inner Mongolia Autonomous Region, China.

Location

The network runs throughout the Inner Mongolia Autonomous Region in China.

Loading map...
内蒙古自治区十三五长输油气管道规划图.jpg

Network background

Inner Mongolia is the major gas production region in China. According to Inner Mongolia Autonomous Region's 14th Five-year-Plan on Oil and Gas Development, the supply of conventional gas, coal-to-gas, and coal-bed methane in 2025 will reach 39.38 billion cubic meters, and the demand in the autonomous region will be about 12 billion cubic meters. The rest will supply areas outside Inner Mongolia. The conventional natural gas supply mainly comes from Sulige, Daniudi and Dongsheng gas field in the Ordos Basin. 33 natural gas and coal-to-gas pipelines were added from 2016 to 2020, totalling 5057.8 kilometers. 90.97 billion cubic meters of gas were transferred every year during that period. The gas pipelines have reached 40 banners or counties. [1] The goal for the 14th Five-Year-Plan period, 2021-2025, is to reach 7909.9 kilometers of gas pipeline mileage, and cover more than 66% of its banners (equivalent to counties). [1]

内蒙古自治区油气管道现状图.jpg

“十三五”期间,全区新增天然气(煤制气)管道 33 条,区内里程 5057.8 公里,年输送能力909.7 亿立方米。管道气已覆盖 8 个盟市、40 个旗(县、区)。

“十四五”期间,常规天然气供应仍主要来自鄂尔多斯盆地苏里格气田、大牛地气田、东胜气田等。常规气、煤制气、煤层气 2025 年供应量约 393.8 亿立方米,自治区内需求量约120亿立方米,自治区天然气作为国内天然气供应资源外输省份,调出量约为 273.8 亿立方米。

到 2025 年,天然气年产量达到333 亿立方米,较“十三五”末增长 20.0%,原油年产量达到150 万吨,较“十三五”末增长 25.7%。 2.基础设施。到 2025 年,油气管网里程达到9649 公里,区内天然气管道纳入“全国一张网”,储气能力达到2.8 亿立方米,管道天然气覆盖 66%以上旗(县、区)。[1]

Network details

Angsu-Aolezhaoqi Gas Pipeline 昂素-敖勒召其输气管道[2] [3]

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 1.6 billion cubic meters per year[3]
  • Length: 52.5 kilometers[3]
  • Diameter:
  • Status: proposed[4]
  • Start year:
  • Cost: 158 million RMB[3]

Baotou-Linhe Gas Pipeline 包头-临河输气管道

包头-临河输气管道走向示意图.png

Baotou-Linhe Gas pipeline 包头-临河输气管线 is a construction natural gas pipeline in China.[5]

On October 25, 2021, the Baotou-Linhe gas pipeline project of the Western Natural Gas Company was officially approved by the Energy Bureau of Inner Mongolia Autonomous Region.[6]

In 2023, the project has completed its preliminary preparation stage and is ready for construction. The construction will start officially once the bidding process is finished. This project will be the first gas pipeline that can transport hydrogen in China.[7] According to the company, the percentage of hydrogen blended in the pipeline is 10%.[8]

As of March 10, 2023, the pipeline was the first domestic high-pressure long-distance natural gas pipeline mixed with green renewable energy --- green hydrogen production in China.[9]

The pipeline runs from the Changqing Gas Field near Baotou, Inner Mongolia, China, to Linhe, Ningxia, China.

Loading map...
  • Owner: 内蒙古西部天然气管道运行有限责任公司 Inner Mongolia West Natural Gas Pipeline Operation Co., Ltd.[6]
  • Parent company:
  • Capacity: 0.39 billion cubic meters per year[3]
  • Length: 258 kilometers[10]
  • Diameter:
  • Status: Construction[5]
  • Start year:
  • Cost: 811.6045 million yuan[10]

Chahar Right Front Banner–Huade Gas Pipeline 察右前旗-化德输气管道

Loading map...
  • Owner: 内蒙古西部天然气管道运行有限责任公司 Inner Mongolia West Natural Gas Pipeline Operation Co., Ltd.
  • Parent company:
  • Capacity: 1 billion cubic meters per year[3]
  • Length: 180 kilometers[3]
  • Diameter: 457 mm
  • Status: Proposed[11]
  • Start year:
  • Cost: 850 million RMB[3]

Changqing Gas Field-Mengxi Gas Pipeline 长蒙输气管道(长庆气田-蒙西)

Loading map...
  • Owner: 鄂托克旗长蒙天然气有限责任公司 Otog Qi Changmeng Ranqi Co., Ltd.
  • Parent company: 中国燃气控股有限公司 (65.00%); Inner Mongolia Erdos Investment Holding Group Co., Ltd. (35.00%)
  • Capacity: 0.8 billion cubic meters per year
  • Length: 300 kilometers
  • Diameter: 508 mm
  • Status: Operating
  • Start year: 2008
  • Cost:

Changqing Gas Field-Uxin Chemical Industry Park Gas Pipeline 长庆气田-乌审召化工园输气管道

Loading map...
  • Owner: 乌审中燃天然气有限公司 Wushen Zhongran Natural Gas Co., Ltd.
  • Parent company:
  • Capacity: 1 billion cubic meters per year
  • Length: 119.2 kilometers
  • Diameter: 406 mm
  • Status: Operating
  • Start year: 2007
  • Cost:

Changqing Gas Field-Wuhai-Linhe Gas Pipeline 长庆气田-乌海-临河输气管道

The pipeline runs from Changqing Gas Field, Jingbian County, Yulin City, Shaanxi, to Linhe District, Bayannur City, Inner Mongolia.[12]

Loading map...
  • Owner: 内蒙古西部天然气管道运行有限责任公司
  • Parent company: Ordos State Owned Assets Investment Holding Group Co., Ltd. (43.20%); China National Petroleum Corporation (42.00%); Baotou Shenyin Industry Group Co., Ltd. (10.00%); other (4.80%)
  • Capacity: 0.4 billion cubic meters per year
  • Length: 426 kilometers[12]
  • Diameter: 355.6 mm
  • Status: Operating
  • Start year: 2008
  • Cost:

Chayou Rear Banner-Chayou Middle Banner-Siziwang Banner Gas Pipeline 察右后旗-察右中旗-四子王旗输气管道

Loading map...
  • Owner: Inner Mongolia Shengneng Beitong Energy Co., Ltd.[13]
  • Parent company:
  • Capacity: 0.4 billion cubic meters per year[3]
  • Length: 151 kilometers[3]
  • Diameter: 219.1 mm[14]
  • Status: Proposed[14]
  • Start year: 2025(anticipated)[3]
  • Cost: 410.22426 million RMB[14]

Dadong Gas Pipeline 大东输气管道(大牛地-东胜)

Daniudi-Dongsheng gas pipeline starts at 59 gas collecting station in Daniudi gas field and ends up at Dongsheng District, Hohhot. The construction began in November 2016. The total investment was 447 million RMB[15]

Loading map...
  • Owner: 中国石油化工股份有限公司华北油气分公司
  • Parent company: China Petroleum & Chemical Co., Ltd. of North Branch (100.00%)
  • Capacity: 1 billion cubic meters per year[16]
  • Length: 108 kilometers[16]
  • Diameter: 711 mm
  • Status: Operating[17]
  • Start year: 2019[17]
  • Cost:

Dalu-Horinger Gas Pipeline 大和输气管道(大路-和林格尔)

The pipeline runs from Changqing Gas Field near Dalu Town, Jungar through Ordos, Inner Mongolia and Shengle Town, Horinger to Hohhot, Inner Mongolia.[18]

Loading map...
  • Owner: Inner Mongolia Xinsheng Natural Gas Pipeline Company (内蒙古新圣天然气管道有限公司)
  • Parent company:
  • Capacity: 0.48 bcm/year
  • Length: 166 km / 103.1 mi
  • Diameter:
  • Status: Operation
  • Start year: 2022
  • Cost:

Daniudi-Hangin Banner Gas Pipeline 大牛地-杭锦旗输气管道

Loading map...
  • Owner: 中国石化集团华北石油局有限公司
  • Parent company: China Petrochemical Corporation (100.00%)
  • Capacity: 0.2 billion cubic meters per year
  • Length: 138 kilometers
  • Diameter: 159 mm
  • Status: Operating
  • Start year: 2003
  • Cost:

Dongsheng-Hanggin Gas Pipeline 东胜-杭锦旗输气管道

Loading map...
  • Owner: 中国石化集团华北石油局有限公司
  • Parent company: China Petrochemical Corporation (100.00%)
  • Capacity: 0.1 billion cubic meters per year
  • Length: 61.5 kilometers
  • Diameter: 159 mm
  • Status: Operating
  • Start year: 2012
  • Cost:

Duolun County Gas Pipeline 多伦县供气管道

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 0.5 billion cubic meters per year[3]
  • Length: 33 kilometers[3]
  • Diameter:
  • Status: Proposed[3]
  • Start year: 2023[3]
  • Cost: 120 million RMB[3]

Fu'antun–Kailu–Naiman Gas Pipeline 福安屯-开鲁-奈曼输气管道

It is a proposed pipeline in Inner Mongolia, China.[19]

The proposed pipeline was discussed in the Inner Mongolia 14th Five-Year Plan, though no other details were available as of October 2021.[19]

Loading map...
  • Owner:
  • Parent company:
  • Capacity:
  • Length:
  • Diameter:
  • Status: Proposed[19]
  • Start year:
  • Cost:

Ganqika-Yilongyong Gas Pipeline 甘旗卡-义隆永输气管道

Loading map...
  • Owner: Inner Mongolia Menggaole Intelligent Energy Co., Ltd.[20]
  • Parent company: Inner Mongolia Menggaole Intelligent Energy Co., Ltd.[21]
  • Capacity: 1.2 billion cubic meters per year[3]
  • Length: 217 kilometers[3]
  • Diameter:
  • Status: Proposed[22]
  • Start year: 2023[3]
  • Cost: 770 million RMB[3]

Guyang-Bayan Obo (Baiyun Ebo) Gas Pipeline 固阳-白云鄂博输气管道

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 0.365 billion cubic meters per year[23]
  • Length: 125 kilometers[23]
  • Diameter: 457 mm[23]
  • Status: Proposed[23]
  • Start year: 2025[23]
  • Cost: 494 million RMB[23]

Hangjin Rear Banner–Urad Rear Banner Gas Pipeline 杭锦后旗-乌拉特后旗输气管道

Loading map...
  • Owner: Inner Mongolia Western Natural Gas Co., Ltd.[24]
  • Parent company: Ordos State Owned Assets Investment Holding Group Co., Ltd. [43.20%]; China National Petroleum Corporation [42.00%]; Baotou Shenyin Industry Group Co., Ltd. [10.00%]; Other [4.80%][25]
  • Capacity: 0.4 billion cubic meters per year[3]
  • Length: 50 kilometers[3]
  • Diameter:
  • Status: Proposed[26]
  • Start year: 2023[3]
  • Cost: 170 million RMB[3]

Hexigten BannerXilinhot Gas Pipeline 克什克腾旗-锡林浩特输气管道

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 0.2 billion cubic meters per year[3]
  • Length: 130 kilometers[3]
  • Diameter:
  • Status: Proposed[3]
  • Start year: 2024[3]
  • Cost: 760 million RMB[3]

Maladi-Shanghai Temple Gas Pipeline 玛拉迪-上海庙输气管道

Loading map...
  • Owner: 鄂托克前旗时鼎天然气经营有限责任公司
  • Parent company: Beijing Yuanjing Dingtai Investment Co., Ltd. (57.00%); Etuokeqian Shiding Natural Gas Operation Co., Ltd. (30.00%); Ningxia Shengyuan Natural Gas Pipeline Co., Ltd. (10.00%); other (3.00%)
  • Capacity: 0.9 billion cubic meters per year
  • Length: 167 kilometers
  • Diameter: 508 mm
  • Status: Operating
  • Start year: 2013
  • Cost:

Malian Lake-Zhongwei Gas Pipeline 马莲湖-中卫输气管道

Loading map...
  • Owner: 国家石油天然气管网集团有限公司西气东输分公司
  • Parent company: West To East Gas Transmission Branch of National Petroleum Pipeline Network Group Co., Ltd. (100.00%)
  • Capacity: 0.13 billion cubic meters per year
  • Length: 24.9 kilometers
  • Diameter:
  • Status: Operating
  • Start year: 2009
  • Cost:

Shuangsheng-Tongliao Gas Pipeline 双胜-通辽输气管道

Loading map...
  • Owner: 通辽市隆圣峰天然气有限公司
  • Parent company: Shuifa Energas Gas Co., Ltd. (51.00%); Tongliao Longshengfeng Natural Gas Co., Ltd. (49.00%)
  • Capacity: 0.5 billion cubic meters per year
  • Length: 183 kilometers
  • Diameter: 508 mm
  • Status: Operating
  • Start year: 2015
  • Cost:

Siziwang Banner-Wuchuan Gas Pipeline 四子王旗-武川输气管道

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 0.4 billion cubic meters per year[3]
  • Length: 60 kilometers[3]
  • Diameter:
  • Status: Proposed[3]
  • Start year: 2026(Anticipated)[3]
  • Cost: 190 million RMB[3]

Sumitu-Dongsheng-Junger Gas Pipeline 苏东准输气管道(苏米图-鄂尔多斯东胜-准格尔)

Loading map...
  • Owner: 内蒙古新圣天然气管道有限公司
  • Parent company: Inner Mongolia Xinsheng Investment Group Co., Ltd. (60.00%); Inner Mongolia Xinsheng Natural Gas Pipeline Co., Ltd. (40.00%)
  • Capacity: 0.47 billion cubic meters per year
  • Length: 370 kilometers
  • Diameter: 660 mm
  • Status: Operating
  • Start year: 2012
  • Cost:

Sumitu Erhetu Gacha-Ulan Town Gas Pipeline 苏米图额尔和图嘎查-乌兰镇输气管道

Loading map...
  • Owner: Etok Banner Hualun Gas Co., Ltd.[27]
  • Parent company:
  • Capacity: 0.5 billion cubic meters per year[3]
  • Length: 70 kilometers[3]
  • Diameter:
  • Status: Proposed[3]
  • Start year: 2024[3]
  • Cost: 180 million RMB[3]

Tongliao Horqin District–Chifeng Hexigten Banner Gas Pipeline 通辽科尔沁区-赤峰克什克腾旗输气管道

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 2 billion cubic meters per year[3]
  • Length: 450 kilometers[3]
  • Diameter:
  • Status: Proposed[3]
  • Start year: 2024[3]
  • Cost: 2.42 billion RMB[3]

Wuyuan-Urad Middle Banner Gas Pipeline 五原县-乌拉特中旗输气管道

Loading map...
  • Owner:
  • Parent company:
  • Capacity: 0.25 billion cubic meters per year[3]
  • Length: 70 kilometers[3]
  • Diameter:
  • Status: proposed[26]
  • Start year: 2024[3]
  • Cost: 280 million RMB[3]

Xiang Gendalai-Bayanhot Gas Pipeline 厢根达来-巴彦浩特输气管道

Loading map...
  • Owner: Alxa League City Gas Co., Ltd.[28]
  • Parent company:
  • Capacity: 0.1 billion cubic meters per year
  • Length: 60 kilometers[29]
  • Diameter: 273 mm
  • Status: Operating
  • Start year: 2010
  • Cost:

Linhe-Hanggin Gas Pipeline 临河-杭锦后旗长输管道工程

Linhe-Hanggin Gas Pipeline 临河-杭锦后旗长输管道工程 is an operating gas pipeline in Inner Mongolia, China.[30]The pipeline has 2 pressure regulating stations and 1 valve chamber. The pipeline can benefit 230,000 people in Hangjin Rear Banner.[30]

Loading map...
  • Owner: Bayan Nur Tengjie Gas Co., Ltd.[31]
  • Parent company:
  • Capacity:
  • Length: 27.6 km[30]
  • Diameter:
  • Status: Operating[30]
  • Start year: 2013[30]
  • Cost: 47 million RMB[30]
  • Financing:
  • Associated infrastructure:

Tongliao-Holingol Gas Pipeline 通辽—霍林郭勒天然气管道

The pipeline is a segment of the Changtu-Tongliao-Holingol Gas Pipeline. The Changtu-Tongliao-Holingol Gas Pipeline is the only long-distance and high-pressured gas pipeline in Eastern Inner Mongolia Region.[32] The pipeline's source is the Harbin-Shenyang Pipeline.[33] 51% stakes of the operating company, Tongliao Longshengfeng Natural Gas Co., Ltd, was purchased by Shuifa Energas Gas Co., Ltd.(水发派思燃气股份有限公司) in 2021.[34]

The pipeline runs from the Tongliao Economic and Technological Development Zone in Inner Mongolia, China to the Holingol Industrial Park in Holingol, Inner Mongolia, China.[35]

Loading map...
  • Operator: Tongliao Longshengfeng Natural Gas Co.( 通辽市隆圣峰天然气公司, Holingol Mintong Natural Gas Co. (霍林郭勒市岷通天然气有限公司)[36]
  • Parent Company:Shuifa Energas Gas Co., Ltd.(水发派思燃气股份有限公司)51% [34]
  • Current Capacity: 0.4 bcm/year[33][37]
  • Length: 308 kilometers / 191 miles[35]
  • Diameter:508 mm[35]
  • Status: Operating[34]
  • Start Year: 2020[34]
  • Cost:1.2 billion RMB[38]

Changqing-Huhhot Pipeline 长庆油田-呼和浩特输气管道

Changqing-Huhhot Pipeline also known as Shaanxi-Huhu Line (长庆油田-呼和浩特输气管道(陕呼线,长呼线)) is an operating gas pipeline in China.[39]The pipeline source is the Changqing Gas Field. Its diameter is 457 mm and a design pressure of 6.4MPa. The pipeline runs from Uxin Banner, Ordos City to Huhhot, Inner Mongolia, China.

Loading map...

Mainline: Shanhu Line & Changhu Line 陕呼线,长呼线

  • Operator: Inner Mongolia Western Natural Gas Co[40]
  • Parent Company: CNPC
  • Current capacity: 1.3 bcm/year
  • Proposed capacity:
  • Length: 314.14 mi / 506 km
  • Diameter:
  • Status: operating
  • Start Year: 2003

Changqing-Huhhot Parallel Pipeline 长呼复线

  • Operator: Inner Mongolia Western Natural Gas Co[41]
  • Parent Company: Ordos State Asset Investment Holding Group (鄂尔多斯市国有资产投资控股集团有限公司) 48%; CNPC 42%; Baotou Shenyin Industrial Group (包头市申银产业集团有限公司) 10%.
  • Current capacity: 6 bcm/year
  • Proposed capacity:
  • Length: 321.87 mi / 518 km
  • Diameter: 864 mm
  • Status: operating[42]
  • Start Year: 2012

Tongliao-Xing'an League Hydrogen-doped Gas Pipeline 通辽—兴安盟天然气掺氢长输管道

The project is a proposed gas pipeline in Inner Mongolia, China.[43]It also has the function of high-proportion hydrogen doping.[43]

The pipeline is proposed to run from Tongliao-Huolingol Gas Pipeline Lubei sub-transmission station to Xing'an League Economic Development Zone, passing through Keyouzhong Banner, Tuquan County and Keyouqian Banner.[43]

Loading map...
  • Operator:
  • Owner: Xing'an League Jitong Natural Gas Co., Ltd.[44]
  • Parent company:
  • Capacity: 1 bcm/y[43]
  • Length: 250 km[43]
  • Diameter: 400 mm[43]
  • Status: Proposed[44]
  • Start year:
  • Cost: 1800 million RMB[43]
  • Financing:
  • Associated infrastructure: Tongliao-Huolingol Gas Pipeline[43]

Ulanqab-Yanshan Petrochemical Hydrogen Pipeline 乌兰察布-燕山石化氢气管道

The project is a proposed hydrogen pipeline in China.[45]

The pipeline is part of the Wulanchabu 0.1 mtpa Wind-solar Hydrogen Production Integrated Demonstration Project. It includes wind-solar hybrid power generation, a hydrogen production capacity of 0.1 mtpa, and a 400-kilometre long-distance hydrogen transmission pipeline to supply hydrogen to the Beijing-Tianjin-Hebei refining and chemical market.[46]

The pipeline is proposed to run from Ulanqab, Inner Mongolia to Yanshan Petrochemical Company, Fangshan distrioct, Beijing.[45]

Loading map...
  • Operator:
  • Owner: Sinopec Xinxing Inner Mongolia Green Hydrogen New Energy Co., Ltd.[45]
  • Parent company:
  • Capacity: 0.1 mtpa[45]
  • Length: 400 km[45]
  • Diameter:
  • Status: Proposed[47]
  • Start year:
  • Cost:
  • Financing:
  • Associated infrastructure: Wulanchabu 0.1 mtpa Wind-solar Hydrogen Production Integrated Demonstration Project

Wuhai-Hohhot Hydrogen Pipeline 乌海至呼和浩特输氢管道

The project is a proposed hydrogen pipeline in Inner Mongolia, China.[48]

The pipeline, also known as the "Inner Mongolia Hydrogen Energy Corridor", transports the hydrogen produced by the Yellow River Group's hydrogen energy "production-storage-transportation-marketing" demonstration project in Wuhai City to Hohhot City through the large-scale clean energy base which is near the Yellow River in Inner Monglia. [48]

The pipeline is proposed to run from Qianlishan Industrial Park, Haibowan District, Wuhai to Hohhot,Inner Mongolia, China .[48]

Loading map...
  • Operator:
  • Owner: Wuhai Zhongtai Hydrogen Energy Technology Co., Ltd.(乌海中太氢能科技有限公司)[48]
  • Parent company:
  • Capacity:
  • Length: 500 km[48]
  • Diameter:
  • Status: Proposed[48]
  • Start year:
  • Cost: 200 million RMB[48]
  • Financing: 50 million RMB (Own capital), 150 million RMB (Bank loan)[48]
  • Associated infrastructure: Yellow River Group Hydrogen Energy "Manufacturing-Storage-Transport-Sale" Demonstration Project[48]



Gas pipeline name Gas pipeline name in Chinese Status Start Year Capacity Capacity Unit Length Length Unit Start location Start Municipality End location End Municipality
Chifeng Northeast loop gas pipeline 赤峰东北环线输气管道 operating 2022 0.34 bcm/y 30.30 km Yuanbaoshan District Chaoyang Chifeng Songshan Chifeng
Wuhai Industrial Zone gas pipeline 乌海低碳工业园区输气管道 operating 2022 0.20 bcm/y 17.50 km Otog Banner Ordos Hainan Wuhai
Zhuozi-Liangcheng gas pipeline 卓资-凉城输气管道 proposed 0.40 bcm/y 49.00 km Zhuozi Ulanqab Liangcheng Ulanqab
Changqing-Huhhot Parallel Pipeline and Shaan-Jing Gas Pipeline 4 connecting pipeline (Uxin Banner) 长呼复线(乌审旗)-陕京四线联络线 proposed 4.00 bcm/y 12.60 km Uxin Banner Ordos Uxin Banner Ordos
Changqing-Huhhot Parallel Pipeline and Shaan-Jing Gas Pipeline 4 connecting pipeline (Dalat Banner) 长呼复线(达拉特旗)-陕京四线联络线 proposed 4.00 bcm/y 17.70 km Dalat Banner Ordos Dalat Banner Ordos
Changqing-Huhhot Parallel Pipeline and Shaan-Jing Gas Pipeline 4 connecting pipeline (Saihan) 长呼复线(赛罕)-陕京四线联络线 proposed 4.00 bcm/y 11.00 km Saihan Huhhot Saihan Huhhot
Changqing-Huhhot Parallel Pipeline and Shaan-Jing Gas Pipeline 4 connecting pipeline (Jining) 呼张延管道(集宁)-陕京四线联络线 proposed 4.00 bcm/y 14.90 km Jining Ulanqab Ulanqab
Changqing-Huhhot Parallel Pipeline and Shaan-Dadong pipeline connecting pipeline 长呼复线—大东管道联络线 proposed 1.00 bcm/y 0.60 km Dongsheng Ordos Dongsheng Ordos
Changqing Gas Field-Wuhai-Linhe Gas Pipeline and Changqing Gas Field-Mengxi Gas Pipeline connecting pipeline 长乌临管道—长蒙线联络线 proposed 0.43 bcm/y 2.50 km Otog Banner Ordos Otog Banner Ordos
Maladi-Shanghai Temple pipeline--Aolezhaoqi gas pipeline 玛上线-敖勒召其输气管道 proposed 0.45 bcm/y 4.30 km Otog Front Banner Ordos Otog Front Banner Ordos
Shanghai Temple Economic Zone-Fine Chemical Industrial Park Gas Pipeline 上海庙经济开发区-精细化工业园输气管道 proposed 0.45 bcm/y 21.00 km Otog Front Banner Ordos Otog Banner Shanghai Temple Ordos
Beihongjing- Aolezhaoqi gas pipeline 北红井-敖勒召其输气管道 proposed 0.65 bcm/y 29.00 km Otog Front Banner Ordos Otog Front Banner Ordos

Articles and resources

References

  1. 1.0 1.1 1.2 "内蒙古自治区能源局印发《内蒙古自治区"十四五"油气发展规划》-中国质量新闻网". m.cqn.com.cn (in 中文(中国大陆)). 2022-03-23.{{cite web}}: CS1 maint: url-status (link)
  2. 鄂尔多斯市“十四五”能源综合发展规划 鄂尔多斯市人民政府, 2022/06/23
  3. 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.18 3.19 3.20 3.21 3.22 3.23 3.24 3.25 3.26 3.27 3.28 3.29 3.30 3.31 3.32 3.33 3.34 3.35 3.36 3.37 3.38 3.39 3.40 3.41 3.42 3.43 3.44 3.45 3.46 3.47 ""十四五"天然气管道工程重点项目表-内蒙古"十四五"油气发展规划" (PDF). nyj.nmg.gov.cn. 2-22-03. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  4. 鄂尔多斯市自然资源局关于昂敖长输管道建设项目用地预审与规划意见的批复, 鄂尔多斯市自然资源局, 2022-07-29
  5. 5.0 5.1 一线动态|国内首条掺氢高压输气管道工程二标段线路主体完工!, 中化华油建设集团, 2024-07-04
  6. 6.0 6.1 "西部天然气公司包头-临河输气管道工程获自治区能源局正式核准_鄂尔多斯市人民政府". www.ordos.gov.cn. Nov.2, 2021. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  7. 回眸2022·西部天然气公司十大事迹, 西部天然气, 2023/01/01
  8. 宝鸡钢管螺旋焊管掺氢比例达10% 中国化工报, 2023/3/8
  9. 总投资9.1亿!国内首条掺氢高压输气管道工程开工,搜狐网,2023-03-10
  10. 10.0 10.1 包头-临河输气管道工程环境影响评价公众参与第一次公示, Inner Mongolia West Natural Gas Co., Ltd., Aug. 18, 2021, accessed Aug. 23, 2021.
  11. 项目简介:内蒙古圣能北通能源有限公司察右前旗至化德县天然气输气管道建设工程项目, 采招帮, 2023-07-30
  12. 12.0 12.1 湖北特检院完成长乌临天然气管道干线第一阶段检验工作, 湖北省市场监督管理局, 2020/06/10
  13. 察右后旗至四子王旗天然气输气管道工程建设项目 社会稳定风险评估公示, 乌兰察布市人民政府, 2023-03-06
  14. 14.0 14.1 14.2 总投资41022.426万!乌兰察布中旗、四子王旗将建设天然气管道输配工程, 乌兰察布生活, 2023-03-07
  15. "鄂尔多斯市东胜区三大民生工程项目复工". inews.nmgnews.com.cn. 2017-04-01.{{cite web}}: CS1 maint: url-status (link)
  16. 16.0 16.1 大东天然气输气管道工程项目获得自治区能源局批复, 鄂尔多斯市人民政府, 2019/04/04
  17. 17.0 17.1 千折百回一路歌乘势而上展宏图-局、分公司 2019 年取得十大改革发展成果, 中国石化华北石油局, 2020/01/19
  18. 重磅!鄂尔多斯大路至呼和浩特和林格尔天然气管道实现省际干线联网!, Sohu, Jun. 17, 2017
  19. 19.0 19.1 19.2 "14th Five-Year Plan 内蒙古自治区国民经济和社会发展第十四个五年规划和2035年远景目标纲要" (PDF). Archived (PDF) from the original on 2021-10-08. Retrieved 2021-10-08.
  20. 库伦旗关于签订天然气管道工程项目, 库伦旗招商局, 2020-11-27
  21. 内蒙古蒙高乐智慧能源有限公司, QCC, Research date: 2023-07-28
  22. 关于市六届人大二次会议第112号建议的答复, 通辽市工业和信息化局, 2023-05-22
  23. 23.0 23.1 23.2 23.3 23.4 23.5 固阳-白云鄂博输气管道工程正式开工, 鄂尔多斯市国有资产管理局, 2024-07-18
  24. 凝心聚力 攻坚克难 砥砺前行 奋力推动高质量发展 团结共创公司新征程, 内蒙古西部天然气股份有限公司, 2021年2月23日
  25. 内蒙古西部天然气股份有限公司, QCC, Research date: 2023-07-28
  26. 26.0 26.1 今年我市将加快推进传统能源产业高效发展, 巴彦淖尔市政府门户网站, 2024-03-05
  27. 鄂尔多斯市自然资源局关于苏米图额尔和图嘎查至乌兰镇管道建设项目用地预审与规划意见的批复, 鄂尔多斯市自然资源局, 2022-07-15
  28. 关于印发《内蒙古自治区安监局2015年度安全生产行政执法工作计划》的通知, 内蒙古自治区应急管理厅, 2015-02-02
  29. ""内蒙古阿拉善左旗巴彦浩特城市总体规划(2015—2030)文本". als.gov.cn. 09-29-2015. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  30. 30.0 30.1 30.2 30.3 30.4 30.5 临河至杭后高压输气管道通气,黄河晚报, 2013-11-19
  31. 巴彦淖尔市天然气输配工程监理招标公告, 采招网,2011-05-03
  32. 水发燃气易主两年持续盈利 拟3亿收购两公司开拓城镇市场 国际能源网, 2021/12/08
  33. 33.0 33.1 《通辽市城市燃气专项规划》(2015-2030), 通辽市人民政府, 2018/02/02
  34. 34.0 34.1 34.2 34.3 水发派思燃气股份有限公司关于收购通辽市隆圣峰天然气有限公司等两家公司51%股权的补充公告 水发派思燃气股份有限公司, 2021/12/08
  35. 35.0 35.1 35.2 通辽-霍林郭勒天然气管道工程焊接工艺评定在管道学院焊接工程系顺利完成, Sohu, Sep. 11, 2019
  36. 通辽-霍林郭勒天然气管道工程贯通 China Petroleum Pipeline Engineering Co, 2019-11-13
  37. 岷通燃气310公里天然气管道项目 霍林郭勒市人民政府门户网站, 2018/07/05
  38. 通辽至霍林郭勒天然气长输管道项目今年将建成投产 国际燃气网, 2017/05/18
  39. "长庆油田-呼和浩特管道(陕呼线)". Infopetro. 11 March 2013. Retrieved 21 February 2020.{{cite web}}: CS1 maint: url-status (link)
  40. 【科学发展 成就辉煌】传输发展动力 提供清洁能源, inews.nmgnews.com, Oct. 12, 2016
  41. 【科学发展 成就辉煌】传输发展动力 提供清洁能源], inews.nmgnews.com, Oct. 12, 2016
  42. 内蒙古日报 (16 December 2012). "长—呼天然气管道复线全线通气 全长518公里途经3市9旗县区".
  43. 43.0 43.1 43.2 43.3 43.4 43.5 43.6 43.7 通辽—兴安盟天然气掺氢长输管道工程举行启动仪式, 兴安盟发展和改革委员会, 2023-05-22
  44. 44.0 44.1 关于通辽-兴安盟天然气长输管道工程项目社会稳定风险评估情况公示, 兴安盟吉通天然气有限公司, 2023-08-29
  45. 45.0 45.1 45.2 45.3 45.4 200亿!中石化拟建400公里输氢管道连接京蒙两地, 氢云链, 2022-11-30
  46. 内蒙古两绿氢项目获批, 现代煤化工, 2023-01-02
  47. 我市首条石化输氢管道项目正式纳入国家规划, 乌兰察布日报, 2023-04-19
  48. 48.0 48.1 48.2 48.3 48.4 48.5 48.6 48.7 48.8 年内投产!中石油500公里输氢管道项目新进展, 氢云链, 2023-02-20