JSPL Jharkhand steel plant
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
JSPL Jharkhand steel plant, also known as JSPL Patratu steel plant; JSPL Balkudra steel plant, is a blast furnace-basic oxygen furnace (BF-BOF) announced steel plant in Patratu, Jharkhand, India.
Location
The map below shows the exact location of the plant in Patratu, Jharkhand, India:
- Location: Jharkhand State Highway 2, Patratu, Jharkhand 829143, India
- Coordinates (WGS 84): 23.632991, 85.325308 (exact)
Background
In 2009, JSPL had begun land acquisition for setting up a greenfield steel plant of 6 mtpa capacity in two phases of 3 mtpa each. Phase I of the project was expected to become operational by 2012.[1] The JSPL Jharkhand steel plant began operating in 2012 under the Jindal Steel and Power Ltd group.[2] The plant contains a 1 million tonne per annum (MTPA) bar rod mill and a 0.6 MTPA wire rod mill.[3] The 0.6 mtpa wire rod mill and 0.6 mtpa bar mill were commissioned in 2010 and 2011, respectively. The steel plant was expected to be fully operational by 2015.[4] The completion of the project was delayed due to land acquisition issues.[5] The plant in 2017 had a finished steel capacity of 1.6 mtpa.[6]
In 2020, the JSPL group announced it was looking to set up a 2-2.5 million tonnes steel plant at the Jharkhand facility .[7] However, according to JSPL's environmental clearance report, which they submitted in 2021, this number has since risen to 6 million tonnes. The expansion will also contain a captive coal power plant.[8] JSPL announced they would be investing Rs 20,000 crore into the expansion.[3][9][10]
As of February 2022, it appears that no environmental damages or accidents have occurred at the JSPL Jharkhand steel plant.
There has been no developments reported on the project. As of September 2023, the plant is still being pursued.[11]
Plant Details
Table 1: General Plant Details
Plant status | Announced date | Start date | Power source |
---|---|---|---|
Announced[12] | 2007[13] | 2024[12] | 1320 MW captive power plant[14] |
Table 2: Ownership and Parent Company Information
Owner | Owner company PermID | Owner company GEM ID |
---|---|---|
Jindal Steel And Power Ltd[15] | 4295874065 | E100000153087 |
Table 3: Process and Products
Steel product category | Steel products | Main production equipment | Detailed production equipment |
---|---|---|---|
semi-finished[16] | wire rod; bar[16] | BF, BOF[17][13] | 1 BF (4019 m3); 2 BOF (200 tonnes each)[17][13] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Capacity operating status* | Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|
announced | 6000 TTPA[12][17][12][17] | 6000 TTPA[12][17][12][17] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|
announced | 3200 TTPA[18] | 3200 TTPA[18] |
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Sinter | Coke | Pellets |
---|---|---|
6000 TTPA[13] | 1900 TTPA[17] | 5000 TTPA[13] |
Blast Furnace Details
Table 7: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Furnace manufacturer and model | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|---|
unknown | announced[19] | 2007[13] | unknown | 2024[19] | Siemens VAI; MECON (Govt. of India) Siemens VAI Blast Furnace Design[20][21][20] | 4019 m³[17] | 3200[18] | unknown | unknown |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ "JSPL begins land acquisition for Jharkhand steel plant". www.projectstoday.com. Retrieved 2023-12-19.
- ↑ "History JSPL Jindal Steel Power India Raigarh Angul". Steel on the Net. Retrieved 2022-03-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 "JSPL to invest Rs 20K cr in Jharkhand: Jindal". The Economic Times. 2017-02-16. Retrieved 2022-03-01.
- ↑ MarketScreener (2011-09-28). "Jindal Steel & Power Limited : JSPL Jharkhand Steel Plant Dedicated to the Nation -September 28, 2011 at 06:45 pm IST | MarketScreener". in.marketscreener.com. Retrieved 2023-12-19.
- ↑ "Land issues delay JSPL, JSW plants in Jharkhand". DNA India. Retrieved 2023-12-19.
- ↑ "JSPL to invest Rs 20,000 crore in Jharkhand: Naveen Jindal". Business Today. 2017-02-16. Retrieved 2023-12-19.
- ↑ Roy, Shobha. "JSPL looking to set up 2-2.5 mtpa steel plant at Patratu in Jharkhand". Hindu Business Line. Retrieved 2022-03-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Compliance to Environmental Clearance" (PDF). Jindal Steel Power. 2021-05-21. Retrieved 2022-03-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ Standard, Business. "JSPL to invest Rs 20,000 cr in Jharkhand: Naveen Jindal". www.business-standard.com. Retrieved 2023-12-19.
{{cite web}}
:|first=
has generic name (help) - ↑ "JSPL to invest Rs 20,000 crore in Jharkhand: Naveen Jindal". Deccan Chronicle. 16 February, 2017. Retrieved 19 December, 2023.
{{cite web}}
: Check date values in:|access-date=
and|date=
(help)CS1 maint: url-status (link) - ↑ "Environmental Statement of plant for 2022-23" (PDF). 2023-09-5. Retrieved 2024-11-12.
{{cite web}}
: Check date values in:|date=
(help)CS1 maint: url-status (link) - ↑ 12.0 12.1 12.2 12.3 12.4 12.5 (PDF) https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2022.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 13.2 13.3 13.4 13.5 (PDF) https://web.archive.org/web/20211102191627/https://d2lptvt2jijg6f.cloudfront.net/jindalsteelpower/custom/1624357373_File%20no.%201.pdf. Archived from the original (PDF) on 02 November 2021.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ (PDF) https://d2lptvt2jijg6f.cloudfront.net/jindalsteelpower/custom/1647322687_File%20no.%202.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220111143857/https://www.jindalsteelpower.com/. Archived from the original on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 16.0 16.1 https://web.archive.org/web/20211102224116/https://www.jindalsteelpower.com/jharkhand.html. Archived from the original on 02 November 2021.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 17.0 17.1 17.2 17.3 17.4 17.5 17.6 17.7 https://web.archive.org/web/20240111025942/https://www.scribd.com/document/284912542/Jindal-Steel-Power-Limited. Archived from the original on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 18.0 18.1 18.2 (PDF) https://web.archive.org/web/20211102190449/https://d2lptvt2jijg6f.cloudfront.net/jindalsteelpower/custom/1629185554_FILE%20NO.1.pdf. Archived from the original (PDF) on 02 November 2021.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 19.0 19.1 (PDF) https://web.archive.org/web/20220111173338/https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2021.pdf. Archived from the original (PDF) on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 20.0 20.1 https://studylib.net/doc/5535054/design-features-of-indian-blast-furnaces.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220525172438/http://www.meconlimited.co.in/Metals/Iron_Making.aspx. Archived from the original on 25 May 2022.
{{cite web}}
: Missing or empty|title=
(help)